PERT/Activity Diagrams, Completion Probability and the Z Score

Slides:



Advertisements
Similar presentations
Chapter 9: Probabilistic Scheduling Models
Advertisements

Chapter 7 Project Management
Project Management - Part 2
Terminology Project: Combination of activities that have to be carried out in a certain order Activity: Anything that uses up time and resources CPM: „Critical.
1 Topics to cover in 2 nd part ( to p2). 2 Chapter 8 - Project Management Chapter Topics ( to p3)
pert and cpm ch 9 Learning objectives:
Other Scheduling Methods Dr. Ayham Jaaron Chapter 11.
Spring 2008, King Saud University PERT Dr. Khalid Al-Gahtani 1 Activity Duration 1.“Guess” the activity duration, especially smaller activities. 2.Use.
In the name of Allah the Most Gracious the Most Merciful.
McGraw-Hill/Irwin © 2006 The McGraw-Hill Companies, Inc., All Rights Reserved. 1 Chapter 3 part 2 Project Management.
LINE DIAGRAMS Learning objectives After this lecture you will be able to: Prepare and use line diagrams Demonstrate the effect that making activities ‘continuous’
Assuming normally distributed data! Naïve Bayes Classifier.
Topics: Inferential Statistics
Variability Measures of spread of scores range: highest - lowest standard deviation: average difference from mean variance: average squared difference.
As with averages, researchers need to transform data into a form conducive to interpretation, comparisons, and statistical analysis measures of dispersion.
SEEM 3530 Program Evaluation and Review Technique
Prepared by: Michael Palazzo
Chapter 4 SUMMARIZING SCORES WITH MEASURES OF VARIABILITY.
MATHEMATICS 3 Operational Analysis Štefan Berežný Applied informatics Košice
Prosjektstyring bma ACTIVITY A B C D E A 4 / 5 / 6 B 8 / 10 / 13 C 9 / 12 / 16 D 7.
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
PERT Program Evaluation and Review Technique Tong Wang 511D ERB.
Describing Behavior Chapter 4. Data Analysis Two basic types  Descriptive Summarizes and describes the nature and properties of the data  Inferential.
Chapter 7 PERT Project Management for Business, Engineering, and Technology.
PROJECT MANAGEMENT Approaches
1 3. M ODELING U NCERTAINTY IN C ONSTRUCTION Objective: To develop an understanding of the impact of uncertainty on the performance of a project, and to.
3 common measures of dispersion or variability Range Range Variance Variance Standard Deviation Standard Deviation.
Chapter 3: Averages and Variation Section 2: Measures of Dispersion.
3 - 1 Course Title: Production and Operations Management Course Code: MGT 362 Course Book: Operations Management 10 th Edition. By Jay Heizer & Barry Render.
Measures of variability: understanding the complexity of natural phenomena.
PERT/Activity Diagrams, Completion Probability and the Z Score
Change management control Sources of Change  Project scope changes  Implementation of contingency plans  Improvement changes ISE Ch. 6 1.
© 2008 McGraw-Hill Higher Education The Statistical Imagination Chapter 8. Parameter Estimation Using Confidence Intervals.
RESEARCH & DATA ANALYSIS
CPM – Critical Path Method Can normal task times be reduced? Is there an increase in direct costs? Additional manpower Additional machines Overtime, etc…
Chapter 7 : Risk Management – part 2
© 2008 McGraw-Hill Higher Education The Statistical Imagination Chapter 5. Measuring Dispersion or Spread in a Distribution of Scores.
Standard Deviation. Two classes took a recent quiz. There were 10 students in each class, and each class had an average score of 81.5.
Project Crashing. c=6 e=9 b=6 a=7 f=8 g=5 d=4 Given the information below, what is the total additional cost to crash the project as much as possible?
Nonparametric tests: Tests without population parameters (means and standard deviations)
Project Management Concepts Gantt Chart – shows tasks as bars whose length indicates timing. PERT* chart (Network Diagram) – shows relationships between.
Prof.Dr. Ahmet R. Özdural – Class Notes_06 - KMU417 Project Planning and Organization – Fall Semester.
m/sampling_dist/index.html.
Unit 2 Time Management Prepared by: Prof. Seemaah Keddar.
PERT CPM assumes duration of activity is known with certainty.
Project Management – PTM721S
PERT/Activity Diagrams, Completion Probability and the Z Score
Project Management (專案管理)
Project Management Chapter Topics
Chapter 17 Project Management McGraw-Hill/Irwin
Chapter 6 Scheduling
The Normal Curve and Sampling Error
Statistics: The Z score and the normal distribution
PERT and CPM.
Statistical Inference
Project Management and scheduling
Project Planning & Scheduling

Probabilistic Time Estimates
Project Scheduling: networks, duration estimation, and critical path
Chapter 6 Scheduling
Chapter 3 Variability Variability – how scores differ from one another. Which set of scores has greater variability? Set 1: 8,9,5,2,1,3,1,9 Set 2: 3,4,3,5,4,6,2,3.
Range.
If the question asks: “Find the probability if...”
Uncertain activity duration (P14)
Uncertain activity duration (P14)
Chapter 6 Scheduling
Managing Risk Chapter 7.
Presentation transcript:

PERT/Activity Diagrams, Completion Probability and the Z Score Source: Bob Hugg, Thinking in Project Management Terms EECS811: IT/Software Project Management

Activity diagraming (CPM) Define the goal of the project and the tasks required to complete it Place tasks in a logical order and determine the critical path The critical path is the longest time path through the network of tasks EECS811: IT/Software Project Management

PERT So far, we considered models with “single time estimates” for activity durations (e.g., with the CPM) PERT requires three estimates for each activity Generate a set of duration estimates for each task An optimistic, a most likely, and a pessimistic Label as a, b, m, or as TO, TL, TP Most likely time (m): Activity duration under normal circumstances Optimistic time (a): Shortest time to complete the activity Pessimistic time (b): Worst possible time to complete the activity EECS811: IT/Software Project Management

Calculate PERT for each task TE = (TP + 4TL + TO)/6 Complete the above for all tasks The sum of duration of tasks on the critical path will determine the project duration EECS811: IT/Software Project Management

Calculate standard deviation and variance Standard deviation is the average deviation from the estimated time As a general rule: the higher the SD, the greater the amount of uncertainty) SD = (TP – TO)/6 Variance reflects the speared of a value over a normal distribution V = (SD)2 SD and V are very useful in determining the probability of a project meeting its desired completion time EECS811: IT/Software Project Management

What is standard deviation? The standard deviation provides some idea about the distribution of scores around the mean (average) The smaller the standard deviation, the more narrow the range between the lowest and highest scores The scores cluster closely to the average score EECS811: IT/Software Project Management

Sample table for the estimates EECS811: IT/Software Project Management

Consider the following tasks and activity diagram EECS811: IT/Software Project Management

Populate table with sample data EECS811: IT/Software Project Management

Table of estimates with start dates EECS811: IT/Software Project Management

Determine completion probability A wealth of information in the above table Critical tasks, non-critical tasks, best and worst estimates and the expected duration for each, SD and V values Calculate probability of project completion on a desired date S: the sum of all expected durations on the critical path V: the sum of all variances on the critical path D: Select a desired completion time Compute Z = (D-S)/ v Look up the value of Z (e.g., here) EECS811: IT/Software Project Management

An example What is the probability of completing the project in 15 days? Z = (D-S) / v = (15 – 15.51) / 2.51 = -0.51/1.59 Z = -.321 A corresponding probability value for Z is 37.7% There is 38% probability that the project will be completed within 15 days of the start day EECS811: IT/Software Project Management