SNS PPU Cryomodule Vacuum Vessel

Slides:



Advertisements
Similar presentations
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Advertisements

Vacuum Vessel Production Readiness Review
FDR Station 3 lift fixture, laser screens and brackets T. Brown and L. Morris with analysis support from A. Brooks December 3, 2007.
Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Lab MICE CM26 at Riverside California March 26, 2010.
CRYO PIPING & INTER-MODULE CONNECTIONS Yun He, Daniel Sabol, Joe Conway External Review of MLC Daniel Sabol, MLC External Review 10/3/2012.
Objective : To understand the fabrication, design, installation welding, inspection and testing for new construction in oil and gas industry After followed.
Cryomodule Concept for the ODU RF Dipole Crab Cavity Tom Nicol* - Fermilab December 10, 2013 * With lots of help from HyeKyoung, Tom J, Shrikant, Ofelia,
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe MLC external review October 03, 2012.
Assembly, Installation and Interfaces Steve Virostek Lawrence Berkeley National Lab RFCC Module Design Review October 21, 2008.
ESS cavities interfaces
NCSX Vacuum Vessel Joint Design Mike Viola PPPL July 1 st, 2003.
1 BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnet and Girder Integration Lewis Doom, NSLS-II Project National Synchrotron Light Source II (NSLS-II) will.
FNAL Cavities for S1 Global Jim Kerby ALCPG 09. FNAL Deliverables Discussed in meetings 15/16 July and 10/11 Sept, and Webex and s 9/30/20092FNAL.
Work toward Stainless Steel SRF Helium Vessels at Fermilab Tom Peterson (presenter), Information from Jeff Brandt, Serena Barbanotti, Harry Carter, Sergei.
Brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Inner Triplet Review Q1, Q2, and Q3 Mechanics T. Nicol April 24-25, 2007.
F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 PF, TF, & Trim Coil Supports (WBS-15) Core Base Support Structure (WBS-17) F. Dahlgren NCSX Coil.
Date 2007/Oct./23 FNAL-GDE-Meeting Global Design Effort 1 Cryomodule Interface Definition (FNAL-GDE-Meeting) N. Ohuchi.
SCH Controls Readiness Review- Cryostat Nov 4-5, 2015 Kurt Cantrell.
SBS Magnet and Infrastructure Status Robin Wines July 2015.
Cryomodule prototype Yun He, Dan Sabol, Joe Conway On behalf of Matthias Liepe, Eric Smith, James Sears, Peter Quigley, Tim O’Connell, Ralf Eichhorn, Georg.
LMQXFA Cold Mass Assembly Antonios Vouris Fermilab February 3, 2016.
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
NCSX VACUUM VESSEL PL Goranson Final Design Review November 17, 2005 Man Access Port /Lateral Supports NCSX.
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
Cryomodule Assembly Facility Fermilab Cleanroom: Assembly/Disassembly Tools Tug Arkan 1.
LCLS-II Prototype Vacuum Vessel (VV) and Helium Gas Return Pipe (HGRP) FDR Planned Quality Control Effort (QC) Ken Premo 12/04/14.
Cryomodules Matthew Howell and Stephen Stewart Cryomodule Design Team Members.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
JLAB Cryomodule Assembly Facilities Visit Report Tug Arkan, Yuriy Orlov March 26, 2012.
Fabrication of Remaining Components Allan DeMello Lawrence Berkeley National Laboratory MICE RF Workshop Fermilab June 2, 2014.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
435B Transport Container Fabrication Challenges and Solutions
Integration of the Spectrometer Solenoid Magnets
Ed Daly for W. Robby Hicks
Preparation of functional/engineering specifications for HL-LHC
Crab Cavity HOM Coupler Specification Drawings & Tolerances
Overview of Mechanical Design
MLC Schedule Plan Proven in-house expertise and infrastructure for fabrication, assembly, and testing cryomodules Confident in our technical expertise.
SC1R Cold Box PDR Mechanical Design
2K Cold Box Mechanical Design
SHMS Downstream Beamline Large SHMS/HMS Angles (Config-1)
Summary of the checking items of the Module-C design
Additional Upstream Coil Shielding
Alignment of Main Linac Cryomodule (MLC)
SNS PPU Cryomodule Instrumentation
Cryomodule Assembly Plan
SNS PPU Cryomodule End Cans
SNS PPU Helium Vessel Design and Assembly
CRYOMODULE FINAL ASSEMBLY
SNS PPU Cryomodule Thermal Shield
SNS PPU Cryomodule Space Frame
SNS PPU Cryomodule Magnetic Shields
Cryomodule Shipping at JLab: SNS and LCLS-II
SNS PPU Cryomodule Shipping Plans
Cryomodule Transportation Preliminary Design
SNS Coupler Shipping Plans
SNS PPU Cryomodule Instrumentation
SNS PPU Helium Vessel Design and Assembly
SNS PPU Cryomodule Space Frame
SNS PPU Cryomodule Thermal Shield & MLI
SNS-PPU upgrades the existing accelerator structure
SNS PPU CRYOMODULE FDR Magnetic Shields Gary Cheng June 10, 2019.
SC1R Cold Box PDR Assembly Sequence
SNS PPU Cryomodule Design Overview
CRYOMODULE FINAL ASSEMBLY
SNS PPU CRYOMODULE PDR Cleanroom Assembly Katherine Wilson
JLAB CHL 2K COLD BOX REPLACEMENT
Presentation transcript:

