Heinz-Dieter Nuhn – LCLS Undulator Group Leader May 14, 2009

Slides:



Advertisements
Similar presentations
Jose Chan FAC- Undulator System Installation & Assembly 10/30/07 1 Undulator System Installation & Assembly Schedule Jose.
Advertisements

Zachary Wolf Undulator Tuning November 12, Undulator Tuning Status Z. Wolf, S. Anderson, R. Colon, S. Jansson, D. Jensen,
HPS MPS OVERVIEW Dan Sexton & the Safety Systems Group JLAB 1.
Experience Report with the Alignment Diagnostic System Georg Gassner September 17 th 2010.
Heinz-Dieter Nuhn, SLAC / LCLS Undulator Checkout and Startup Plans November 12, Undulator Checkout and Startup Plans Heinz-Dieter.
January 24, 2008 Heinz-Dieter Nuhn, SLAC / LCLS Undulator BLM PDR Review 1 Undulator BLM PDR Review Heinz-Dieter Nuhn, SLAC / LCLS.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
October 12, 2006 Heinz-Dieter Nuhn, SLAC / LCLS Undulator Good Field Region and Tuning Strategy 1 Undulator Good Field Region and.
Marion M. White Undulator System 07 April 2005 LCLSLCLSLCLSLCLS Undulator System Tests Marion M. White ANL-ASD-LCLS.
Undulator Physics Requirements April 7, 2005 Heinz-Dieter Nuhn, SLAC / LCLS Facility Advisory Committee Meeting Undulator Physics.
Undulator Alignment Strategy – April 20, 2006 Heinz-Dieter Nuhn, SLAC / LCLS FAC 1 Undulator Alignment Strategy Heinz-Dieter Nuhn,
Zachary Wolf Undulator Tuning June 17, 2008 Undulator Tuning Status Z. Wolf, S. Anderson, R. Colon, S. Jansson, S.Kaplunenko,
LCLS Undulators October 14, 2004 Heinz-Dieter Nuhn, SLAC / SSRL MMF Review Introduction to the LCLS Undulators Heinz-Dieter Nuhn,
Isaac Vasserman Magnetic Measurements and Tuning 10/14/ I. Vasserman LCLS Magnetic Measurements and Tuning.
X-Ray Diagnostics for the LCLS Jan , 2004 UCLA.
October 30, 2007 Heinz-Dieter Nuhn, SLAC / LCLS Undulator Physics Issues 1 Undulator Physics Issues Heinz-Dieter Nuhn, SLAC / LCLS.
1 Zachary Wolf 1 Undulator Tuning Status June 9, 2009 Undulator Tuning Status Z. Wolf, S. Anderson, R. Colon, S. Jansson, D. Jensen,
Robert Ruland Installation Alignment -Magnetic Measurements – Fiducialization April 7-8, 2005 FAC Meeting 1 Installation Alignment,
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
1 Heinz-Dieter Nuhn 1 BFW Results June 2009 FAC BFW Results Heinz-Dieter Nuhn – LCLS Undulator Group Leader June 9, 2009.
Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center LCLS Undulator Physics.
Robert Ruland Intra Girder Assembly and Alignment - October 20, 2005 Internal LCLS Undulator Alignment and Motion Review 1 Intra.
1 Heinz-Dieter Nuhn 1 Undulator Commissioning August 2009 FEL2009 Undulator Commissioning, Alignment and Performance Heinz-Dieter.
April 16, 2007 Heinz-Dieter Nuhn, SLAC / LCLS Undulator Physics Issues 1 Undulator Physics Issues Heinz-Dieter Nuhn, SLAC / LCLS.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
J. Welch Talk MMF 10/14/04 LCLS Magnetic Measurement Facility Requirements Functional Temperature Vibration Earth's.
Zachary Wolf LCLS Undulator October 30, LCLS Undulator Tuning And Fiducialization Zack Wolf, Yurii Levashov, Achim.
J. Pflüger / DESY - Radiation Damage Workshop Stanford June 19, 2008 Radiation Damage Study at FLASH using the Diagnostic Undulator J. Pflüger, J. Skupin,
Geoff Pile LCLS Und. System Fabrication FAC 29 th, 30 th & 31 st October 2007 LCLS Undulator System Fabrication Schedule FAC.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
1 Heinz-Dieter Nuhn 1 Undulator Plans June 2009 FAC Undulator Commissioning Heinz-Dieter Nuhn – LCLS Undulator Group Leader June.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
Zachary Wolf Undulator Oct 12, LCLS Undulator Tuning Zack Wolf, Yurii Levashov, Achim Weidemann, Seva Kaplounenko,
DELTA Quadrant Tuning Y. Levashov, E. Reese. 2 Tolerances for prototype quadrant tuning Magnet center deviations from a nominal center line < ± 50  m.
Undulator Working Group Summary Heinz-Dieter Nuhn – Alexander Temnykh Presented at Friday, March 9, 2012.
Technical Challenges and Concerns S. Sharma and R. Alforque, R. Beuman, C. Foerster, E. Haas, E. Hu, P. Montanez, P. Mortazavi, S. Pjerov, J. Skaritka,
Radiation Monitoring at the Undulator System Heinz-Dieter Nuhn – LCLS Undulator Group Leader Presented at Wednesday, March 7, 2012.
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Commissioning Samuel Krinsky-Accelerator Physics Group Leader NSLS-II ASAC Meeting October 14-15, 2010.
The Stripping Foil Test Stand in the Linac4 Transfer Line
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
Catherine LeCocq, SLAC Alignment Plan for the LCLS Undulator IWAA 2006,1 Alignment Plan for the LCLS Undulator Catherine.
What did we learn from TTF1 FEL? P. Castro (DESY).
Overview Preparatory work at the MML BBA to define the reference orbit
Possible causes for SPS ZS2 misalignment
Magnetic Measurements For The LCLS Undulator System
LCLS Undulator Fiducialization
Undulator Tolerances for LCLS-II using SCUs
SCU Next Phase Meeting July 8, 2014.
Phase Adjustments: K vs
A Cold SCU Phase-Shifter
Beam-Based Alignment Results
Overview Pre-Beam Checkouts
Undulator System Components Status Dean Walters
Undulator Line Design Liz Moog, Advanced Photon Source April 24, 2002
High Level Physics Applications for LCLS Commissioning
Undulator Cost & Schedule Patric Den Hartog, ANL April 24, 2002
Undulator Tuning Status Heinz-Dieter Nuhn, SLAC / LCLS for Zack Wolf, Yurii Levashov, Achim Weidemann, Seva Kaplounenko, Scott Jansson, Ralph Colon, Dave.
LCLS Undulator System Status and Schedule
Undulator Tuning Status
LCLS Undulator System Status and Schedule
Undulator Physics Diagnostics / Commissioning Strategy Heinz-Dieter Nuhn, SLAC / SSRL August 11, 2004 Undulator Overview FEL Parameters Diagnostics and.
Introduction [Documents and Parameters]
Final Break Length Choice AC Conductivity Wakefields
Physics Requirements for Conventional Facilities
Undulator Alignment Plan
Alignment Diagnostic System Status
Breakout Session SC3 – Undulator
LCLS Undulator Magnetic Measurements
Undulator Physics Issues Heinz-Dieter Nuhn, SLAC / LCLS July 11, 2007
Presentation transcript:

Heinz-Dieter Nuhn – LCLS Undulator Group Leader May 14, 2009 Undulator Plans Heinz-Dieter Nuhn – LCLS Undulator Group Leader May 14, 2009

25 Undulators Installed

Answers to Committee Questions What in project scope activities remain for LCLS undulators? ANSWER: There are 5 undulators more to be tuned, a total of 8 undulators to be installed. There are also ANL BLMs in scope which need to be made. What improvements can you anticipate in the area of undulators and undulator diagnostics for LCLS looking ahead to operations? ANSWER: Upgrade of signal processing for existing BLMs to add integration capability. K-vs-temperature calibration for undulator segments to improve the estimate of undulator K values at deviating temperatures. Procurement of precision temperature sensors for undulator segments. Procurement of additional ANL-Style BLMs (under consideration) some additional are now in scope, a full complement would need an addition to scope.

Answers to Committee Questions Can you present a summary of ‘Lessons Learned’ from the undulator construction activities supporting LCLS? ANSWER: Tuned Undulators were initially stored in an uncontrolled temperature storage area (building 750 pit, ). We ended up re-tuning all undulators. Since we had no data and mechanical calculations would have been too complicated and expensive, we should have tested the temperature limit of undulators. Interference fit of undulator shims and vacuum chamber occurred this was due to many design iterations of vacuum chamber. This should have been discovered at fully integrated model. Heavier bolts should have been used to hold the pole assemblies to the titanium strong back. Undulator feet design should have been finalized during final design review and not during measurement and implementation stage. Longitudinal thermal expansion was not considered. Temperature excursions caused big problems for us. Canted poles are a great idea. Without them, we would not have been able to set K to 0.015 %, i.e., we would not have been able to set the gap to 0.9 µm with parallel poles. Spending money on a good measurements lab is essential. We have had to overcome many unnecessary obstacles such as air conditioner failures, air compressor failures, space constraints, bad cranes, etc. These take up a lot of time and energy.

