SPS 1 and 5 during W7-9 2019 J.MEIGNAN EN-ACE-OSS 20/02/2019.

Slides:



Advertisements
Similar presentations
Backwards Compatibility L4 – L2 W. Weterings LBCC - 14.
Advertisements

CENF – Civil Engineering Extension B887 CERN: An accelerator complex unique in the world -Prevessin site complex- -EHN1 Extension Area- EHN1 Extension.
Notes After TIG 17/7/08 HF+ Move out of garage: Aug 15* Platform+table+collars+racks+BP support (jack up for platform) = 3 days Controls for motors = 1.
WP2 Superbeam Work Breakdown Structure Version 2 Chris Densham (after Marco Zito version 1 )
Consolidation and Upgrade of the SPS Electrical Networks Current Status JP. Sferruzza, on behalf of EN/EL.
7/23/ J.Coupard. 1) Cryogenic risks 2) Cryogenic phases from RT/floating to nominal and additional safety rules A. Sectors warmed-up to RT or considered.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed.
SPS Dump relocation Radioactive Dump storage alternatives JL GRENARD EN-HE
LS1preparation & planning status A L Perrot on the behalf of EN/MEF R2E project meeting 11 th May 2012 EN.
Design, integration and installation milestones Legend: 2015/Q1= 1 st quarter of 2015 (January-March) Phase 1 = proton & laser beams operation Phase 2.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
On behalf on EN-EL October 1 st, 2015 YETS Works EN-EL [ CF excluded ]
HIGH RADIATION TO MATERIALS: EXPERIMENTAL AREA HiRadMat Users meeting, 14/7/2011 Outline  Location  Test zone  Test tables geometry and position  Services.
Substation L1/ MCC L1 Update #2 July 27,2012. Status of Procurement  Substation  All approval drawings submitted  Testing is expected to take place.
Technical Support /15/08 PHENIX WEEKLY PLANNING 5/15/2008 Don Lynch.
Injectors & LHC report K. Foraz on behalf of OSS members 01/11/13LSC - EN-MEF-OSS1.
Injectors & LHC report K. Foraz on behalf of OSS members 01/08/2013LSC - K. Foraz1.
Vault Reconfiguration IT DMM January 23 rd 2002 Tony Cass —
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
PSB HW Commissioning Meeting 8 February 2016 A. Akroh, B. Mikulec.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
Magnet activities in SPS during EYETS
SPS-FIRE The SPS Fire Safety Project Planning Status
K. Foraz on behalf of OSS members
Linac4-PSB 160 MeV connection readiness review
TE-EPC internal review of the ELENA project
CLIC Handling Engineering Update
SPS LS1 Planning meeting (N019) 04/09/13
Update on the Critical Path of the PS Booster Schedule for the EYETS
SPS Winter stop Planning meeting (N06) 05/01/2011
EYETS Works EN-EL [ FC excluded ]
YETS & LS2 Works EN-El on LHC / Power distribution
BE-ICS Activities during the LS2 Period (15 min)
TE-MSC activities in SPS during LS2
EYETS David Hay EN-OSS.
BA6 – crab cavity activities in EYETS
K. Foraz on behalf of OSS members
TE/EPC activities for LINAC 2, PSB, PS & TT2 during EYETS
EN-HE SPS works during EYETS
SPS EN-CV Planning LS (initial draft)
SPS Planning for the EYETS Meeting 8 (07/12/2016)
SPS Planning for the EYETS Meeting 9 (14/12/2016)
RWTCS Steering Commitee
RWTCS Steering Commitee
SPS activities during LS2 TE-EPC (Power Converter Group)
Extension SR1 WP3 Electrical installations
TE-MSC activities in SPS during YETS
Status with crucial LSS5 kicker transmission line cables
K. Foraz on behalf of OSS members
BE-ICS work for SPS Safety Systems
Magnet electrical and hydraulic (dis)connections for coating
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
ACS news Circulator TCU: control tests in progress All cavity racks
Undulator System Installation
Experimental Areas – LS2 planning
SPS 1 and 5 during W J.MEIGNAN EN-ACE-OSS 09/01/2019.
SPS 1 and 5 during W J.MEIGNAN EN-ACE-OSS 23/01/2019.
SPS Planning meeting for LS2 #18 Vacuum sectors situation
SPS Planning meeting for LS2 #16 Vacuum sectors situation
SPS 1 and 5 during W J.MEIGNAN EN-ACE-OSS 06/03/2019.
EN-HE SPS during LS2 J-L GRENARD on behalf of EN-HE 23/1/2019.
SPS 2, 3, 4 and 6 during W D.MCFARLANE EN-ACE-OSS 26/06/2019.
SPS Planning meeting for LS2 #25 Vacuum sectors status
SPS 2, 3, 4 and 6 during W D.MCFARLANE EN-ACE-OSS 12/06/2019.
SPS Planning meeting for LS2 #26 Vacuum sectors status
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

SPS 1 and 5 during W7-9 2019 J.MEIGNAN EN-ACE-OSS 20/02/2019

Update for WP4 water feeding SPS1 Works in false floor in BA1 from 02/09/19 to 23/09/19 (3 weeks) Water cut (primary cooling circuit) the last week SPS5 Works in false floor in BA5 from 18/11/19 to 09/12/19 (3 weeks) Water cut (RIA in ECX5/ECA5) the last week (Fire hydrants outside = operational) 20/02/2019 J.MEIGNAN

Warning Helium line coming from BA6 to BA4 This line is NOT OBSOLETE Issue for civil engineering Issue for the safety on the crane bridge 20/02/2019 J.MEIGNAN

Activities ongoing week 7-8 Point 1 BA1: Transformer maintenance LSS1-/Arc1-: Safety cable trays Shaft/TA/TT10: Fire safety WP3 (Dry riser): TT10 OK, TA/shaft almost finished Puisard maintenance Smoothing survey ongoing: high values to correct vertically (+2,5mm!) 20/02/2019 J.MEIGNAN

Activities ongoing week 7-8 Point 5 BA5: Decabling (also in TA/Shaft) Ethernet cables (until 01/03/19) Power converters reconfiguration Arc5-: Ac coating finished LSS5 Decabling campaign 20/02/2019 J.MEIGNAN

Activities ongoing week 7-8 Point 5 ECX5 Moving of the cable trays in the tunnel eye Arc 5+: Fire safety WP3 (fire safety) BB5: Mock up ongoing (and impressive!) 20/02/2019 J.MEIGNAN

Activities scheduled on week 9 Point 1: BA1: MKDV racks dismantling Point 5: BA5 Power converters reconfiguration Lift maintenance: 04/03 6am to 8am in BA5 LSS5 Decabling campaign Transmission line installation 20/02/2019 J.MEIGNAN

Any questions?

Reminder: rules near BA5 To avoid problems seen during other YETS/EYETS with neighbours Road to use Pedestrian roads Parking outside point 5 : forbidden 20/02/2019 J.MEIGNAN

**Supports Equipment owners are responsible of their supports They are in charge to organise their removal, packaging and storage EN-HE will transport these supports to the storage place 20/02/2019 J.MEIGNAN