LS1 BLM@LHC status 07/04/2014.

Slides:



Advertisements
Similar presentations
CSC upgrade for LS1 USA-15 rack: layout, construction and installation 11 th February 2013.
Advertisements

C. Fernández Bedoya, A. Navarro, I. Redondo. C. Fernández Bedoya November 29th, Goal: Replace SC crate with simple CuOF electronics and place TSC.
David Emschermann DCS Workshop – PI Heidelberg – 22/01/2007 How to power up the TRD David Emschermann Physikalisches Institut Universität Heidelberg updated.
WorldFIP optical repeaters 1 | status Feb 2013: 66 repeaters ordered to HLP; never delivered Feb 2014: HLP announced eminent closure Jun 2014: 40 of the.
INJECTORS BLM BI-TB on Proton Injector start-up. Summary of actions 2 BLM SystemComments LINAC2 8 movable detectors.
May Exp-Area meeting1 Safety Systems Installation status Flammable Gas Detection System Fire Detection System in SG8 ODH Detection System CO2 Detection.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
Tunnel Gallery Girders x ADC’s HV Power supply Rack channels digitizer VME module (SIS3300), 12 bits 96.
EN-CV interventions during YETS
BLM “sunglasses” Filter Box. Current layout: BLM crates CIBU units Rack BY02 / SR8 BIC crate ( UA83 ) User_Permits Maskable channel Unmaskable channel.
Beam Interlock System MPP Internal ReviewB. Puccio17-18 th June 2010.
8 June 2006A.Ciocio - SCTSG1 Status of Type IV Cables Cables production –resumed in February after 3 months stop –See ID week February ‘06 Delivery of.
LS1 status 6/06/2014. BLM re-installation ARC Sector 3-4 – in work, will be done to Sector 4-5 – from 30(23).06 – Sector for Cool.
March 12 th 2013 Muon LS1 operation meeting1 Muon LS1 Status Outline Recap of last week P1 weekly schedule Muon related activities Open issues and discussions.
Status of HO Installation Shashi Dugad Tata Institute of Fundamental Research India-CMS Collaboration Meeting, Chandigar April 2007.
Beam Instrumentation during LS1 Ray Veness on behalf of the BE/BI group.
MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters –Marshalling for all other quadrupole & dipole units –Houses.
1 hcal installation and commissioning status pawel de barbaro, vitali smirnov, june 11, 2007.
BLM System R2E and Availability Workshop, B.Dehning 1 Bernd Dehning CERN BE-BI
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
TRT HV System status and plans for LS1 LPI Moscow, K. Zhukov.
ELENA installation progress F. Butin / ELENA collaboration.
TOTEM Electronics Status
MICE RF System Power Supplies, Control and Monitoring Status report
Rack Design Proposal as of 01/03/2013
Micromegas Vertex Tracker Status Report
BE-BI Activities and Status: LHC and Injectors
MEMORANDUM Cabling and Electrical activities requests YETS 2017/2018
VELO-installation meeting CERN, January 17, 2006
BA6 – crab cavity activities in EYETS
Collaboration meeting 26 to 28 June 2017
Injectors BLM system: PS Ring installation at EYETS
T1 Electronic status Conclusions Electronics Cards:
Injection region BLMs – ECR
ELENA electron cooler and SEM grids status
SPS Planning for the EYETS Meeting 8 (07/12/2016)
Audit of the BLM LHC system
LHC BLM system: system overview
LPI Moscow, K. Zhukov, MEPhI-LPI Moscow, V. Kantserov
Authorizing Arcgis desktop licenses with license server administrator
Pierluigi Paolucci - I.N.F.N. Naples
Pierluigi Paolucci - I.N.F.N. Naples
Undulator System Installation
Key Dates-Odd Days April 26th-Lottery April 28th-Draft & Work Day
CSC Electronics Installation and Commissioning CSCE I&C
Combiner functionalities
ATLAS USA15 - Rack 52U with 9U crates, remote PS
TileCal ROD Commissioning Counting Room Installation
Trigger M&O Progress -- Florida, Rice, UCLA, Wisconsin
BLM planning 24/02/2014.
BLM planning 03/03/2014.
BLM changes HV software interlock (SIS)
LS1 status 28/04/2014.
Magnet PS Controls Hardware Status
LS1 status 24/03/2014.
BEAM LOSS MONITORS The BLM system Status of the monitors
07/07/2014 * status, all * AccTest framework
LS1 status 17/03/2014.
Report on Beam Loss Monitors
SPS 1 and 5 during W J.MEIGNAN EN-ACE-OSS 20/02/2019.
WA105: Order Status IFAE Thorsten Lux.
BLM planning 03/02/2014.
Saturday 2nd October BLM threshold follow-up - Bernd Dehning and Joerg Wenninger Following MPP approval, Bernd Dehning has increased the BLM thresholds.
Week 43 ( LHC only) Installation of BLECF in LSS 4L and LSS 4R (Adrien and Mounir) - Done Check and repairs of BLECF in LSS 4L and LSS 4R (Steve) -? Installation.
Needed for Team A on -End
SPS Injection BIS - Draft requirements
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

LS1 BLM@LHC status 07/04/2014

Surface racks P2 + corrected the configuration P4 + installed but p.s. should be below row 31 ( currently 34). + 4 extensions in hall of P4 Rack configuration: R L I C SR1|3|5|6 & SX4 Rack: BLMLHC BY01 Rack: BLMLHC BY02 Empty OPTICAL CABLE STORAGE OPTICAL CABLE SUPPORT 1   2 3 4 5 6 7 8 BOBR 9 10 11 12 13 14 15 BLECS D S C A R r c P U L e f t SN: 16 17 18 19 20 21 CFVM-SR1-BLML Fan VME SN: 71300130 CFVM-SR2-BLMC SN: 71300217 AIR DEFLECTOR I g h V CFVM-SR2-BLMR SN: 71300216 Rack Control HV Power Supply F A N BIC "UNMASKABLE" HCCIBUS-ID000xxx BIC "MASKABLE" Internet

BLM tunnel BLM re-installation: Sector 8-1: R8 done, L1 – not yet finish (20L1->33L1, 2-3 working days) Sector 1-2 : from 07.04 * Re-install BLM in open Ics ( sector 6-7 first) LSS Coating of rest of supports and brides outside of CERN, RAL3020 + schedule : the sample? 2nd Russian team – + 02/04 – 30/06 ; -3rd team 30/06(24/06?) – 30.09 (23.09) – the possible prolongation of Russian team: 30.09(23.09) – 12.12.2014 SEM->LIC New Installation HV divider Last, April 2014, BLM related schedule ( 2 pdf files)