Change Assurance Report March 2019

Slides:



Advertisements
Similar presentations
Introduction to Impact Assessment
Advertisements

Roadmap for Sourcing Decision Review Board (DRB)
Page 1 Capability Business Benefit Business Risk KEYBA Capabilities: Benefits V Risks Facilitation of Decision making Getting the right people together.
State of Indiana Business One Stop (BOS) Program Roadmap Updated June 6, 2013 RFI ATTACHMENT D.
Workforce Assurance Tool - Overview & Application John Parker Workforce Planner / Analyst East Cheshire NHS Trust June 2013.
IDBM industry project Project Plan. Add text here giving a brief background of the project Project Background.
Supporting people with a learning disability Introduction to Project Management Presenter: Steve Raw FInstLM, FCMI.
What do reviewers look for in a research proposal? Research Councils’ review criteria Dimitra Koutsantoni Research & Knowledge Transfer Manager.
CS 4310: Software Engineering
Lifecycle Management and the Projects Portfolio. 2 Agenda How project portfolio management fits within an overall lifecycle for managing the delivery.
OSF/ISD Project Portfolio Management Framework January 17, 2011.
Service Transition & Planning Service Validation & Testing
Object-oriented Analysis and Design Stages in a Software Project Requirements Writing Analysis Design Implementation System Integration and Testing Maintenance.
Supporting Industry Change Planning: Risk & Milestone Assessment Process & Tools 07/07/2014.
UK Link Programme Dashboard Report Change Overview Board: 13/05/2014 Critical HLD activities complete enabling entry into Detailed Design Detailed Design.
UK Link Programme Update to PNUNC June 17 th 2013.
{ Phases of Project & life cycle Prepared by: Syed ShahRukh Haider.
Practical Investment Assurance Framework PIAF Copyright © 2009 Group Joy Pty. Ltd. All rights reserved. Recommended for C- Level Executives.
Project management Topic 7 Controls. What is a control? Decision making activities – Planning – Monitor progress – Compare achievement with plan – Detect.
PNISG Update June Xoserve’s UKLP Assessment Principles 1.Maintain current delivery plans where possible and appropriate e.g. don’t just push all.
Recall The Team Skills 1. Analyzing the Problem (with 5 steps) 2. Understanding User and Stakeholder Needs 3. Defining the System A Use Case Primer Organizing.
Lecture 2 System Development Lifecycles. Building a house Definition phase Analysis phase Design phase Programming phase System Test phase Acceptance.
The Implementation of BPR Pertemuan 9 Matakuliah: M0734-Business Process Reenginering Tahun: 2010.
Auditing for achievement Does Partnering Work ? Partnerships.
Phase-1: Prepare for the Change Why stepping back and preparing for the change is so important to successful adoption: Uniform and effective change adoption.
Quantum Leap Project Management
DSC Change Committee UK Link Future Releases Proposed Approach
Solihull Review of Urgent Care Programme Approach And Governance 2013
Workplace Projects.
Approaches to Defining Risk
Status of the MICE Construction Project
Project life span.
MANCHESTER LOCALITY PLAN BOARD – GOVERNANCE RESPONSIBILITIES
UK Link Programme Update to PNUNC August 13th, 2013
Why Realising Benefits from projects is a rarity and how to ensure you actually realise benefits Version 1.0 Prepared by: David Walton David Walton.
SIP Report – Nov 2017 Overview Headlines Workstream report
Key Information Summary (KIS)
Project Roles and Responsibilities
Requirements and the Software Lifecycle
Strawman Best Practice IIA Change Forum June 2017
Guidance notes for Project Manager
Change Assurance Dashboard
Release 3 Plan Options Decision
Recommendations for using this ‘framework’ template
Change Assurance Update
Overall Project RAG Status
West Essex Business Planning Process
Change Assurance Dashboard
EUC Project Timelines Key Upcoming Dates:
DSC Change Committee Summary – 11th July
Release 3 Plan Options Analysis
Overall Project RAG Status
Change Assurance Findings for UK Link Release 3 Health-check 2
Release 3 Update 9th January 2019.
Overall Project RAG Status:
xrn4340 – UK Link Future Release 1.1
Portfolio, Programme and Project
KVI Change Management Survey Feedback
Overall Project RAG Status
WFD and Agriculture Activity under the CIS 2005/2006 Work Programme
XRN4361 – UK Link Release 2 - Delivery
XRN4361 – UK Link Release 2 - Delivery
Programme Management Board
KVI Change Management Survey April 2019
CSS Consequential Programme Change Assurance March, 2019
Change Management Committee
XRN June 19 Release - Status Update
XRN4361 – UK Link Release 2 - Delivery
Change Management Committee
Description of Change(s)
Presentation transcript:

