LCLS Week 4-8 April, 2005 Steve Lewis

Slides:



Advertisements
Similar presentations
Delta Tau Coordinate Systems and PLCs at Diamond Matthew Pearson Controls Group, Diamond Light Source Overview: Delta Tau Geobrick motor controller Delta.
Advertisements

Steve Lewis XTOD October, 2005 UCRL-PRES LCLS Week/FAC October, 2005 Steve Lewis X-ray Transport, Optics,
Richard M. Bionta XTOD October 12, 2004 UCRL-PRES-XXXXX X Ray Transport, Optics, and Diagnostics, Overview Facility Advisory Committee.
Steve Lewis Direct Imager 06 Dec EPICS Controls Steve Lewis 07 December 2007 LCLS Direct Imager Final Design Review.
John Arthur Photon Systems April 16, LCLS Photon Systems Status Technical status and accomplishments Response to.
X Ray Transport / Optics / Diagnostics Overview Richard M. Bionta Facility Advisory Committee Meeting April 29, 2004 Richard M. Bionta Facility Advisory.
John Arthur Photon October 18, 2005 LCLS Photon Systems Status John Arthur SLAC.
John Arthur Photon October 27, Photon Systems Overview John Arthur SLAC.
John Arthur Photon April 20, 2006 Photon Systems Update John Arthur SLAC Photon Systems Manager.
Richard M. Bionta X-Ray Transport, Diagnostic, & Commissioning September 22, 2004 UCRL-PRES Two Problems... LCLS Diagnostics.
Steve Lewis XTOD 4-8 April, 2005 UCRL-PRES LCLS Week 4-8 April, 2005 Steve Lewis X-ray Transport, Optics, and Diagnostics:
John Arthur Photon October 12, Photon Systems Update John Arthur SLAC 1.
John Arthur Photon Systems April 7, 2005 Photon Systems Overview John Arthur.
Steve Lewis XTOD Controls FDR 14 February 2008 XTOD Instrument Controls Final Design Review Steve Lewis 14 February 2008.
Steve Lewis XTOD Controls FDR 13 March 2008 XTOD Vacuum Controls Final Design Review Steve Lewis/Keith Kishiyama 13 March 2008.
Lawrence Livermore National Laboratory This work performed under the auspices of the U.S. Department of Energy by Lawrence Livermore National Laboratory.
Donn H. McMahon XTOD Configuration October 24-26, 2005 UCRL-PRES X Ray Transport, Optics, and Diagnostics Overview FAC.
Stephen Schuh Vacuum Controls SCR and 16 November 2005 Vacuum Controls System Concept Review and Preliminary Design Review.
Steve Lewis Gas Detector 6 December Instrumentation & Controls Steve Lewis Paul Pax Elden Ables 6 December 2006 LCLS Gas Detector.
Steve Lewis Gas Attenuator 11 December Instrumentation & Controls Steve Lewis 11 December 2006 LCLS Gas Attenuator Preliminary.
John N. Galayda LCLS Accelerator Readiness December 2, LCLS Overview December 2, 2008 Project Construction Status.
18th June 2003 Diamond Vacuum System Steve Singleton 18th June 2003.
Laser Heater Controls Overview 21 August 2008 Matt Boyes Laser Heater Controls Design Overview EPICS IOC Team Meeting Matt Boyes.
Managed by UT-Battelle for the Department of Energy SCL Vacuum Control System Upgrade Derrick Williams
Steve Lewis Controls: Vacuum 5 April, 2005 UCRL-PRES LCLS Week 5 April, 2005 Steve Lewis Vacuum Standards.
LCLS Control Group FAC – 06 Installation October 27/28, Plans for 2006 Installation October 27, 2005 Installation.
ESS Timing System Plans Timo Korhonen Chief Engineer, Integrated Control System Division Nov.27, 2014.
LCLS Commissioning & Operations High Level Software
ControlLogix Portfolio
Cryogenic Plant Electrical and Controls
LCLS-II 2K Cold Box Controls Design Review
LUSI Coordination with LCLS
Timing and Event System S. Allison, M. Browne, B. Dalesio, J
AIP /02 P Bellomo - QE Magnet Power System Upgrade
Experimental Facilities Planning
HAPS Controls Glen White ATF2 Software Review Workshop, LAL, June 2008
LCLS Commissioning & Operations High Level Software
DOE Review May, 2005 Steve Lewis
SC1R Cold Box PDR Controls
EPICS Controls Steve Lewis 13 December 2007
LCLS Ultrafast Science Instruments
LCLS Timing Outline Scope The order of things
LCLS Event System - Software
LTU/Undulator Installation Status
LCLS-II Cryoplant Controls FDR Status of Past Reviews and Lessons Learned Dana Arenius Sept 13, 2017.
LCLS Timing Outline Scope The order of things
John N. Galayda – Director of LCLS Construction March 30, 2009
Installation of Photon Beam Transport to FEH
X-Ray Endstation Design & Management/Commissioning
X-Ray Transport, Optics, and Diagnostics WBS Alan J
Undulator Cost & Schedule Patric Den Hartog, ANL April 24, 2002
John Arthur – LCLS Experimental Operations
DOE Review 11 May 2005 Stephen A. Lewis
FEE Diagnostics and Commissioning
LCLS Personnel Protection System and Beam Containment System
LTU/Undulator Installation Status
DOE Review 7-9 February, 2006 Steve Lewis
Linac Coherent Light Source Project Update
Commissioning the European XFEL cryogenic system and best practice
LCLS Lehman Review February 7-9, 2005
LCLS XTOD Mechanical and Vacuum Systems; Gas Attenuator
Vacuum Controls Stephen Schuh Tom Porter 25 October 2006
Lehman Review: XTOD Beam Transport
Vacuum Control System for Monolith Vacuum
LCLS Control System Personnel Linac & BC2 Controls progress
Rack installation and local tests for the MEBT Chopper Rack
LCLS Photon Systems Overview
DOE Review 11 May 2005 Stephen A. Lewis
LUSI Controls and Data Systems W.B.S. 1.6
OPC UA and EPICS Introduction
Presentation transcript:

LCLS Week 4-8 April, 2005 Steve Lewis X-ray Transport, Optics, and Diagnostics: Controls Status LCLS Week 4-8 April, 2005 Steve Lewis

Layout Each hutch is 10 m long FEH NEH FEE Tunnel Experiments: Atomic Physics Front End Enclosure Fast Close Valve Slits Attenuators Shielding Experiments Optics Structual Bio Nano-scale Femtochem FEL Measurements & Experiments: Low Power Imaging High Power Imaging Spectrometer Calorimeter Flipper Mirror Experiments: Optics Warm Dense Matter

Major Effort Areas Getting an accurate count of all devices Naming devices (and extending SLC convention) Aligning XTOD controls devices with LCLS global standards Reviewing cost+schedule Installing EPICS at LLNL

Counting Devices Layout and instrument list has changed since original design Original design was not “EPICS-aware” Need block diagram or even one-line diagram to accurately define PLC, IOC and other controls- specific components LCLS-wide standards are (just) now being set All of above are basis for accurate cost+schedule

Will conform to (and extend) SLC conventions Naming Devices Will conform to (and extend) SLC conventions Especially for “SLC-aware” devices Allows uniform notation on spread-sheets, one-line diagrams, as well as EPICS configuration Implicitly forces accurate counting

Safety must be engineered in LCLS Global Standards Safety must be engineered in Commerical products are one way to ensure this (UL, CE, …) Initial Q/A will take place at LLNL for many items

LCLS Global Standards… Motor/Encoder chains: OMS58 in VME+transition card+power “brick”: 3 vendors; extra box+cables; great reuse of EPICS practice; parts long-lived Newport XPS single-box: turnkey; TCP/IP field- bus; new driver (and motor record?); rapid evolution of product likely Other?

LCLS Global Standards… Vacuum/Gas: Controllers & Architecture “Smart” controllers + inter-controller wiring + serial to EPICS Wiring complexity; less global integrity “Dumb” controllers+PLC+ Ethernet/IP to EPICS Global integrity; simple wiring ControlLogix vs. FlexLogic Trade-offs in cost, need for wire-centers, availability of EPICS driver

LCLS Global Standards… Choices for Gauges MKS-937A w/317-CEP and 422-CCG 15msec response option Other? Choices for Ion Pumps Dual; Quad; ? MPS-2 SafeCONN Kaiser StarCell

Reviewing Cost+Schedule Accurate device count supports: I/O hardware and cabling costs Approx $200K to be added for master PLCs Configuring+Commissioning Effort Approx 1500 hours to be added for Tunnel Fixed costs as well: Server for LLNL prototyping Licenses (PLC…) Any new drivers

Borrow small VME crate, CPU, EVR and EVG from SLAC EPICS at LLNL Set up a server RH Linux or MacOS X? Keep CVS at SLAC Intellectual property issue? Borrow small VME crate, CPU, EVR and EVG from SLAC Gas Attenuator prototype is first application First use of PLC Will train LLNL staff