Commercial Arrangements For Gas Quality Service – Introduction

Slides:



Advertisements
Similar presentations
Funding UKLink Process changes (User Pays). 2 Purpose of Presentation  Review of User Pays  Principles  Application to date  National Grid NTS observations.
Advertisements

NTS Exit (Flat) Capacity Charges – Credit Arrangements (UNC TPD V3.3.4) Simon Trivella – 14 th January 2009 Distribution Workstream.
RIIO-T1 impact on allowed revenues and network charges 6 September 2012.
Review of industry code governance 26 March 2010.
Commercial Arrangements For Gas Quality Service – Process UNC Transmission Workstream 23 rd April 2007.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
A regulatory framework for gas quality treatment facilities: recap and update.
UNC Modification Proposal Revised Timescales for LDZ Shrinkage Arrangements Simon Trivella – 25 th September 2008 Distribution Workstream.
Long Term Entry Capacity & User Commitment Transmission Workstream 7 th August 2008.
Operating Margins. 2 Competitive Provision of Operating Margins Change to National Grid Gas’s Transporter Licence which:  Introduced Special Condition.
The economic regulation of gas processing services Key issues and initial thoughts Ofgem presentation 18 June 2007.
Moving the QSEC and AMSEC Auctions National Grid NTS, Transmission Workstream.
Entry Capacity Release Methodology Statement Transmission Workstream, 4 th May 2006.
SO Incentives from April 2010 John Perkins. 2 Gas System Operator (SO) Incentives National Grid operates the high pressure Gas Transmission System in.
Ofgem’s Gas SCR – Background on the DSR mechanism Stephen Jarvis 02/07/14.
Mod 0333: Update of default System Marginal Prices Review Group August 2010 Transmission Workstream 07/10/2010.
Discretionary Release of Non Obligated NTS System Entry Capacity Transmission Workstream 1st May 2008.
Delivering Connections and Capacity RIIO-T1 and associated commercial changes - Summary June 7th 2012.
Gas Emergency Arrangements Proposal Transmission Workstream 5 th April 2007.
Governance and Charging Methodology for User Pays Services 10 th January 2007.
Update on Entry Capacity Substitution Transmission Workstream 6 th March 2008 Summary of consultation responses.
Exit Capacity Substitution and Revision Transmission Workstream meeting, 3 rd December 2009.
Open letter on Development of the regime ahead of winter 2007/8 Nienke Hendriks Head of Gas Transmission Policy, Enforcement and Compliance 28 June 2007.
UNC Modification Proposal 0229 Guidelines document.
Code Governance Review UNC Modification Proposals Beverley Viney - National Grid NTS.
Supply Assumptions for Investment Planning Transmission Planning Code Workshop 1 3rd April 2008.
Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th March 2009.
Facilitating Release of Non-obligated Entry Capacity Draft – for discussion purposes only 22 November 2007.
Demand Side Investment Planning Transmission Planning Code Workshop 2 1 st May 2008.
Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.
Industry Dialogue on xoserve Services 14 th September 2007.
Development Modification Proposal: Introduction of an Inter-day Linepack Product Review Group August 2010 Transmission Workstream 07/10/2010.
Stuart Forrest, Network Planning Manager, Scotia Gas Networks 19 th October 2010 MOD Review of Industry Charging & Contractual Arrangements in Relation.
Presentation at REEEP Regulatory Forum, 28 September 2004
Transmission Workstream 6 January 2011
Transitional Exit Capacity Proposals -Update
Entry Capacity Overrun price calculation
Review Group 291- Ofgem Update
Review of UNC Section Q “Emergencies”
Code Governance Review UNC Modification Proposals
Transmission Planning Code
Transmission Workgroup 4th October 2012
Introduction of Code Contingency Guidelines Document
Transmission Workstream 4th July 2007
SO Incentives from April 2010
UNC Trader User – Licence obligations
NG Strawman – Ofgem response
Discussion on Mod262 and next steps
0291 – NTS Licence Special Condition 27 – Balancing Arrangements
Exit Capacity Substitution and Revision
The Necessary Criteria for a UNC Modification Proposal
Consideration of issues raised by UNC Modification Proposal 0244
Development of Entry Capacity Substitution
Transmission Planning Code Review
Modification 501 slides for Workgroup
Introduction of Code Contingency Guidelines Document
Review Group 291- Ofgem Update
Proposed Transitional Gas Exit Arrangements
Transmission Workstream 2nd December 2010
Richard Fairholme Transmission Workstream 4th September 2008
Consideration of issues raised by UNC Modification Proposal 0244
Entry Overrun Calculation
Options for the Development of a Demand Side Response Mechanism
Open Letter - Summary of Responses
CAM: Next Steps UNC Transmission Workgroup Lisa Martin 9 January 2014.
195AV “Future work” – system flexibility
Dis 1208: Mod The ability and requirement for Users and Transporters to raise issues to be considered by the Allocation of Unidentified Gas Expert.
Modification 0621 / GB Charging Project DSC Change Management Committee update June 2018.
Capacity Access Review
Presentation transcript:

Commercial Arrangements For Gas Quality Service – Introduction UNC Transmission Workstream 23rd April 2007

Background In October 2006 Ofgem established two industry workstreams to consider: how likely it was that the gas flowing to GB in the future would be of a quality that was outside of that allowed to flow onto the British network; and the most appropriate regulatory treatment for any gas processing facility required to treat gas to ensure that it is within the GB specifications. Ofgem published the conclusions from the workstreams on the 30 January 2007.

Scenarios Workstream Output Great deal of uncertainty on the need for a gas processing facility.

Economic Regulation Workstream Output

Work in Progress “Ofgem to initiate a process of consultation on the changes to NGG's gas transporters licence necessary to support the proposed approach and for NGG, or others, to raise any required modifications to the Uniform Network Code.”

Assumptions NGG will carry out feasibility studies only after being approached by an interested party. The feasibility study will be paid for by the interested party. NGG will offer services to the market via an open season process based on information from the feasibility study. The UNC Modification proposal will be developed on the basis of the hybrid 2 model i.e. the plant is built based on User commitment and NGG has an opportunity to build above User signal GS(M)R limits are unlikely to be amended before 2020.

Proposed Way Forward on UNC Modification Many elements of the potential service need to be developed with industry participants before a Modification Proposal can be raised e.g.: definition of the service ("gas quality product") registration mechanisms (how and when a UNC User can apply for the gas quality product) charging arrangements (what a UNC User would pay and when) liability arrangements (user's rights if purchased product not available) Our intention is therefore to begin this process today by suggesting a process & timeline for resolution of these issues and development of a UNC Modification Proposal. In addition we intend to begin to explore some of these issues today.