Monday :00 – 15:00 : Stable beams 15:30 : Recover…

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
Weekly summary Summary Week /19.07 M. Lamont & J. Wenninger for the OP team and for all colleagues from the various groups 8:30 meeting 1.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Injection issues overnight 10:50 Access  QPS & EPC  Vacuum leak SPS – magnet to be replaced Monday – cycling for FT and LHC only over the weekend 12:15.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
Tuesday 7 th August - morning 07:10 Reinjection after loss of fill 2920 to UFO near ALICE  26 pb -1 in 1h16m; peak lumi 6.4e33 cm -2 s -1 08:10 dump at.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Week 13: R. Assmann, J. Wenninger
Floating MD week 28 summary
Wednesday 8.9 External crossing angles:
Day :00-11:30: Optics at 3.5 TeV Optics re-measured with AC-dipole. Excellent reproducibility. Small emittance increase from AC-dipole. Collapsed.
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Saturday 24 March 2012.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday :00 Stable beams 9_6_6_6 13:40 Access.
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Saturday 30th June - Sunday: Rocky !
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Summary week 30 Week 30 R. Bailey & J. Wenninger
LHC commissioning Week 38
Summary of Week 16 G. Arduini, J. Wenninger
Note: squeeze in Atlas, CMS, LHCb and Alice on going
Wed :40 Lost S78 - QPS controller.
Friday 31st August & night
Monday Morning – recovery from cryo.
Friday :00 machine setup for luminosity run. Better b-to-b stability from injectors. 01:58 stable run with 228 bunches 11:00 luminosity leveling.
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Friday morning 10:30 Optics measurements and corrections.
Friday Morning 7:30 injection for fill 2908
Wednesday 03/11 – The Plan Finish electron-cloud program:
Programme for VDM measurements Friday Oct 15
Saturday 7th May Sat – Sun night
(on behalf of the LHC team)
Sunday/Monday & :30 Stable beams. Fill #1851.
Aims for the week Recover from technical stop and precycle at 10A/s
Thursday morning 08:45 Stable beams fill 2855 for ATLAS/CMS VdMs.
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Thursday Fill 1364 (24 bunch) dumped at 07h
Tuesday morning 08:30-09:00 Squeeze with probe.
Summary week 18 Intensity ramp up & production
Tue/Wed 12/ :00 Probe beam back again
Thursday 26th July 13:21 Fill 2880 beam dumped
Collective effects in the SPS and LHC (longitudinal plane)
Monday 6th 07:39 Dump fill #1854, RQ6.L2 tripped, followed by access
Saturday Wire scans at end of fill 1253 B1H : 4.2 B1V : 4.3 B2H : 5 B2V : 7.2 Beams dumped (after ~14h of collisions) Some issues during refill.
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
LHC Status Tue Morning 22-Aug
07/08/2010 Fill #1264 dump at 02:14:38.
Monday :15 fill 3523 dumped by BPMs IP6
Thursday 30th September De-bunching test
Wednesday h18: 228b fill lost just before start of ramp.
Friday 15th February - morning
Tuesday – Morning and Evening
Another Immortal Fill….
Tuesday 6th April 8:00 Injection studies 16:00 RF studies
Saturday 15th May One bunch 1 e11 per beam 09:57: start ramp
31/3/2010 Difficult day… but at the end stable beams.
Tuesday
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Monday 17.05 06:00 – 15:00 : Stable beams 15:30 : Recover… 18:00 : Injection for high intensity ramp Longitudinal blowup : switch on phase loop after some seconds only… Observed ‘large’ amounts of un-captured beam around the ring (dump BTV). 20:15 : Start ramp Longitudinal emittance 0.7 eVs (B1), 0.58 (B2) as compared to 0.3 eVs over the weekend. Octupoles on. Ramp start: Emittance B1: ~ 4.7 um in H (chirp !!) and 3.2 um in V. Emittance B2: ~ 3.2 um in H and 3.3 um in V. Flat top: Emittance B1: ~ 7.9 um in H and 5.5 um in V. Emittance B2: ~ 7.3 um in H and 4.7 um in V. 8:30 meeting

Ramp 1e11 8:30 meeting

Bunch length in ramp Over the week-end : 0.6 ns at 3.5 TeV 8:30 meeting

Monday 17.05 21:00 : Flat top Base orbit for collimator setup today (rms wrt injection orbit ≤ 80 um) Chromaticity in both beams approx. +12 (H) / +8(V). Lowered Q’ to around +5 both planes and beams. 22:30 : Sudden trip of 24 60 A CODs all over the machine ! Manage to save the beam by correcting in parallel with other CODs, orbit maintained within 0.25 mm. Lifetime to ~ 5 hours, almost no measurable loss. All CODs that tripped had kicks of < 10 urad, typical ~ 5 urad. Apparently the CODs received a large change request – OFB was OFF. Ghost command ?!! we had that before… 8:30 meeting

COD trips Apparently, all 60 A which were lost at 22.24:59 fell for the same reason: REF_RATE_LIM --> TRG|VOUT_OVER_VOLTAGE. The PCs received a request of more than 100 mA in 100 ms --> more than 6 V were asked. 8:30 meeting

Monday 17.05 22:35 : Lowered octupoles. Ok down to 10%, then losses on B2 at 5%. We manage to revert the trim in time. B2 bunch length increases. Trim to 0. First nothing happens, then after some tens of seconds the losses increase drastically, lifetimes < 1 h. Beams saved by going back to 5%. We need some octupoles, but clearly much less than what is programmed into the ramp now. 8:30 meeting

Beam becoming unstable… 8:30 meeting

Tuesday 18.05 01:00 : Prepare physics fill 05:00 : Stable beams 05:40 : Beam lost due to electrical perturbation Lost beams due to perturbations on power grid. RPTF.SR3.RQ5.LR3         RPTG.SR1.RD1.LR1         RPTG.SR3.RD34.LR3        RPTG.SR5.RD1.LR5         RPTG.SR7.RD34.LR7 and ALICE and LHCb dipoles FMCM triggers. 8:30 meeting

Tuesday 18.05 06:20 : Lost sector 34 during ramp down. Initiated by a PC fault. MPR3 investigating. Program of today: Recover S34 and precycle. Inject & ramp 1e11/beam for collimator setup at 3.5 TeV. Clean up orbit at 3.5 TeV. Then physics fill overnight. 8:30 meeting