PIXEL Project Status John Arthur Photon Instrumentation for

Slides:



Advertisements
Similar presentations
Tom Fornek LUSI June 17, LUSI UPDATE – June, 2008.
Advertisements

Stefan Moeller XES FAC Review – April 16, 2006 X-Ray Endstation Systems (XES) Status Stefan Moeller.
John N. Galayda LCLS Facility Advisory November 11, LCLS Update November 11, 2008 Construction Status LCLS Instruments.
John Arthur X-ray November 11, 2008 SLAC National Accelerator Laboratory 1 X-ray Overview LCLS Directorate structure.
Richard M. Bionta XTOD October 12, 2004 UCRL-PRES-XXXXX X Ray Transport, Optics, and Diagnostics, Overview Facility Advisory Committee.
John Arthur LCLS September 26, 2005 John Arthur SLAC LCLS Construction and Science.
Stefan Moeller Revised XES April 7, 2005 Revised X-Ray Endstation Scope Stefan Moeller.
J. B. Hastings LUSI Overview LCLS FAC March 20, 2007 LUSI Overview J. B. Hastings January 2007 Lehman Review Response to Lehman Review.
J. B. Hastings LCLS User October 12-13, 2004 LCLS User Program J. Hastings SLAC/SSRL.
Diffraction studies of stimulated dynamics (pump-probe) Coherent-scattering studies of nanoscale fluctuations Atomic, molecular and optical science High.
LCLS Studies of Laser Initiated Dynamics Jorgen Larsson, David Reis, Thomas Tschentscher, and Kelly Gaffney provided LUSI management with preliminary Specifications.
John Arthur Photon Systems April 16, LCLS Photon Systems Status Technical status and accomplishments Response to.
John Arthur Photon October 29, Photon Systems Update FAC recommendations Current status New plan for Photon Systems.
John Arthur Photon October 27, Photon Systems Overview John Arthur SLAC.
John Arthur Photon April 20, 2006 Photon Systems Update John Arthur SLAC Photon Systems Manager.
John Arthur X-Ray Endstation April 29, 2004 X-Ray Endstations Overview John Arthur.
John Arthur PIXEL Project April 7, 2005 Status of the Proposed PIXEL Project John Arthur SSRL/SLAC Photon Instrumentation.
John Arthur Photon October 12, Photon Systems Update John Arthur SLAC 1.
LCLS Undulator Systems TDR Charge Linac Coherent Light Source Stanford Linear Accelerator Center Technical Review, March 3, 2004.
Stefan Moeller XES Plan for FAC Review - April 20, 2006 X-Ray Endstation Systems (XES) Status and Plan for FY06 Stefan Moeller.
24 April 2015 FY 2016 Budget Request to Congress for DOE’s Office of Science Dr. Patricia M. Dehmer Acting Director, Office of Science
Keith O. Hodgson SSRL Director Brief Update on the Linac Coherent Light Source - LCLS February 26, 2002 Basic Energy Sciences Advisory Committee Undulator.
W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 1 Project Management W. J. Foyt Project Scope Timeline Cost Estimate.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
Workshop Overview, Charge and Deliverables Joachim Stöhr.
LCLS-II Project Overview David Schultz LCLS-II Deputy Project Director March 19, 2012.
LCLS User Access Policy
MSc-Student Activities at the European XFEL
Hutch 4 (XCS) Laser System
Introduction to Synchrotron Radiation
X-ray Correlation Spectroscopy (WBS 1.4) Aymeric Robert
LUSI Coordination with LCLS
Experimental Facilities Planning
LCLS Instrument Development
Preparations for a Lehman Review
LCLS Ultrafast Science Instruments
X-ray Pump-Probe Instrument
LUSI X-ray Pump-Probe Instrument WBS 1.2
Linac Ops Budget Review LCLS Overview / Org Structure / Legacies
WBS 5.0 LCLS Strategic Projects Division
Development of LCLS Far Experimental Hall Hutches
LCLS History and Science Overview Keith Hodgson, SSRL Director April 23, 2002 LCLS DOE Review, April 23, 2002 Keith Hodgson, SSRL.
X-ray Pump-Probe Instrument
Thomas Fornek Project Manager July 15, 2009
LINAC OPS Budget Review
X-Ray Endstation Design & Management/Commissioning
X-Ray Transport, Optics, and Diagnostics WBS Alan J
X-ray Pump-Probe Instrument
X-Ray Endstations Update
Tom Fornek Project Manager April 20-22, 2009
LCLS User Access Policy
Project Management Issues John N. Galayda, SLAC April 24, 2002
Synchrotron Science and User Program at SSRL A Brief Overview for the Context of LCLS Presented to the DOE Review of the LCLS Project Keith O. Hodgson,
Optics John Arthur, SLAC & William W. Craig, LLNL April 24, 2002
Experimental Program and Endstations System (WBS ) J
John Arthur – LCLS Experimental Operations
NEH - Status Stefan Moeller.
The Transition to User Operations
Coherent X-ray Imaging Instrument WBS 1.3
Conventional Facilities Status
X-ray Correlation Spectroscopy Instrument
Linac Coherent Light Source Project Update
Linac Coherent Light Source Transition to Operations 11 July 2007
X-Ray Endstation Design & Management/Commissioning
LUSI Status and Early Science
X-Ray Endstation Systems (XES) 2006 Schedule
Welcome and Photon Science at SLAC – LCLS – SSRL – Science Initiatives
LCLS Instrument MIE Project: Staffing, Schedule
LCLS Photon Systems Overview
Presentation transcript:

PIXEL Project Status John Arthur Photon Instrumentation for X-ray Experiments at LCLS

Boundary conditions that define the PIXEL project LCLS construction schedule DOE funding profile LCLS science thrusts endorsed by SAC Organization of the PIXEL project Org chart Phased approach Straw man schedule

LCLS Construction Schedule NEH beneficial occupancy June 2007 FEH beneficial occupancy September 2007 First electrons through undulator December 2008 (maybe June) Begin LCLS operations phase April 2009

PIXEL possible funding profile $millions Total = $50M-$60M

The LCLS Science Thrust Areas Coherent scattering at the nanoscale (XPCS) Atomic, Molecular, and Optical Science Pump/probe diffraction dynamics Pump/probe high-energy-density (HED) science Nano-particle and single-molecule (non-periodic) imaging

BES approach to the Thrust Areas AMO science will be included in LCLS construction project HED science deemed to be outside the mission of BES

Proposed PIXEL Scope Build instruments that address the 3 remaining Thrust Areas within BES mission Include one additional instrument, for soft-x-ray coherent imaging of magnetic domains (also endorsed by SAC) Include HED Science if outside (non-BES) funding can be found

DOE BES project requirements Not a line-item in the DOE budget Can include construction funding and R&D funding Must build distinct instruments, separate from what LCLS builds All new rules for BES project management apply PIXEL will be what is called a “major item of equipment” (MIE)

PIXEL organization Keith Hodgson LCLS Science Teams Jerry Hastings SSRL Director PIXEL organization LCLS Science Teams Jerry Hastings SSRL Asst. Dir for LCLS Science John Arthur PIXEL Project Director TBD PIXEL Project Chief Engineer Budget ES&H PMCS Database Purchasing Administration Inst #1 Instrument Scientist Engineering & Development 4-5 Engineers 2-3 Designers Inst #2 Instrument Scientist Inst #3 Instrument Scientist Inst #4 Instrument Scientist

Why a phased approach is needed Each instrument costs $12M-$15M Funding profile provides ~$22M maximum by end of FY08 However, $50M-$60M can be expected by ~2012

What will $12M-$15M buy? Controls (including laser timing)+Computers Slits Flight path Valves/windows/pumps KB focusing system (1 µm and sub-µm options) X-ray pulse split+delay with table Crystal monochromator with table Diffractometer with table Optical table for laser Laser PPS Laser system (10 mJ Ti:sapphire plus OPA) Laser diagnostics X-ray diagnostics 2d detector Typical PIXEL “instrument” + PEOPLE

The phased approach Build two instruments in Phase 1, plus a prototype 2d detector Have Phase 1 close to completion by first light (summer 2008) Finish Phase 1 by April 2009 (begin LCLS operations phase) Roll Phase 1 science resources onto LCLS ops in 2009 Begin Phase 2 in 2009, hire additional scientists Phase 2 includes two instruments plus additional detectors Finish Phase 2 in 2012

Proposed Project Milestones CD0 (Statement of mission need, beginning of project) 6-05 CD1 (Completion of conceptual design) 6-06 CD2a (Baseline costs of Phase 1) 12-06 CD3a (Begin construction of Phase 1) 6-07 CD4a (Finish Phase 1) 4-09 CD4b (Finish Phase 2) 9-12

A Straw Man

Near Experimental Hall 2008-9 Soft X-ray Station AMO Physics (funded by LCLS) Hard X-ray Imaging Station Coherent imaging (funded by PIXEL) Extreme states of matter (funding?) Hard X-ray Diffraction Station Pump-probe dynamics (funded by PIXEL) XPCS (funded by PIXEL) Green applications do not have full capability, but can do preliminary experiments Far Experimental Hall

Near Experimental Hall by 2012 Soft X-ray Station AMO Physics Magnetic imaging Hard X-ray Imaging Station Coherent imaging Hard X-ray Diffraction Station Pump-probe dynamics Hard X-ray Diffraction Station XPCS Hard X-ray Station Extreme states of matter (assumes funding found) Far Experimental Hall

The funding profile constraints on the PIXEL project, along with the LCLS schedule, seem to indicate that a phased approach is needed Two instruments in Phase1, two in Phase2, along with a detector development program Funding for this project is lean, especially in the first years Strong support from the Science Teams will be needed Summary