Capacity and Constraint Management

Slides:



Advertisements
Similar presentations
Job Order Costing Chapter 4.
Advertisements

Flexible Budgets, Variances, and Management Control: II
Cost Behavior, Operating Leverage, and Profitability Analysis
CALENDAR.
The 5S numbers game..
Break Time Remaining 10:00.
The basics for simulations
A sample problem. The cash in bank account for J. B. Lindsay Co. at May 31 of the current year indicated a balance of $14, after both the cash receipts.
Introduction to Cost Behavior and Cost-Volume Relationships
PP Test Review Sections 6-1 to 6-6
MCQ Chapter 07.
© 2006 Prentice Hall, Inc.S7 – 1 Operations Management Supplement 7 – Capacity Planning © 2006 Prentice Hall, Inc. PowerPoint presentation to accompany.
Capacity Planning. How much long-range capacity is needed When more capacity is needed Where facilities should be located (location) How facilities should.
S7 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall Process Strategies ( process, repetitive, product) The objective of the process strategy.
PRODUCTION AND OPERATIONS MANAGEMENT
Capacity Planning For Products and Services
Capacity Planning For Products and Services
Chapter 5 Strategic Capacity Planning
Capacity and Constraint Management
Capacity and Constraint Management
© 2004 by Prentice Hall, Inc., Upper Saddle River, N.J S 7-1 Operations Management Capacity Planning Supplement 7.
Chapter 5 Capacity Planning For Products and Services
Managing Capacity Chapter 6.
Copyright © 2012, Elsevier Inc. All rights Reserved. 1 Chapter 7 Modeling Structure with Blocks.
MaK_Full ahead loaded 1 Alarm Page Directory (F11)
Slide R - 1 Copyright © 2009 Pearson Education, Inc. Publishing as Pearson Prentice Hall Active Learning Lecture Slides For use with Classroom Response.
Copyright © 2008 Pearson Addison-Wesley. All rights reserved. Chapter 10 A Monetary Intertemporal Model: Money, Prices, and Monetary Policy.
Static Equilibrium; Elasticity and Fracture
Clock will move after 1 minute
Product Costing in Service and Manufacturing Entities
Select a time to count down from the clock above
Process Strategies How to produce a product or provide a service that
Management Decision Making Management Decision Making Supplement – Break Even Analysis.
S7 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall S7 Capacity and Constraint Management PowerPoint presentation to accompany Heizer and.
Operations Management Capacity Planning Supplement 7
Operations Management Capacity Planning Supplement 7
Operations Management
Operations Management
PowerPoint presentation to accompany Heizer/Render - Principles of Operations Management, 5e, and Operations Management, 7e © 2004 by Prentice Hall, Inc.,
Capacity and Constraint Management
© 2008 Prentice Hall, Inc.S7 – 1 Operations Management Supplement 7 – Capacity Planning PowerPoint presentation to accompany Heizer/Render Principles of.
Capacity Planning Production Planning and Control.
S7 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall Process Strategies ( process, repetitive, product) The objective of the process strategy.
LSM733-PRODUCTION OPERATIONS MANAGEMENT By: OSMAN BIN SAIF LECTURE 29 1.
S7 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall S7 Capacity and Constraint Management PowerPoint presentation to accompany Heizer and.
© 2006 Prentice Hall, Inc.S7 – 1 Operations Management Capacity Planning © 2006 Prentice Hall, Inc.
S7 - 1© 2014 Pearson Education, Inc. Capacity and Constraint Management PowerPoint presentation to accompany Heizer and Render Operations Management, Eleventh.
S7 - 1 Course Title: Production and Operations Management Course Code: MGT 362 Course Book: Operations Management 10 th Edition. By Jay Heizer & Barry.
7 Capacity Planning PowerPoint presentation to accompany
S7 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall S7 Capacity and Constraint Management yl.
S7 - 1© 2014 Pearson Education Capacity Planning PowerPoint presentation to accompany Heizer and Render Operations Management, Global Edition, Eleventh.
© 2006 Prentice Hall, Inc.S7 – 1 Capacity Planning © 2006 Prentice Hall, Inc.
Capacity Planning Pertemuan 04
Chapter 7s Class 2.
S7 - 1 Course Title: Production and Operations Management Course Code: MGT 362 Course Book: Operations Management 10 th Edition. By Jay Heizer & Barry.
Suppl Capacity Planning Heizer and Render Principles of Operations Management, 8e PowerPoint slides by Jeff Heyl.
Operations Management Capacity Design
© 2008 Prentice Hall, Inc.S7 – 1 Operations Management Supplement 7 – Capacity Planning PowerPoint presentation to accompany Heizer/Render Principles of.
S7 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall S7 Capacity and Constraint Management PowerPoint presentation to accompany Heizer and.
© 2011 Pearson Education, Inc. publishing as Prentice Hall Break-Even Analysis  Technique for evaluating process and equipment alternatives  Objective.
S7 - 1 Course Title: Production and Operations Management Course Code: MGT 362 Course Book: Operations Management 10 th Edition. By Jay Heizer & Barry.
© 2006 Prentice Hall, Inc.S7 – 1 Operations Management Supplement 7 – Capacity Planning © 2006 Prentice Hall, Inc. PowerPoint presentation to accompany.
S7 - 1 Capacity Planning PowerPoint presentation to accompany Heizer and Render Operations Management, Global Edition, Eleventh Edition Principles of Operations.
© 2008 Prentice Hall, Inc.S7 – 1 Operations Management Supplement 7 – Capacity Planning PowerPoint presentation to accompany Heizer/Render Principles of.
7 3 Capacity Planning PowerPoint presentation to accompany
Capacity and Constraint Management
Operations Management
Operations Management Capacity Design
Operations Management
Presentation transcript:

