CRYOMODULE FINAL ASSEMBLY

Slides:



Advertisements
Similar presentations
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Advertisements

ATD Assembly. ATD Assembly #1 Dewar Assembly #1 Status: Dewar has been completely assembled and vacuum tested. No vacuum leaks were detected on the outer.
AMS-02 Cryosystem Phase III Flight Safety Review January 12, 2010 Phil Mott.
February 17-18, 2010 R&D ERL Roberto Than R&D ERL Cryogenics Roberto Than February 17-18, 2010 CRYOGENICS.
Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009.
LINAC LASER NOTCHER READINESS REVIEW August 5 th, 2014 Kevin Duel – Mechanical Support Engineer.
CRYO PIPING & INTER-MODULE CONNECTIONS Yun He, Daniel Sabol, Joe Conway External Review of MLC Daniel Sabol, MLC External Review 10/3/2012.
FNAL-SCRF 会議報告 1. Cryomodule, Plug-compatible Interface ( 大 内) 2. High Pressure Code, 5K Shield (Tom Peterson)
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe MLC external review October 03, 2012.
Assembly, Installation and Interfaces Steve Virostek Lawrence Berkeley National Lab RFCC Module Design Review October 21, 2008.
SPL cryo-module conceptual design review Cavity, helium vessel and tuner assembly N. Valverde, G. Arnau, S. Atieh, I. Aviles, O. Capatina, M. Esposito,
Date Event Global Design Effort 1 Technical System Review John Noonan, ANL Yusuke Suetsugu,KEK Paolo Michelato, INFN Milano.
ESS cavities interfaces
Internal Cryomodule Instrumentation ERL Main Linac Cryomodule 10/10/2015 Peter Quigley, MLC Design Review.
24 January 2014 LARP VTF Follow-up Meeting P. Kovach VTF 1 LARP Vertical Test Facility Vertical Dewar Design, Magnet Prep And Installation Paul Kovach.
April, 2009 ERL SRF CRYO MODULES AND CRYOGENIC SYSTEM.
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
LCLS-II cryomodule alignment. 2 Wednesday meeting, 6/17/2015 Topics Alignment of Components inside the CM Tunnel Network Tolerances LCLS-II cryomodule.
FNAL Cavities for S1 Global Jim Kerby ALCPG 09. FNAL Deliverables Discussed in meetings 15/16 July and 10/11 Sept, and Webex and s 9/30/20092FNAL.
Mechanical Design of Main Linac Cryomodule (MLC) Yun He, Dan Sabol, Joe Conway On behalf of Matthias Liepe, Eric Smith, James Sears, Tim O’Connell, Ralf.
Date 2007/Oct./25 FNAL-GDE-Meeting Global Design Effort 1 Cryomodule Report N. Ohuchi KEK 1.Cryomodule & Cryogenics KOM 2.GDE-meeting discussion I.Interface.
Summary ( Cryomodule, Plug-compatible Interface) Norihito Ohuchi.
Date 2007/Oct./23 FNAL-GDE-Meeting Global Design Effort 1 Cryomodule Interface Definition (FNAL-GDE-Meeting) N. Ohuchi.
1 K.Jensch, D.Kostin, DESY - Cryomodule components List S1 – DESY parts DESY parts for the S1 Cavity-String.
56 Mhz Vacuum Mike Mapes Mhz Insulating Vacuum TURBO PUMP WITH GATE VALVE AND GAUGE SET MOUNTED ON TANK SIMILAR TO RHIC CRYOSTAT & VALVE.
Cryomodule prototype Yun He, Dan Sabol, Joe Conway On behalf of Matthias Liepe, Eric Smith, James Sears, Peter Quigley, Tim O’Connell, Ralf Eichhorn, Georg.
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe.
Check the component list with FNAL solid model Norihito Ohuchi 2009/8/251 19th Biweekly Webex meeting (S1-G, Cryomodule, Cryogenics)
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
Cryomodule Assembly Facility Fermilab Cleanroom: Assembly/Disassembly Tools Tug Arkan 1.
MICE Prototype Coupling Coil Cooling Circuit Design Dan Cheng Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
MICE Coupling Coil Fabrication Steps to Complete Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
Cryomodules Matthew Howell and Stephen Stewart Cryomodule Design Team Members.
Overview of elliptical cryomodules vacuum system Vacuum Equipment Standardization meeting February 2014 P. Bosland – C. Darve – N. Elias.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
Extra / Discussion Slides. 2 1.Helium Top Fill Port Add extra CF/ISO flange as collar so that the weld-region is not disturbed 2.Helium bottom FillCF.
1 IPN Orsay / Division Accélérateurs The Spoke cryomodule Vacuum aspects P. DUTHIL on behalf of the IPNO team ESS Lund February 19 th 2013.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
F LESEIGNEUR / G OLIVIER LUND January 9th, ESS HIGH BETA CRYOMODULE ESS CRYOMODULE STATUS MEETING HIGH BETA CRYOMODULE LUND JANUARY 9TH, 2013 Unité.
October 7, 2010 HINS Test Cryostat 2 K Conversion Status October 7, 2010.
Hongyu Bai LCLS-II 2 K Cold Box PDR September 27, 2016
Integration of the Spectrometer Solenoid Magnets
Mechanical and cryogenic configurations
CERN – Zanon discussions
T5.2: Harmonization - Material and Component Reference
Overview of Mechanical Design
LARP Vertical Test Facility
TTC Topical Workshop on SRF Cryomodule Clean Room Assembly
SHMS Downstream Beamline Large SHMS/HMS Angles (Config-1)
Teleconference ACS – FREIA 20th February 2018
IMP Cryomodule Assembly and Alignment
Alignment of Main Linac Cryomodule (MLC)
SNS PPU Cryomodule Instrumentation
Cryomodule Assembly Plan
CEPC-650MHz Cavity Cryomodule
PANDA The conceptual design of the control Dewar
SNS PPU Cryomodule End Cans
SNS PPU Cryomodule Thermal Shield
WP11: CDS-SL CDR Overview
SNS PPU Cryomodule Vacuum Vessel
SNS PPU Cryomodule Space Frame
SNS PPU Cryomodule Instrumentation
SNS PPU Cryomodule Space Frame
SNS PPU Cryomodule Thermal Shield & MLI
SNS PPU CRYOMODULE FDR Magnetic Shields Gary Cheng June 10, 2019.
SC1R Cold Box PDR Assembly Sequence
SNS PPU Cryomodule Design Overview
CRYOMODULE FINAL ASSEMBLY
SNS PPU CRYOMODULE PDR Cleanroom Assembly Katherine Wilson
Presentation transcript:

CRYOMODULE FINAL ASSEMBLY SNS PPU CRYOMODULE PDR CRYOMODULE FINAL ASSEMBLY Jim Henry Wednesday, February 27, 2019

OUTLINE THIS DISCUSSION WILL ADDRESS THE FINAL CRYOMODULE ASSEMBLY THE SPACEFRAME \ THERMAL SHIELD ASSEMBLY HAS BEEN INSTALLED, ALIGNED, AND LOCKED DOWN. THE END CANS HAVE BEEN FINAL ALIGNED AND INSTALLED. DESIGN REQUIREMENTS ARE THE SAME AS STATED FOR SIMILAR COMPONENTS

SUPPLY END FINAL ASSEMBLY STEP 1 BEAMLINE THERMAL INTERCEPT

SUPPLY END FINAL ASSEMBLY STEP 2 FLANGE \ COUPLER VALVE PRIMARY JT VALVE PRIMARY LHe SUPPLY SHIELD SUPPLY HP He FROM H/X HP He TO H/X

SUPPLY END FINAL ASSEMBLY STEP 3 THERMAL SHIELD EXTENSION

SUPPLY END FINAL ASSEMBLY STEP 4 OUTER MAGNETIC SHIELD EXTENSION

SUPPLY END FINAL ASSEMBLY STEP 5

SUPPLY BEAMPIPE INSTALLATION BEAMPIPE THERMAL INTERCEPT INSTALLED BELLOWS BRACE REMOVED THRU VACUUM TANK PORT O-RING SEAL BEAMPIPE TO VACUUM TANK END PLATE CF SEAL BEAMPIPE TO PUMP DROP

RETURN END FINAL ASSEMBLY STEP 1 BEAMLINE FLANGE THERMAL INTERCEPT

RETURN END FINAL ASSEMBLY STEP 2 PRIMARY 2K RETURN SURGE TANK HP He FROM H/X HP He TO H/X SHIELD RETURN

RETURN END FINAL ASSEMBLY STEP 3 THERMAL SHIELD EXTENSION

RETURN END FINAL ASSEMBLY STEP 4 OUTER MAGNETIC SHIELD EXTENSION

RETURN END FINAL ASSEMBLY STEP 5

RETURN BEAMPIPE INSTALLATION BEAMLINE THRERMAL INTERCEPT INSTALLED BELLOWS BRACE REMOVED THRU VACUUM TANK PORT O-RING SEAL BEAMPIPE TO VACUUM TANK END PLATE CF SEAL BEAMPIPE TO GATE VALVE

EXTERIOR ASSEMBLY INSTRUMENTATION PORTS INSULATING VACUUM GAGES ASME BURST DISC INSULATING VACUUM VALVE COUPLER OUTER CONDUCTOR COOLING RETURN PARALLEL PLATE VACUUM RELIEF (x2)

REMAINING TASKS ADJUST BEAMLINE THERMAL INTERCEPT TO SUIT AVAILABLE CLEARANCE DETAIL PIPING ASSEMBLIES FINALIZE SHEET METAL DESIGNS (THERMAL AND MAGNETIC) FINALIZE BEAMPIPE TO VACUUM TANK INTERFACES CHECK PRESSURE, FLEXIBILITY, AND SHIPPING DESIGNS CREATE DESIGN DRAWINGS CREATE SOW’S AS NEEDED

Jim Henry QUESTIONS? CRYOMODULE FINAL ASSEMBLY