Girder Position / Temperature Stability Temperature fluctuations and ground motion cause changes in Undulator strength, which depends on Temperature Beam trajectory Electron beam trajectory (phase errors) due to Quadrupole position instability Observed stability of girder positions and temperatures is better than expected.

Temperature at All Girders Upstream U23 Center U23 Downstream U23 On Girder Mounted to Undulator

Temperature Recording Girder 16 SHUT DOWN (UND INSTALLATION) REPAIR OPPORTUNITY DAY (ROD) HVAC SETPOINT ADJUSTMENT 50 mK

Girder 15 Movement (18 h) During ROD (11 h) Mechanical Hysteresis >1 µm

Girder 13 Stability During 19h Operation 200 nm

Girder Stability During 2008 Winter Break RMS Position Change < 1 µm Courtesy of Franz Peters

K Adjusted for Temperature Deviations

Use of (T-)Corrected K Values TEMPERATURE CORRECTED K K ADJUSTMENT RANGE TAPER REQUIREMENT

Radiation Control and Monitoring Undulator radiation damage is greatly reduced through Machine Protection System (MPS) hardware interlocks that inhibit beam to the undulator hall when PEP/ANL type BLM signals are above threshold Beam loss fiber signals are above threshold Horizontal and/or vertical trajectory is outside ±1mm Comparator toroids indicate beam loss. Any of the upstream profile monitors is inserted More than 1 BFW is inserted or a BFW is moving A regular TLD monitoring program is in place (s. below) A regular undulator replacement program will start soon (s. below)

TLD Readings at First Undulator LOCATION WEEK 1 PHOTON [rem] WEEK 2 PHOTON [rem] WEEK 3 PHOTON [rem] U25:ANL-BLM 0.081 0.106 0.051 U25: PEP-BLM 0.042 0.048 0.030 U25: Back +X 0.065 0.008 0.033 U25: Back +Y 0.012 0.071 0.064 U25: Back -X 0.039 0.026 0.029 U25: Back+Y 0.013 0.014 U25: Front +X 0.112 0.093 0.072 U25: Front +Y 0.217 0.105 0.110 U25: Front -X 0.046 0.055 0.025 U25: Front -Y 0.141 0.123

Dose During Initial X-Ray Operation e-folding length 8.7 m Increased TLD Readings are expected to be predominantly low energy synchrotron radiation, not to cause significant magnet damage

TLD Replacement Program Thermo Luminescent Dosimeters (TLDs) are mounted inside the Undulator Hall and are regularly replaced and evaluated Baseline 10/3/2008 – 12/9/2008 (10 TLDs) Startup 12/12/2008 – 12/17/2008 (12 TLDs) 1st Undulator 1/28/2009 – 2/4/2009 (15 TLDs) 1st Undulator 2/4/2009 – 2/11/2009 (14 TLDs) 1st Undulator 2/11/2009 – 2/18/2009 (18 TLDs) 1st Undulator 2/18/2009 – 3/2/2009 (48 TLDs) FEL Operation 3/24/2009 – 4/22/2009 (68 TLDs) FEL Operation 4/22/2009 – 5/6/2009 (125 TLDs) FEL Operation 5/6/2009 – … (128 TLDs) FEL Operation … Latest TLD placements include detection of neutrons and high energy gamma through use of moderators and Ti and Pb absorbers. TLD volume is expected to taper down after initial observation period.

Undulator Replacement Program Undulators will be periodically removed from the Undulator Hall to be re-measured at the MMF to check for radiation damage. A “test”-undulator was re-measured after several weeks of beam operation. No damage was found. First undulator that participated in FEL run is scheduled for re-measuring in June. Depending on MMF availability, up to 2 undulators per month will be removed from the Undulator Hall for checking. After the undulators have been found undamaged they will be reinstalled onto the original girder.

Summary Undulator tuning and installation close to completion Temperature and girder stability well within tolerance Beam loss control and radiation monitoring is in place High radiation levels at initial FEL operation are expected to be predominantly low energy photons that should not generate demagnetization Electronics components may need additional shielding Undulator replacement program will start soon

End of Presentation