Capacity and Constraint Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint slides by Jeff Heyl © 2011 Pearson Education, Inc. publishing as Prentice Hall

Outline Capacity Design and Effective Capacity Capacity and Strategy Capacity Considerations Managing Demand Demand and Capacity Management in the Service Sector © 2011 Pearson Education, Inc. publishing as Prentice Hall

Outline – Continued Bottleneck Analysis and Theory of Constraints Process Times for Stations, Systems, and Cycles Theory of Constraints Bottleneck Management Break-Even Analysis Single-Product Case Multiproduct Case © 2011 Pearson Education, Inc. publishing as Prentice Hall

Outline – Continued Reducing Risk with Incremental Changes Applying Expected Monetary Value to Capacity Decisions Applying Investment Analysis to Strategy-Driven Investments Investment, Variable Cost, and Cash Flow Net Present Value © 2011 Pearson Education, Inc. publishing as Prentice Hall

Learning Objectives When you complete this supplement, you should be able to: Define capacity Determine design capacity, effective capacity, and utilization Perform bottleneck analysis Compute break-even analysis © 2011 Pearson Education, Inc. publishing as Prentice Hall

Learning Objectives When you complete this supplement, you should be able to: Determine the expected monetary value of a capacity decision Compute net present value © 2011 Pearson Education, Inc. publishing as Prentice Hall

Process Strategies The objective of a process strategy is to build a production process that meets customer requirements and product specifications within cost and other managerial constraints © 2011 Pearson Education, Inc. publishing as Prentice Hall

Capacity The throughput, or the number of units a facility can hold, receive, store, or produce in a period of time Determines fixed costs Determines if demand will be satisfied Three time horizons This slide provides some reasons that capacity is an issue. The following slides guide a discussion of capacity. © 2011 Pearson Education, Inc. publishing as Prentice Hall

Planning Over a Time Horizon Modify capacity Use capacity Intermediate-range planning Subcontract Add personnel Add equipment Build or use inventory Add shifts Short-range planning Schedule jobs Schedule personnel Allocate machinery * Long-range planning Add facilities Add long lead time equipment * Difficult to adjust capacity as limited options exist Options for Adjusting Capacity Figure S7.1 © 2011 Pearson Education, Inc. publishing as Prentice Hall

