Tasks completed this period Tasks in focus next period

Slides:



Advertisements
Similar presentations
Project Quality Plans Gillian Sandilands Director of Quality
Advertisements

Introduction to Impact Assessment
By Saurabh Sardesai October 2014.
9 Closing the Project Teaching Strategies
Travel Website Enhancement Project Project Update First Name Last Name.
1 © The Delos Partnership 2004 Project Management Organisation and Structure.
Project Status Report Presenter Name Presentation Date.
Insert Procurement Event Name Here Procurement Plan Presentation.
UK Link Programme Dashboard Report Change Overview Board: 13/05/2014 Critical HLD activities complete enabling entry into Detailed Design Detailed Design.
MEDIN Work Plan for By March 2011 MEDIN will be 3 years into the original 5 year development plan started in Would normally ask for continued.
X Project Highlight Report – (Date) Achievements  Key high level outputs delivered by the project this month. Communications Key high level communications.
Portfolio Overview as at page 1 of 3 Portfolio Headlines Clinical pathway work is progressing, with all three clinical pathway programmes being.
Project management Topic 7 Controls. What is a control? Decision making activities – Planning – Monitor progress – Compare achievement with plan – Detect.
Monitoring and Control
WEEK 9 supporting significant life events Olutoyin Hussain.
Prospects Programme Controlled Programme Delivery Toolkit Sofia September 2007 Author - Lynn Oates 1/8/2007- Page 1.
WP6 – Monitoring and Evaluation 17th November 2014 Rome.
CD FY08 Tactical Plan Status FY08 Tactical Plan Status Report for Networks Physical Infrastructure Rick Finnegan April 22, 2008.
Programme Management Board
Programme Management Board
4th Assessment of Progress Against the GEOSS 2015 Strategic Targets
Project Management The Roles and Responsibilities of a Project Manager
SA&S-Fortnightly Status Report – Overview Period Ending 3rd May 2017
Overview May 24, 2017.
Initiative Name Initiative Leader Target Go Live Date: Reporting Date
Hyper-V Cloud Proof of Concept Kickoff Meeting <Customer Name>
Steering Committee Meeting
Portfolio and key programme overview as at Page 1 of 4
Program Control Services – Overview
INF 410 Education for Service-- snaptutorial.com.
INF 410 Teaching Effectively-- snaptutorial.com
Executive Summary Project Name: Period :.
STEP 7 - EXECUTION PHASE: MONITORING & CONTROLING
Strawman Best Practice IIA Change Forum June 2017
Guidance notes for Project Manager
Successful IT Projects By Darren Dalcher & Lindsey Brodie
[Project Name] STEERING COMMITTEE UPDATE [Date]
Eagle Programme : 4 Box Summary
Overall Project RAG Status
What would improve the RAG status when red or amber
Amendment Invoice Task Force Progress Report
Insert subhead here Project Status.
Sustainability Plan 2015 Summary RAG Report
Release 3 Plan Options Decision
Stakeholder Management Template
Programme Management Board
Launch readiness template
Recommendations for using this ‘framework’ template
ViVa_MultimediaStoryboard
Amendment Invoice Task Force Progress Report
Overall Project RAG Status
Release 3 Plan Options Analysis
introducing MICHELLE SLY
Change Assurance Findings for UK Link Release 3 Health-check 2
What would improve the RAG status when amber or red
xrn4340 – UK Link Future Release 1.1
What would improve the RAG status when amber or red
SA&S-Fortnightly Status Report – Overview Period Ending 1st June 2017
Amendment Invoice Task Force Progress Report
Programme Management Board
Launch readiness template
Project Progress Summary - Week 18
Overview Headlines RSP – Progress Overview General progress report
SA&S-Fortnightly Status Report – Overview Period Ending 21 Feb 2018
Schedule (Major Deliverables and Milestones)
Tasks completed this period Tasks in focus next period
Tasks completed this period Tasks in focus next period
Key Activities/ Milestones
Description of Change(s)
Presentation transcript:

Tasks completed this period Tasks in focus next period Delivery element: Specialist Home-Start Team Leader: Caren Stone Report Period start Schedule Milestones Risk Assessment Issues Overall Delivery Report Period end 2.1.18 G A Progress Summary Aims and Objectives continuing to support for 4 clients previously signed up for them to fully access the project To get participant to be able to access project on their own after initial support to access routeways. To sign up/engagement/initial assessment participants To deliver intensive support to those participants who would find it hard to access MWP independently. Support/encourage participants to access all areas of project. Risk / Issue in focus Impact Action Status Tasks completed this period Baseline Actual one client is proving hard to keep contact with, wasn’t in for appointment but then called when bailiffs came round Now crises control instead of planned work with CALS and then financial team To hopefully get client to engage with project fully. 2 new clients signed up. It has been difficult working out whether a particular client can start project due to her complex situation, would be some time before she progressed to other parts of project after financial. Sought advice from Terry, Nadine and Kelly. Have signed client up. Issue: Tasks in focus next period Targets Target Sign up 1-2 clients in the Feb/March To sign up 10 participants and follow them through the entire project 10 in the year 6 To identify 2 more clients to sign up

RAG DEFINITION ACTION RED One or more aspects of project viability — time, cost, scope or benefits will not be delivered unless action is taken. No current plan is in place to mitigate the issue.   The project requires corrective action to meet Programme objectives. ESCALATE The matter should be escalated to the Exec Sponsor and Project Board immediately. Path from Red to Green: Mitigating actions must be recommended and implemented. AMBER One or more aspect of project viability — time, cost, scope or benefits is at risk of not being delivered. However, a plan is in place to mitigate any deviation from the plan.  INFORM The Programme Board should be informed using a progress report with a scheduled briefing with the Programme Manager and or Exec Sponsor to take place. Path from Amber to Green: Any mitigating actions must be recommended and implemented. GREEN The project is performing to plan with no issues known that could effect the project viability in terms of time, cost, scope or benefits. IGNORE For information ONLY. No Action required. ARROW DEFINITION    The RAG status has declined to a lower status (Green to Amber or Amber to Red) from the previous reporting period. The RAG status has Improved to a higher status (Red to Amber or Amber to Green) from the previous reporting period. The RAG Status has remained at the same status from the previous reporting period