Change Assurance Report March 2019

Change Assurance Health Checks – UK Link Releases Two UK Link related health checks were carried out in January 2019 The projects are June’19 Release and EUC Release The summary reports and findings closure can be seen below

UK Link June’19 Release Summary Dashboard Area Date Change Project RAYG by Area CA1 – CA4 Summary Programme Delivery January 2019 UK Link June’19 – Health check Overall Business Case Team Sponsorship Plan Governance Customer Scope and Solution Other CA1 CA2 CA3 CA4 • UK Link June’19 release is made up of 3 Change Requests, all of which are perceived to be relatively straightforward. • The project has faced a number of challenges which has put the outcomes at risk: o The requirements as handed over from Capture required significant further work to refine them putting pressure on the timelines. The Capture process is relatively new and work is required to improve the outputs from this process, to enable effective transition from Capture to Start-up. This has been recognised and work is underway introduce improvements. These should be implemented promptly and some monitoring of results should be established. o A new delivery 3rd party (TCS) were bought with limited Knowledge Transfer (KT); this has introduced risk to the quality of delivery. The project needs to plan further activities for TCS to reduce the risk and the platform as a whole needs to establish an on-boarding process and supporting materials for new suppliers/SIs. o There have been significant issues with the documentation needed for design. Due to poor control of the functional specification (FS) versions, it has been difficult to identify the latest versions. Thus there is a risk that the design will be based on an out of date FSs, leading to the desired functionality either not working or introducing an unexpected problem (defect). This is an issue which impacts all UK Link related change activity and is probably contributing to the level of defects. Work needs to take place with all parties that are enacting UK Link related change to establish an action plan to eradicate this issue. •These challenges have resulted in, not all of artefacts ,needed to pass through the next Stage Gate, being complete. The team are working hard to rectify this so that they can be successful at the next Stage Gate Approval Board. •It should be noted that TCS has worked very hard to compensate for the limited KT and the FS version issue; partially mitigating the risks. They have also worked well with stakeholders to build confidence in their ability to deliver and deliver to the desired timescale. •Project Governance needs to be tightened up, but the project team are demonstrably working to do this. Provided they close out these actions quickly the on-going monitoring and control should be straightforward. The discipline of the Stage Gates should help to drive this. Original Latest 3 1 8 5 6 1 1 Readiness to enter CUT

UK Link EUC Release Summary Dashboard Area Date Change Project RAYG by Area CA1 – CA4 Summary Programme Delivery January 2019 UK Link EUC – Health check Overall Business Case Team Sponsorship Plan Governance Customer Scope and Solution Other CA1 CA2 CA3 CA4 There is a much greater degree of nervousness from all internal stakeholders about this project, compared with June’19, as it has much more wide ranging system and process impacts. If we do not make the change cleanly there is a risk that we will negatively impact to our customers and thus our reputation. The project has faced similar challenges to June’19 which has put the outcomes at significant risk: The requirements as handed over from Capture required significant further work to refine them putting pressure on the timelines. Confidence in the understanding of the impacts of this change have not been high, with the impacts on other systems having been a source on significant debate. This has lead to the requirements and design documents not being complete and requiring thorough review before they are moved into CUT. The Capture process is relatively new and work is required to improve the outputs from this process, to enable effective transition from Capture to Start-up. This has been recognised and work is underway introduce improvements. These should be implemented promptly and some monitoring of results should be established. A new delivery 3rd party (TCS) were bought in with limited Knowledge Transfer (KT); this has introduced risk to the quality of delivery. The project needs to plan further activities for TCS to reduce the risk and the platform as a whole needs to establish an on-boarding process and supporting materials for new suppliers/SIs. There have been significant issues with the documentation needed for design. Due to poor control of the functional specification (FS) versions, it has been difficult to identify the latest versions. Work needs to take place with all parties that are enacting UK Link related change to establish an action plan to eradicate this issue. TCS have experienced similar challenges with BW: Due to the lack of availability of key BW documentation TCS have to inspect all 575 individual reports to establish whether they are impacted by this project and so need changing. This approach is not only time consuming but is likely to be at risk of mistakes being made which result in rework. These challenges have resulted in, most of artefacts ,needed to pass through the next Stage Gate, being incomplete. A return to green plan needs to be established and acted on promptly. It should be noted that TCS has worked very hard to compensate for the limited KT and the FS version issue; partially mitigating the risks. They have also worked well with stakeholders to build confidence in their ability to deliver but they are less confident in this project The project governance needs to be tightened up and an time taken to plan in some detail. This needs to form part of the return to green plan. Original Latest 4 1 8 2 6 1 Readiness to enter CUT

Findings Closure Performance The project teams have successfully closed out the majority of the findings for these two projects and the remaining findings are actively being moved to closure All remaining findings are targeted for closure before the end of March Given the current position of the findings closure, both projects are better placed to effectively deliver the required outcomes Further health checks are recommended later in the lifecycle