Design and Effective Capacity Design capacity is the maximum theoretical output of a system Normally expressed as a rate Effective capacity is the capacity a firm expects to achieve given current operating constraints Often lower than design capacity This slide can be used to frame a discussion of capacity. Points to be made might include: - capacity definition and measurement is necessary if we are to develop a production schedule - while a process may have “maximum” capacity, many factors prevent us from achieving that capacity on a continuous basis. Students should be asked to suggest factors which might prevent one from achieving maximum capacity. © 2011 Pearson Education, Inc. publishing as Prentice Hall

Utilization and Efficiency Utilization is the percent of design capacity achieved Utilization = Actual output/Design capacity Efficiency is the percent of effective capacity achieved Efficiency = Actual output/Effective capacity © 2011 Pearson Education, Inc. publishing as Prentice Hall

Bakery Example Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 - 8 hour shifts Design capacity = (7 x 3 x 8) x (1,200) = 201,600 rolls It might be useful at this point to discuss typical equipment utilization rates for different process strategies if you have not done so before. © 2011 Pearson Education, Inc. publishing as Prentice Hall

Bakery Example Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 - 8 hour shifts Design capacity = (7 x 3 x 8) x (1,200) = 201,600 rolls It might be useful at this point to discuss typical equipment utilization rates for different process strategies if you have not done so before. © 2011 Pearson Education, Inc. publishing as Prentice Hall

Bakery Example Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 - 8 hour shifts Design capacity = (7 x 3 x 8) x (1,200) = 201,600 rolls It might be useful at this point to discuss typical equipment utilization rates for different process strategies if you have not done so before. Utilization = 148,000/201,600 = 73.4% © 2011 Pearson Education, Inc. publishing as Prentice Hall

Bakery Example Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 - 8 hour shifts Design capacity = (7 x 3 x 8) x (1,200) = 201,600 rolls It might be useful at this point to discuss typical equipment utilization rates for different process strategies if you have not done so before. Utilization = 148,000/201,600 = 73.4% © 2011 Pearson Education, Inc. publishing as Prentice Hall

Bakery Example Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 - 8 hour shifts Design capacity = (7 x 3 x 8) x (1,200) = 201,600 rolls It might be useful at this point to discuss typical equipment utilization rates for different process strategies if you have not done so before. Utilization = 148,000/201,600 = 73.4% Efficiency = 148,000/175,000 = 84.6% © 2011 Pearson Education, Inc. publishing as Prentice Hall

Bakery Example Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 - 8 hour shifts Design capacity = (7 x 3 x 8) x (1,200) = 201,600 rolls It might be useful at this point to discuss typical equipment utilization rates for different process strategies if you have not done so before. Utilization = 148,000/201,600 = 73.4% Efficiency = 148,000/175,000 = 84.6% © 2011 Pearson Education, Inc. publishing as Prentice Hall

Bakery Example Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 - 8 hour shifts Efficiency = 84.6% Efficiency of new line = 75% Expected Output = (Effective Capacity)(Efficiency) It might be useful at this point to discuss typical equipment utilization rates for different process strategies if you have not done so before. = (175,000)(.75) = 131,250 rolls © 2011 Pearson Education, Inc. publishing as Prentice Hall

Bakery Example Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 - 8 hour shifts Efficiency = 84.6% Efficiency of new line = 75% Expected Output = (Effective Capacity)(Efficiency) It might be useful at this point to discuss typical equipment utilization rates for different process strategies if you have not done so before. = (175,000)(.75) = 131,250 rolls © 2011 Pearson Education, Inc. publishing as Prentice Hall

Capacity and Strategy Capacity decisions impact all 10 decisions of operations management as well as other functional areas of the organization Capacity decisions must be integrated into the organization’s mission and strategy You might point out to students that this slide links capacity to work measurement (standard times). © 2011 Pearson Education, Inc. publishing as Prentice Hall

