BET403 Cost Engineering Individual Assignment & Group Report

Slides:



Advertisements
Similar presentations
CTC-275 Construction Methods
Advertisements

Taking off and ESTIMATING
Earthwork Operations & Equipments
E STIMATION 1 Excavation 2 lesson 5. E XCAVATION 2 Recap from excavation 1 Looking at site plans Desk top study Site Visit Unit pricing of excavation.
3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine.
Lecture 4 Excavating and Lifting
Lecture 7 Loading and Hauling
Initial Conditions of the Road Initial Conditions of the Road Initial Conditions of the Road.
Chapter 3 Measuring Excavation and Sitework
Measuring Sitework, Excavation, and Piling
Earthmoving Materials and Operations
Culverts – Installation Soil Steel Structures – No backfill.
Earthwork QTO Stage 1 Preconstruction Stage 2: Procurement
CE/ENVE 320 – Vadose Zone Hydrology/Soil Physics Spring 2004 Copyright © Markus Tuller and Dani Or Soil Bulk Density and Compaction Hillel, pp.
Pricing Excavation and Backfill
ESTIMATING EARTHWORK Prof Awad S. Hanna.
Lecture 3 Earthmoving Materials
CTC-375 Construction Methods
Earthwork: Use of Fine Grained & Granular Material.
Estimating Ahmed Elyamany, PhD, AVS. EARTHWORK AND EXCAVATION bank  Earth that is to be excavated is called bank measure. loose  Earth that is to be.
University of Palestine Industrial Engineering Department Materials And Construction Technology Chapter (2) Blocks And Stone works.
Sanitary Engineering Lecture 16
2013 Section Engineer’s Meeting.  Correct Type, Gauge, and Coating (Standard Drawings)  Based on Pipe Diameter, Fill Height & Soil pH  Obtain copy.
4. Phase Relations (Das, Chapter 3) Sections: All except 3.6
Calculations On completion of this unit the Learner should be able to demonstrate an understanding of: The formula used to calculate: Areas Volumes Ratios.
Areas and Volumes Introduction Faculty of Applied Engineering and Urban Planning Civil Engineering Department 2 nd Semester 2008/2009 Surveying.
Estimation 1 Lesson 4 - Excavation.
Lecture 2 Introduction to Earthmoving
Planning for Earthwork Construction
1. 2 Civil Engineering Practice Introduction Instructor: Dr. Attaullah Shah Lecture # 1 Department of Civil Engineering Swedish College of Engineering.
Soil and Earth Works Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lecture 3 - Week 2 2 nd Semester 2008/2009 UP Copyrights.
Procedures in Modern Road Construction I. Development of Ancient Roads 1. Great civilizations throughout history enhanced road building. 2. Cross-section.
Soil Compaction Topic I Topic I.
GEO-MECHANICS (CE2204) Engineering Properties of Soils
Hydraulics & Hydrology Review 1 Lecture3 Dr. Jawad Al-rifai.
ESTIMATING EARTHWORK DR. Nabil Dmaidi.
Soil And Rock General Soil Characteristics Trafficability – ability of soil to support weight of vehicles under repeated traffic –Controls traffic on unimproved.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Geotechnical Conditions Tom Joos Civil/Structural Engineer BNL Plant Engineering.
Resource Leveling Advantages/Applications of Resource Leveling 1. Maintain the lowest uniform number of employees to perform the work. 2. Establishing.
© Awad S. Hanna, PhD, P.E.1 Estimating and Scheduling CEE 492 Lecture 5 ESTIMATING EARTHWORK.
Sanitary Engineering Lecture 13
Riprap Installation Construction Inspection for Field Office Activities Will use Riprap Gradation and Riprap Subgrade Problems from Class Problem Section.
Sanitary Engineering Lecture 10 Revision
Minimum Price $100. Minimum Price $45 Minimum Price $40.
BY MOHANA.V CIVIL ENGINEERING FINAL YEAR - VII SEM.
Underground Pipelines Module #8 Prepared by Dr. Randy R. Rapp July 2005.
DETERMINATION OF FIELD DENSITY BY CORE CUTTER METHOD
Eps: Campus rainworks challenge
SHREE LABHUBHAI TRIVEDI INSTITUTE OF ENGINEERING AND TECHNOLOGY
Detailed planning for fish farm construction Once the site has been selected, then initiation of planning begins. There are two main related components.
EXERCISES Two water reservoirs are connected by a pipe 610m of 0.3m diameter, f’=0.038 and the flow produced by the difference in water surface elevations.
In the Name of Allah The Most Beneficent & Merciful
Ground improvement techniques
Supervised by Dr. Sami Hijjawi Prepared by Hamza Saifan
Soil Texture.
B.V.Patel Institute of Technology-Diploma studies
5. WEIGHT VOLUME RELATIONSHIPS
CONSTRUCTION METHODS & TECHNOLOGY
CONSTRUCTION METHODS & TECHNOLOGY
SAB 3122 CONSTRUCTION TECHNOLOGY AND ESTIMATING Excavation
Geotechnics 1 (BFC 21702) SOIL COMPACTION.
American Concrete Pipe Association Short Course School 2014
Investigation of pipeline failure
FBE05 – Mathematics and Statistics
Lecture 5 Dozer TSP-308 MPK Ferdinand Fassa.
ESTIMATING EARTHWORK Prof Awad S. Hanna.
Earth and Rock fill Dams
Rate Analysis Rate Analysis of Local Materials (Typical Example)
ESTIMATING EARTHWORK Prof Awad S. Hanna.
Presentation transcript:

