XRN November 2019 Release - Status Update

Slides:



Advertisements
Similar presentations
XRN4361 – UK Link Release 2 - Delivery
Advertisements

XRN4572 – UK Link Release 3 - Design
Overall Project RAG Status
Amendment Invoice Task Force Progress Report
Overall Project RAG Status
Overall Project RAG Status:
Amendment Invoice Task Force Progress Report
DSC Change Committee Summary – 13th June
Release 3 Update December 2018.
XRN4340 – UK Link Future Release 1.1
Amendment Invoice Task Force Progress Report
Overall Project RAG Status
Release 3 Update November 2018.
XRN4361 – UK Link Release 2 - Delivery
EUC Project Timelines Key Upcoming Dates:
XRN4361 – UK Link Release 2 - Delivery
Overall Project RAG Status
DSC Change Committee Summary – 9th May
XRN4361 – UK Link Release 2 - Delivery
Release 3 Update 9th January 2019.
Overall Project RAG Status:
xrn4340 – UK Link Future Release 1.1
Release 3 Update 13th February 2019.
Amendment Invoice Task Force Progress Report
Overall Project RAG Status:
XRN Nov 19 Release - Status Update
XRN Nov 19 Release - Status Update
June 19 Timelines Key Upcoming Dates:
4361 – UK Link Future Release 2
Release 3 Update 07th March 2018.
Change Management Committee – Retail & Networks Update
XRN4361 – UK Link Release 2 Project Status Update
Overall Project RAG Status
Amendment Invoice Task Force Progress Report
4361 – UK Link Future Release 2
4340 – UK Link Future Release 2
Overall Project RAG Status:
Overall Project RAG Status:
XRN4361 – UK Link Future Release 2
Overall Project RAG Status
XRN June 19 Release - Status Update
XRN Feb 19 Minor Release - Status Update
June 19 Timelines Key Upcoming Dates:
XRN4361 – UK Link Release 2 - Delivery
XRN Nov 19 Release - Status Update
Release 3 Update 07th March 2018.
XRN4361 – UK Link Release 2 - Delivery
XRN4361 – UK Link Release 2 - Delivery
Overall Project RAG Status:
4340 – UK Link Future Release 1.1
XRN Nov 19 Release - Status Update
UIG Task Force Progress Report
XRN June 19 Release - Status Update
UIG Task Force Progress Report
DSC ChMC Switching Programme Update 10th July 2019
XRN4361 – UK Link Release 2 - Delivery
XRN Nov 19 Release - Status Update
UIG Task Force Progress Report
XRN 4954 – MiR Drop 5 - Status Update
XRN 4927 – MiR Drop 4 - Status Update
Overall Project RAG Status:
XRN June 19 Release - Status Update
XRN June 19 Release - Status Update
XRN Nov 19 Release - Status Update
XRN4361 – UK Link Release 2 - Delivery
UIG Task Force Progress Report
UIG Task Force Progress Report
UIG Task Force Progress Report
UIG Task Force Progress Report
UIG Task Force Progress Report
Presentation transcript:

XRN4828 - November 2019 Release - Status Update 29th October 2018 Overall Project RAG Status: Schedule Risks and Issues Cost Resources RAG Status Status Justification Scope: Scope agreed at 12/12 ChMC. XRNs 4573, 4621, 4725 and 4679 confirmed. Solution Options: Outstanding question on which solution option will be required for XRN4753 Plan: Initial plan drafted. Detailed planning for Start-up and Initiation phases to follow Tendering: Suppliers engaged Funding: The project team are on track to raise the Business Case Environment and Resource Capacity – There is a risk that due to multiple deliveries running in parallel (June 19, GB Charging, CSSCC and EUC) that environment and resource constraints may become an issue from the Build phase onwards The BER is due to be drafted on receipt of supplier responses Weekly monitoring of SME resources supporting multiple demands (e.g. BAU defects, Future Releases etc) is ongoing

XRN4828 - November 2019 Release Timelines Key Milestone Dates: XRN4753 Solution Option to be confirmed – 9th Jan 19 6 Month Notice of November 8th Implementation – 08th May 19 8th May: 6 month notice of implementation