Capacity Considerations Forecast demand accurately Understand the technology and capacity increments Find the optimum operating level (volume) Build for change © 2011 Pearson Education, Inc. publishing as Prentice Hall

Economies and Diseconomies of Scale Number of Rooms 25 50 75 (dollars per room per night) Average unit cost 25 - room roadside motel 75 - room roadside motel 50 - room roadside motel Economies of scale Diseconomies of scale Figure S7.2 © 2011 Pearson Education, Inc. publishing as Prentice Hall

Managing Demand Demand exceeds capacity Capacity exceeds demand Curtail demand by raising prices, scheduling longer lead time Long term solution is to increase capacity Capacity exceeds demand Stimulate market Product changes Adjusting to seasonal demands Produce products with complementary demand patterns © 2011 Pearson Education, Inc. publishing as Prentice Hall

Complementary Demand Patterns 4,000 – 3,000 – 2,000 – 1,000 – J F M A M J J A S O N D J F M A M J J A S O N D J Sales in units Time (months) Jet ski engine sales Figure S7.3 © 2011 Pearson Education, Inc. publishing as Prentice Hall

Complementary Demand Patterns 4,000 – 3,000 – 2,000 – 1,000 – J F M A M J J A S O N D J F M A M J J A S O N D J Sales in units Time (months) Snowmobile motor sales Jet ski engine sales Figure S7.3 © 2011 Pearson Education, Inc. publishing as Prentice Hall

Complementary Demand Patterns Combining both demand patterns reduces the variation 4,000 – 3,000 – 2,000 – 1,000 – J F M A M J J A S O N D J F M A M J J A S O N D J Sales in units Time (months) Snowmobile motor sales Jet ski engine sales Figure S7.3 © 2011 Pearson Education, Inc. publishing as Prentice Hall

Tactics for Matching Capacity to Demand Making staffing changes Adjusting equipment Purchasing additional machinery Selling or leasing out existing equipment Improving processes to increase throughput Redesigning products to facilitate more throughput Adding process flexibility to meet changing product preferences Closing facilities © 2011 Pearson Education, Inc. publishing as Prentice Hall

Demand and Capacity Management in the Service Sector Demand management Appointment, reservations, FCFS rule Capacity management Full time, temporary, part-time staff © 2011 Pearson Education, Inc. publishing as Prentice Hall

Bottleneck Analysis and Theory of Constraints Each work area can have its own unique capacity Capacity analysis determines the throughput capacity of workstations in a system A bottleneck is a limiting factor or constraint A bottleneck has the lowest effective capacity in a system © 2011 Pearson Education, Inc. publishing as Prentice Hall

Process Times for Stations, Systems, and Cycles The process time of a station is the time to produce a unit at that single workstation The process time of a system is the time of the longest process in the system … the bottleneck The process cycle time is the time it takes for a product to go through the production process with no waiting These two might be quite different! © 2011 Pearson Education, Inc. publishing as Prentice Hall

A Three-Station Assembly Line 2 min/unit 4 min/unit 3 min/unit A B C Figure S7.4 © 2011 Pearson Education, Inc. publishing as Prentice Hall

Process Times for Stations, Systems, and Cycles The system process time is the process time of the bottleneck after dividing by the number of parallel operations The system capacity is the inverse of the system process time The process cycle time is the total time through the longest path in the system © 2011 Pearson Education, Inc. publishing as Prentice Hall

Capacity Analysis Two identical sandwich lines Lines have two workers and three operations All completed sandwiches are wrapped Wrap 37.5 sec/sandwich Order 30 sec/sandwich Bread Fill Toast 15 sec/sandwich 20 sec/sandwich 40 sec/sandwich © 2011 Pearson Education, Inc. publishing as Prentice Hall