BET403 Cost Engineering Individual Assignment & Group Report 2016 Lecture 4

Individual Assignment and Group Report BET403 Cost Engineering Individual Assignment and Group Report Prepare a tender submission for the following tender: Construction of a 24 km long 1200mm diameter concrete pipeline comprising 16 km from pumping station A to reservoir B and 8 km from B to an industrial consumer C. There is a continuous outcrop of rock from chainage 10 to 13 km TENDER closes at 1:00 pm (13:00) on Thursday 28 April 2016 Rock tip, 5km away Pumping station A Industrial consumer C Reservoir B A rock outcrop B C 10 13 16 24 2016 Lecture 4

Assumptions: 1200DN Class 6 concrete pipes H2 support class BET403 Cost Engineering Assumptions: 1200DN Class 6 concrete pipes H2 support class Average backfill height 2.5m Minimum trench width and clayey sand Rock excavation between chainage 10 and 13 consists of 15% hard rock and 85% medium to soft rock Provide for removal and dumping of excavated rock to tip 5 km away 2016 Lecture 4

Individual Assignment and Group Report BET403 Cost Engineering Individual Assignment and Group Report Task Time required (including Work Break-down Structure and Time/Location diagram) Group Material quantities and costing Individual 1 Labour requirements and costing Individual 2 Plant and equipment requirements and costing Individual 3 Development of project price Tender submission 2016 Lecture 4

BET403 Cost Engineering Group Report Individual Assignment 1: 1. Time required (including Work Break-down Structure and time/location diagram) 2. Materials quantities and costing* 3. Labour requirements and costing* 4. Plant and equipment requirements and costing* 5. Development of project price 6. Tender submission Individual Assignment 1: Materials quantities and costing Individual Assignment 2: Labour requirements and costing Individual Assignment 3: Plant and equipment requirements and costing * Individual Assignments 2016 Lecture 4

Remove and dump excavated rock Skills required Pipelaying team BET403 Cost Engineering Work required Excavate trench Lay pipe Testing Remove and dump excavated rock Skills required Pipelaying team 1 x foreman 3 x machine operators 5 x trades people 4 x labourers Testing team 2016 Lecture 4

BET403 Cost Engineering Notes 2016

Quantities Source: Humes Concrete pipe reference manual BET403 Cost Engineering Quantities Source: Humes Concrete pipe reference manual 2016

Given: Quantities BET403 Cost Engineering 1200DN Class 6 concrete pipes H2 support class Average backfill height 2.5m Minimum trench width and clayey sand Quantities Quantities ‘out’ - Excavation quantities Hard rock Medium to soft rock Clayey sand Quantities ‘back in’ Bedding quantities Haunch quantities Compacted ordinary fill quantities Backfill quantities Pipe Source: Humes Concrete pipe reference manual 2016

BET403 Cost Engineering Source: Humes Concrete pipe reference manual 2016

Effect of excavation and compaction BET403 Cost Engineering Effect of excavation and compaction Excavation: increased volume – bulking or swelling Compaction: decreased volume - shrinking One cubic excavated does not translate to one cubic loose or one cubic compacted 0.95 m3 compacted 1 m3 bank/ in-situ 1.25 m3 loose/ excavated Shrinking Bulking 2016

Bulking and shrinking Bank material: Loose material: BET403 Cost Engineering Bulking and shrinking Bank material: Soil that is in its natural, or in situ, state before disturbance Measured as bank cubic meters Loose material: Soil that has been disturbed and is no longer in its original state Measured as loose cubic meters Compacted material: Soil that has been compacted for use in construction projects Measured as compacted cubic meters Source: https://etd.auburn.edu/bitstream/handle/10415/3532/Crooks,%20Alexandria_MS%20Thesis_Spring%202013.pdf?sequence=2 2016

Bulking (Swell) Factor (%) BET403 Cost Engineering Shrink factor SF = (volume of in-situ material – volume of compacted material) volume of in-situ material Bulk factor BF = (volume of loose material – volume of in-situ material) Example: Bulking of excavated materials After excavation of 300 m3 clay the volume of loose clay material swells to 420 m3 in the dump Bulking factor = (420 – 300)/ 300 = 0.4 = 40% Material In-situ Density 103 (kg/m3) Bulking (Swell) Factor (%) Clay 1,800 – 2,600 20 - 40 Granite 2,600 – 2,800 75 - 80 Sand, dry 1,600 20 - 30 Sand, wet 1,950 Sandstone 2,100 – 2,400 Soil 1,200 – 1,600 Source: http://www.engineeringtoolbox.com/soil-rock-bulking-factor-d_1557.html 2016

LE > LP Excavated volume = LE x d x w BET403 Cost Engineering LP Plan A w A LE > LP d LE Elevation B B B A A Excavated volume = LE x d x w B 2016