Sat morning Until 12:40: Loss maps at injection

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
Saturday ● 06:00: Physics fill from the night shift ● 15:00: End stable beam mode: – problems with incorporation of settings for the squeeze ● 16:40:
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
Week 13: R. Assmann, J. Wenninger
Ion Commissioning: Thursday & Friday
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
Wednesday 8.9 External crossing angles:
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Saturday 24 March 2012.
Wednesday 21 March 2012.
Monday :00 Stable beams 9_6_6_6 13:40 Access.
Friday 30th September 06:00 Operator dump fill #2171, int. lumi about 75 pb-1 Previous operator dump from physics was on 14 September ! 07:00 Start of.
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
MD2490: Measurement of the TMCI Threshold at Flat-Top
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Thursday morning – optics correction
Machine availability reaching well over 80%
Tuesday 23/11/10 8:00 Physics fill #1511 dumped
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
Monday – recovery from MKI flashover
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Thursday morning 09:30 Dump of pPb fill.
Summary of Week 16 G. Arduini, J. Wenninger
LHC Morning Meeting - G. Arduini
Saturday 2/4/ :00-09:00 Problems with SPS:
Week 36 plan Todo’s: And also: 12+b injection.
Friday March 4th 08h32: Access for beam dump system.
Week 35 – Technical Stop and Restart
Sunday morning Recovering from 400 kV disturbance.
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Planning at 5 o’clock meeting Friday
Friday morning 10:30 Optics measurements and corrections.
Thursday :00: Physics fill from the night shift
Saturday – Morning 7:36 beams dumped
Friday Morning 7:30 injection for fill 2908
Sunday
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Saturday 7th May Sat – Sun night
(on behalf of the LHC team)
Summary Thursday h21: Stable beams fill #1303.
Aims for the week Recover from technical stop and precycle at 10A/s
Thursday Physics fill 1250 (with 13b) dumped at 10.30
Thursday morning 08:45 Stable beams fill 2855 for ATLAS/CMS VdMs.
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Summary week 18 Intensity ramp up & production
Wednesday 13th 9:30 Stable Beams… with 1 pilot and 2 nominals
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Collimation qualification during the first weeks of the 2011 run
MD Planning Fri – Sat (1. – 2.7.)
Monday Fill 1803 into stable beams at 9:30. Dump at 19:45.
Saturday 12 March Morning: problem on RSD1.A12B2 – flow rate problem on the cooling water for the converter. 14:00: Loss map -500 Hz (positive energy offset)
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Tuesday In the morning test cycle with probe for Q’ measurement.
Saturday 06/11 Triplet R8 tripped during ramp for collision setup.
Wednesday h18: 228b fill lost just before start of ramp.
Tuesday – Morning and Evening
LHC Morning Meeting - G. Arduini
Another Immortal Fill….
Monday 10th December - morning
Saturday 28th 08:17 Fill #1812: Stable beams, peak luminosity ~1.1x1033 cm-2s-1 19:00 Go to adjust for RF-checks; Record fill lumi of 31.7 pb-1 for CMS.
Saturday 15th May One bunch 1 e11 per beam 09:57: start ramp
Friday During the night from Thursday to Friday: by mistake, SPS longitudinal blow-up was not active  Smaller transverse emittance from the.
Tuesday
Daniel, Gianluca and Belen (for the Collimator team)
Saturday Morning used to complete the loss maps and asynch dumps (with RPs). All loss maps OK (B. Salvachua), but the off-p cleaning for B1 (Lead) was.
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Sat morning Until 12:40: Loss maps at injection Analysis of high losses in IR6 for B1H: Showed that TCSG.4R6.B1 set up too tight Repeat of IR6 TCSG collimation setup at injection Results:                  center          beam size ratio TCSG.4R6.B1      +0.150         99% TCSG.4L6.B2      -0.318          94% previous alignment from 2012.03.21                  center          beam size ratio TCSG.4R6.B1      +0.110          92% TCSG.4L6.B2      -0.185           94% 5/10/2019 LHC 8:30 meeting

B1H loss map – IR6  20% leakage 5/10/2019 LHC 8:30 meeting

TCSG.4R6.B1 out  less than1% leakage 5/10/2019 LHC 8:30 meeting

Sat afternoon Some time lost with PS and SPS problems (POPS, dump kicker, …). 17:20 Ramp 2 nominal bunches Some problems to see tune  chirp B2 Sudden lifetime drop in B2 some time after end of squeeze (as seen before) 18:45 Collimator (TCT) setup at end of squeeze Beam not very stable, complicating setup Finally all achieved 21:36 TCT setup completed: 2012 Collimation Setup done! 22:04 Setting up for RP alignment  collision 22:51 Dump Attempt to open the limits of XRPV.A6L5.B2 via the menu button "Set Thresholds to HW limits" which is incorrectly configured, such that it sets the outer limits inside the RP home position. Thus the RP sitting at HOME violated the outer limit and caused the dump. 5/10/2019 LHC 8:30 meeting

Intensity 5/10/2019 LHC 8:30 meeting

Lifetime drop after end of squeeze 5/10/2019 LHC 8:30 meeting

Beam Stability Issues in beam stability: For the squeeze we turned on the chirp for B2, and squeezed without problem, but just after the squeeze (FBs still on) we again had significant losses for B2, after the tune peak on B2H jump to a 2nd peak. the resulting instability caused losses and only stabilized with reduced intensity and minor coupling trims. ( this was exactly like the fill of yesterday afternoon). Note that we checked chrom and bunch length evolution and all seemed OK. During the setup, it was observed that the 2nd bunch of B1 (bucket 17851) was blown up by in the transverse by at least a factor 3. We stablized losses by adding a few units of chroma. We also optomised the coupling to try to improve the spectra. 5/10/2019 LHC 8:30 meeting

TCT Setup and Issues All completed! Horizontal TCTs proved much more difficult, since the background was noisy and spikes not caused by the collimator movement, of the same order of magnitude as the spikes we were looking for, were often showing up and making it hard to see if the jaws were touching the beam or not. Often one step caused a clear spike, but then the next few steps didn't cause any losses. Could this be caused by off-momentum halo and spurious dispersion? In particluar, TCTH.4R5.B2 took a long time to setup and showed in the end a beam size ratio of 79%. The effective beta beat at this collimator should maybe be checked. Roderik, Gianluca, Luisella 5/10/2019 LHC 8:30 meeting

Saturday Night into Sunday morning Nice fill with 2 bunches into adjust mode. 3:23 Setting up collisions. Issues to find collisions in CMS. Joerg: “I found the problem : the lumi knob incorporation rule was not correct, it was propagating back constant and not decay-out, as a consequence the corrector settings are also constant, and they are 'eradicated' by a subsequent incorporation from the squeeze. Simple cure: We zero the lumi knob settings in the collision BP function (they have been zeroed anyhow at the lower level), Then we move back to the lumi knob settings of the start of this fill (or end of fill on friday) in the actual BP, and re-incoporate with the correct rule.” 6:11 Collisions found in IR5. Start of RP alignment. 5/10/2019 LHC 8:30 meeting

Fills Saturday until Sunday Minimal losses, no lifetime issue, no instability, … 5/10/2019 LHC 8:30 meeting

Today Sunday Continuing RP alignment? 12:00 Injection and dump work 20:00 BI setup with nominal bunches at 4 TeV 5/10/2019 LHC 8:30 meeting