Capacity Analysis Wrap 37.5 sec Order 30 sec Bread Fill Toast 15 sec 20 sec 40 sec Toast work station has the longest processing time – 40 seconds The two lines each deliver a sandwich every 40 seconds so the process time of the combined lines is 40/2 = 20 seconds At 37.5 seconds, wrapping and delivery has the longest processing time and is the bottleneck Capacity per hour is 3,600 seconds/37.5 seconds/sandwich = 96 sandwiches per hour Process cycle time is 30 + 15 + 20 + 40 + 37.5 = 142.5 seconds © 2011 Pearson Education, Inc. publishing as Prentice Hall

Capacity Analysis Standard process for cleaning teeth Cleaning and examining X-rays can happen simultaneously Check out 6 min/unit Check in 2 min/unit Develops X-ray 4 min/unit 8 min/unit Dentist Takes X-ray 5 min/unit X-ray exam Cleaning 24 min/unit © 2011 Pearson Education, Inc. publishing as Prentice Hall

Capacity Analysis All possible paths must be compared Check out 6 min/unit Check in 2 min/unit Develops X-ray 4 min/unit 8 min/unit Dentist Takes X-ray 5 min/unit X-ray exam Cleaning 24 min/unit All possible paths must be compared Cleaning path is 2 + 2 + 4 + 24 + 8 + 6 = 46 minutes X-ray exam path is 2 + 2 + 4 + 5 + 8 + 6 = 27 minutes Longest path involves the hygienist cleaning the teeth Bottleneck is the hygienist at 24 minutes Hourly capacity is 60/24 = 2.5 patients Patient should be complete in 46 minutes © 2011 Pearson Education, Inc. publishing as Prentice Hall

Theory of Constraints Five-step process for recognizing and managing limitations Step 1: Identify the constraint Step 2: Develop a plan for overcoming the constraints Step 3: Focus resources on accomplishing Step 2 Step 4: Reduce the effects of constraints by offloading work or expanding capability Step 5: Once overcome, go back to Step 1 and find new constraints © 2011 Pearson Education, Inc. publishing as Prentice Hall

Bottleneck Management Release work orders to the system at the pace of set by the bottleneck Lost time at the bottleneck represents lost time for the whole system Increasing the capacity of a non-bottleneck station is a mirage Increasing the capacity of a bottleneck increases the capacity of the whole system © 2011 Pearson Education, Inc. publishing as Prentice Hall

Break-Even Analysis Technique for evaluating process and equipment alternatives Objective is to find the point in dollars and units at which cost equals revenue Requires estimation of fixed costs, variable costs, and revenue This chart introduces breakeven analysis and the breakeven or crossover chart. As you discuss the assumptions upon which this techniques is based, it might be a good time to introduce the more general topic of the limitations of and use of models. Certainly one does not know all information with certainty, money does have a time value, and the hypothesized linear relationships hold only within a range of production volumes. What impact does this have on our use of the models? © 2011 Pearson Education, Inc. publishing as Prentice Hall

Break-Even Analysis Fixed costs are costs that continue even if no units are produced Depreciation, taxes, debt, mortgage payments Variable costs are costs that vary with the volume of units produced Labor, materials, portion of utilities Contribution is the difference between selling price and variable cost This chart introduces breakeven analysis and the breakeven or crossover chart. As you discuss the assumptions upon which this techniques is based, it might be a good time to introduce the more general topic of the limitations of and use of models. Certainly one does not know all information with certainty, money does have a time value, and the hypothesized linear relationships hold only within a range of production volumes. What impact does this have on our use of the models? © 2011 Pearson Education, Inc. publishing as Prentice Hall

Break-Even Analysis Assumptions Costs and revenue are linear functions Generally not the case in the real world We actually know these costs Very difficult to verify Time value of money is often ignored This chart introduces breakeven analysis and the breakeven or crossover chart. As you discuss the assumptions upon which this techniques is based, it might be a good time to introduce the more general topic of the limitations of and use of models. Certainly one does not know all information with certainty, money does have a time value, and the hypothesized linear relationships hold only within a range of production volumes. What impact does this have on our use of the models? © 2011 Pearson Education, Inc. publishing as Prentice Hall