SNS PPU Cryomodule Vacuum Vessel SNS PPU CRYOMODULE PDR SNS PPU CRYOMODULE PDR SNS PPU Cryomodule Vacuum Vessel SNS PPU Cryomodule Vacuum Vessel Matt Marchlik Matt Marchlik Wednesday, February 27 2019 Wednesday, February 27 2019

Outline Requirements Design Fabrication/Procurement methodology Remaining Tasks Summary

Requirements Vacuum Vessel will be ASME stamped vessels with a MAWP of 25 PSIG Design pressures of 30 PSIG internal and 15 PSIG external Interface with all necessary subsystems

Requirements Agreement between the labs defined in detail in “SNS PPU Cryomodule Pressure & Vacuum Systems” Power Point slides, by Gary Cheng, dated November 6, 2018 To meet ORNL requirements The End Can vacuum shell and Vacuum Vessel will be ASME stamped vessels with a MAWP of 25 PSIG Design pressures of 30 PSIG internal and 15 PSIG external To meet JLab requirements Helium vessels will be designed and built to the intent of the ASME BPVC pressure vessel code FPC Vacuum top hats and bellows will be designed to the ASME BPVC but treated as JLab Category II vacuum components Consistent with the SNS HB Prototype and allows JLab to make the top hat bellows closure weld

The existing SNS drawings will be used for unchanged components Design The existing SNS drawings will be used for unchanged components JLab drawings will be created to capture any changes This section primarily highlights any design changes

Design - Vacuum Vessel Weldment Comprised of the welded bodies that make up the pressure boundary and items welded to the boundary Only the vendor, a ASME BPVC code shop, may weld to the pressure boundary. All of these pieces, even the small brackets will be included in the weldment

Design - Vacuum Vessel Weldment Lock Down Weld Pads x24 Return End Can Mount Pad Stiffener Rings x5 Return End Can Port JT Valve Port ISO250-K Ports x10 Air Side FPC Ext. Mounts X4 sets Supply End Can Mount Pad End Flanges FPC Exhaust Manifold Ports x4 FPC Exhaust Manifold Port Supports x3 Supply End Can Port

Design - Vacuum Vessel Weldment Pressure Manifold Port Instrumentation Ports x4 FPC Ports x4 Interface Panel Mounts x4

Design - Vacuum Vessel Assembly Weldment Tie downs x24 End flanges x2 Parallel plate PRV x2 Blanks x7 Coupler top hats x4

Design – End Flange Weld The original vessel end flange configuration closely matched that shown in sketch (11) of fig.2-4 of ASME BPVC VIII-I (11) The configuration was changed to match that of sketch (4a) Radially and longitudinally self-fixturing to assist in arriving at desired tolerances Internal circumferential weld contraction should have less impact on flange flatness than other configuration (4a) Flange flatness, location and perpendicularity to shell axis will be GD&T controlled on the weldment drawing

Design – Vessel End Can Ports Originally, the return end can port of the vac vessel had a significantly smaller ID than that of the end can elbow Original vessel port 6.36 in ID The vac vessel port ID has been opened up to match that of the return can elbow Allows much more flex/displacement during end can alignment Increased vessel port 7.80 in ID

Design – Vessel End Can Ports Supply end can vessel port ID > elbow ID

Design – End Can Mounting Support Mount Mounting pad End Can Support Arm Pockets have been added to both of the end can mounting pads to receive the support mounts and allow compliance during installation/alignment of the end cans Tooling supports and aligns the ends cans. Support to pad welding is then completed These are considered weld pads, do not make up the pressure boundary. Welded by JLAB during assembly

Design – End Can Mounting Vertical Adjustability +/- .13 in Lateral Adjustability +/- .21 in Lateral Adjustability +/- 8∘ Pitch Adjustability Yaw Adjustability +/- 3∘

Design – End Flange Reinforcement The warm to cold beam line modification outlined by K. Wilson requires the opening in the end flange to increase. The new opening of 6.1 in and reinforcement was shown to be acceptable per ASME BPVC VIII-I, UG-39 Reinforcement d/2

Design – Beamline to Vessel Flange There were 20 bolts making up the beamline to vacuum vessel end flange joint A calculation per BPVC VIII-I, Mandatory Appendix 2 to determine the minimum required number of bolts The number of bolts has been reduced to 10 20 bolts 10 bolts

Procurement Fabrication plan/traveler PQR Work site visits Vessel weldment along with corresponding flanges will be fabricated by an ASME BPVC “code shop”. SOW will reflect the existing SNS and JLab SOW. Fabrication plan/traveler Materials Welding WPS PQR Dimensional verification Testing Leak Pressure Work site visits Customer visits/witnessing U-1 Shipping

Finalize and review any new drawings Procurement SOW PR PO Remaining Drawings Finalize and review any new drawings Procurement SOW PR PO

Summary Preliminary vessel design is in good shape Vessel interfaces with other subsystems have been verified Existing drawings have been reviewed Drawings for any design changes have been started Necessary calculations for proposed changes are complete Procurement methodology exists

Backups End flange calculations Beamline to Vacuum Bolt Number and Flange Stress Calculation

End Flange Calculations Backups End Flange Calculations

Backups – End Flange Calcs

Backups – End Flange Reinforcement/Max Opening Calc

Backups – End Flange Reinforcement/Max Opening Calc

Backups – End Flange Reinforcement/Max Opening Calc

Backups – End Flange Reinforcement/Max Opening Calc

Backups – End Flange Reinforcement/Max Opening Calc

Backups – End Flange Reinforcement/Max Opening Calc

Beamline to Vacuum Bolt Number and Flange Stress Calculation Backups Beamline to Vacuum Bolt Number and Flange Stress Calculation

Backups

Backups

Backups

Backups