Total cost = Total revenue Break-Even Analysis – 900 – 800 – 700 – 600 – 500 – 400 – 300 – 200 – 100 – | | | | | | | | | | | | 0 100 200 300 400 500 600 700 800 900 1000 1100 Cost in dollars Volume (units per period) Total revenue line Profit corridor Loss corridor Total cost line Break-even point Total cost = Total revenue Variable cost This chart introduces breakeven analysis and the breakeven or crossover chart. As you discuss the assumptions upon which this techniques is based, it might be a good time to introduce the more general topic of the limitations of and use of models. Certainly one does not know all information with certainty, money does have a time value, and the hypothesized linear relationships hold only within a range of production volumes. What impact does this have on our use of the models? Fixed cost Figure S7.5 © 2011 Pearson Education, Inc. publishing as Prentice Hall

Break-Even Analysis TR = TC F or BEPx = P - V Px = F + Vx BEPx = break-even point in units BEP$ = break-even point in dollars P = price per unit (after all discounts) x = number of units produced TR = total revenue = Px F = fixed costs V = variable cost per unit TC = total costs = F + Vx Break-even point occurs when This chart introduces breakeven analysis and the breakeven or crossover chart. As you discuss the assumptions upon which this techniques is based, it might be a good time to introduce the more general topic of the limitations of and use of models. Certainly one does not know all information with certainty, money does have a time value, and the hypothesized linear relationships hold only within a range of production volumes. What impact does this have on our use of the models? TR = TC or Px = F + Vx BEPx = F P - V © 2011 Pearson Education, Inc. publishing as Prentice Hall

Break-Even Analysis BEP$ = BEPx P = P = Profit = TR - TC P - V BEPx = break-even point in units BEP$ = break-even point in dollars P = price per unit (after all discounts) x = number of units produced TR = total revenue = Px F = fixed costs V = variable cost per unit TC = total costs = F + Vx BEP$ = BEPx P = P = F (P - V)/P P - V 1 - V/P Profit = TR - TC = Px - (F + Vx) = Px - F - Vx = (P - V)x - F This chart introduces breakeven analysis and the breakeven or crossover chart. As you discuss the assumptions upon which this techniques is based, it might be a good time to introduce the more general topic of the limitations of and use of models. Certainly one does not know all information with certainty, money does have a time value, and the hypothesized linear relationships hold only within a range of production volumes. What impact does this have on our use of the models? © 2011 Pearson Education, Inc. publishing as Prentice Hall

Break-Even Example Fixed costs = $10,000 Material = $.75/unit Direct labor = $1.50/unit Selling price = $4.00 per unit BEP$ = = F 1 - (V/P) $10,000 1 - [(1.50 + .75)/(4.00)] © 2011 Pearson Education, Inc. publishing as Prentice Hall

Break-Even Example Fixed costs = $10,000 Material = $.75/unit Direct labor = $1.50/unit Selling price = $4.00 per unit BEP$ = = F 1 - (V/P) $10,000 1 - [(1.50 + .75)/(4.00)] = = $22,857.14 $10,000 .4375 BEPx = = = 5,714 F P - V $10,000 4.00 - (1.50 + .75) © 2011 Pearson Education, Inc. publishing as Prentice Hall

Break-Even Example Revenue Break-even point Total costs Fixed costs 50,000 – 40,000 – 30,000 – 20,000 – 10,000 – – | | | | | | 0 2,000 4,000 6,000 8,000 10,000 Dollars Units Revenue Break-even point Total costs Fixed costs © 2011 Pearson Education, Inc. publishing as Prentice Hall

∑ 1 - x (Wi) Break-Even Example Multiproduct Case F BEP$ = Vi Pi where V = variable cost per unit P = price per unit F = fixed costs W = percent each product is of total dollar sales i = each product © 2011 Pearson Education, Inc. publishing as Prentice Hall

Multiproduct Example Fixed costs = $3,000 per month Annual Forecasted Item Price Cost Sales Units Sandwich $5.00 $3.00 9,000 Drink 1.50 .50 9,000 Baked potato 2.00 1.00 7,000 © 2011 Pearson Education, Inc. publishing as Prentice Hall

Multiproduct Example Fixed costs = $3,000 per month Annual Forecasted Item Price Cost Sales Units Sandwich $5.00 $3.00 9,000 Drink 1.50 .50 9,000 Baked potato 2.00 1.00 7,000 Sandwich $5.00 $3.00 .60 .40 $45,000 .621 .248 Drinks 1.50 .50 .33 .67 13,500 .186 .125 Baked 2.00 1.00 .50 .50 14,000 .193 .096 potato $72,500 1.000 .469 Annual Weighted Selling Variable Forecasted % of Contribution Item (i) Price (P) Cost (V) (V/P) 1 - (V/P) Sales $ Sales (col 5 x col 7) © 2011 Pearson Education, Inc. publishing as Prentice Hall

Multiproduct Example ∑ 1 - x (Wi) F BEP$ = Vi Pi = = $76,759 $3,000 x 12 .469 Fixed costs = $3,000 per month Annual Forecasted Item Price Cost Sales Units Sandwich $5.00 $3.00 9,000 Drink 1.50 .50 9,000 Baked potato 2.00 1.00 7,000 Daily sales = = $246.02 $76,759 312 days Sandwich $5.00 $3.00 .60 .40 $45,000 .621 .248 Drinks 1.50 .50 .33 .67 13,500 .186 .125 Baked 2.00 1.00 .50 .50 14,000 .193 .096 potato $72,500 1.000 .469 Annual Weighted Selling Variable Forecasted % of Contribution Item (i) Price (P) Cost (V) (V/P) 1 - (V/P) Sales $ Sales (col 5 x col 7) .621 x $246.02 $5.00 = 30.6  31 sandwiches per day © 2011 Pearson Education, Inc. publishing as Prentice Hall

Reducing Risk with Incremental Changes (a) Leading demand with incremental expansion Demand Expected demand New capacity (b) Capacity lags demand with incremental expansion Demand New capacity Expected demand (c) Attempts to have an average capacity with incremental expansion Demand New capacity Expected demand This slide probably requires some discussion or explanation. Perhaps the best place to start is the left hand column where capacity either leads or lags demand incrementally. As you continue to explain the options, ask students to suggest advantages or disadvantages of each. Figure S7.6 © 2011 Pearson Education, Inc. publishing as Prentice Hall

Reducing Risk with Incremental Changes (a) Leading demand with incremental expansion Demand Time (years) 1 2 3 New capacity Expected demand This slide probably requires some discussion or explanation. Perhaps the best place to start is the left hand column where capacity either leads or lags demand incrementally. As you continue to explain the options, ask students to suggest advantages or disadvantages of each. Figure S7.6 © 2011 Pearson Education, Inc. publishing as Prentice Hall

Reducing Risk with Incremental Changes (b) Capacity lags demand with incremental expansion Demand Time (years) 1 2 3 New capacity Expected demand This slide probably requires some discussion or explanation. Perhaps the best place to start is the left hand column where capacity either leads or lags demand incrementally. As you continue to explain the options, ask students to suggest advantages or disadvantages of each. Figure S7.6 © 2011 Pearson Education, Inc. publishing as Prentice Hall

Reducing Risk with Incremental Changes (c) Attempts to have an average capacity with incremental expansion Demand Time (years) 1 2 3 New capacity Expected demand This slide probably requires some discussion or explanation. Perhaps the best place to start is the left hand column where capacity either leads or lags demand incrementally. As you continue to explain the options, ask students to suggest advantages or disadvantages of each. Figure S7.6 © 2011 Pearson Education, Inc. publishing as Prentice Hall

Expected Monetary Value (EMV) and Capacity Decisions Determine states of nature Future demand Market favorability Analyzed using decision trees Hospital supply company Four alternatives © 2011 Pearson Education, Inc. publishing as Prentice Hall

Expected Monetary Value (EMV) and Capacity Decisions -$90,000 Market unfavorable (.6) Market favorable (.4) $100,000 Large plant Market favorable (.4) Market unfavorable (.6) $60,000 -$10,000 Medium plant Market favorable (.4) Market unfavorable (.6) $40,000 -$5,000 Small plant $0 Do nothing © 2011 Pearson Education, Inc. publishing as Prentice Hall

Expected Monetary Value (EMV) and Capacity Decisions -$90,000 Market unfavorable (.6) Market favorable (.4) $100,000 Large plant Market favorable (.4) Market unfavorable (.6) $60,000 -$10,000 Medium plant Market favorable (.4) Market unfavorable (.6) $40,000 -$5,000 Small plant $0 Do nothing Large Plant EMV = (.4)($100,000) + (.6)(-$90,000) EMV = -$14,000 © 2011 Pearson Education, Inc. publishing as Prentice Hall

Expected Monetary Value (EMV) and Capacity Decisions -$14,000 -$90,000 Market unfavorable (.6) Market favorable (.4) $100,000 Large plant $18,000 Market favorable (.4) Market unfavorable (.6) $60,000 -$10,000 Medium plant Market favorable (.4) Market unfavorable (.6) $40,000 -$5,000 Small plant $0 Do nothing $13,000 © 2011 Pearson Education, Inc. publishing as Prentice Hall

Strategy-Driven Investment Operations may be responsible for return-on-investment (ROI) Analyzing capacity alternatives should include capital investment, variable cost, cash flows, and net present value This slide suggests that the process selection decision should be considered in light of the larger strategic initiative © 2011 Pearson Education, Inc. publishing as Prentice Hall

Net Present Value (NPV) In general: F = P(1 + i)N where F = future value P = present value i = interest rate N = number of years Solving for P: P = F (1 + i)N © 2011 Pearson Education, Inc. publishing as Prentice Hall

Net Present Value (NPV) In general: F = P(1 + i)N where F = future value P = present value i = interest rate N = number of years While this works fine, it is cumbersome for larger values of N Solving for P: P = F (1 + i)N © 2011 Pearson Education, Inc. publishing as Prentice Hall

NPV Using Factors F P = = FX (1 + i)N where X = a factor from Table S7.1 defined as = 1/(1 + i)N and F = future value Year 6% 8% 10% 12% 14% 1 .943 .926 .909 .893 .877 2 .890 .857 .826 .797 .769 3 .840 .794 .751 .712 .675 4 .792 .735 .683 .636 .592 5 .747 .681 .621 .567 .519 Portion of Table S7.1 © 2011 Pearson Education, Inc. publishing as Prentice Hall

Present Value of an Annuity An annuity is an investment which generates uniform equal payments S = RX where X = factor from Table S7.2 S = present value of a series of uniform annual receipts R = receipts that are received every year of the life of the investment © 2011 Pearson Education, Inc. publishing as Prentice Hall

Present Value of an Annuity Portion of Table S7.2 Year 6% 8% 10% 12% 14% 1 .943 .926 .909 .893 .877 2 1.833 1.783 1.736 1.690 1.647 3 2.676 2.577 2.487 2.402 2.322 4 3.465 3.312 3.170 3.037 2.914 5 4.212 3.993 3.791 3.605 3.433 © 2011 Pearson Education, Inc. publishing as Prentice Hall

Present Value of an Annuity $7,000 in receipts per for 5 years Interest rate = 6% From Table S7.2 X = 4.212 S = RX S = $7,000(4.212) = $29,484 © 2011 Pearson Education, Inc. publishing as Prentice Hall

Limitations Investments with the same NPV may have different projected lives and salvage values Investments with the same NPV may have different cash flows Assumes we know future interest rates Payments are not always made at the end of a period © 2011 Pearson Education, Inc. publishing as Prentice Hall

Printed in the United States of America. All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without the prior written permission of the publisher. Printed in the United States of America. © 2011 Pearson Education, Inc. publishing as Prentice Hall