Workshop on fire protection for physics research facilities 20-21 June 2017 European Spallation Source FCC study – Design solutions being proposed by the Infrastructures & Operations Working Group Updated to FCC week 2017 S. La Mendola HSE/SEE/XP 27-May-19 EDMS no: 1817640
Summary Civil engineering; Integration; Electrical distribution; Air management; (Reliability); Safety strategy; Discussion; Full presentations available at https://indico.cern.ch/event/556692/timetable/#20170529.detailed 27-May-19 EDMS no: 1817640
FCC Civil Engineering Optimisation and Design Development, John Osborne & Joanna Stanyard Shaft at point F is 476 meters deep! 27-May-19 EDMS no: 1817640
FCC Civil Engineering Optimisation and Design Development, John Osborne & Joanna Stanyard Shafts F and G are removed in this option. 30 km long bypass tunnel. 27-May-19 EDMS no: 1817640
FCC Civil Engineering Optimisation and Design Development, John Osborne & Joanna Stanyard 27-May-19 EDMS no: 1817640
FCC Civil Engineering Optimisation and Design Development, John Osborne & Joanna Stanyard 27-May-19 EDMS no: 1817640
FCC Civil Engineering Optimisation and Design Development, John Osborne & Joanna Stanyard 27-May-19 EDMS no:
Civil engineering for FCC-eh Interaction Region FCC Civil Engineering Optimisation and Design Development, John Osborne & Joanna Stanyard Civil engineering for FCC-eh Interaction Region 27-May-19 EDMS no: 1817640
Underground structures, F. Valchkova-Georgieva 27-May-19 EDMS no: 1817640
6 m FCC-hh 3D, dipole, compartment wall/cryogenic jumper, transport vehicle F. Valchkova-Georgieva 27-May-19 EDMS no: 1817640
Shafts, F. Valchkova-Georgieva 27-May-19 EDMS no: 1817640
Underground structures, F. Valchkova-Georgieva 27-May-19 EDMS no: 1817640
Tunnel cross section, FCC-hh, F. Valchkova-Georgieva 27-May-19 EDMS no: 1817640
Supply and distribution of Electrical Energy, Davide Bozzini 27-May-19 EDMS no: 1817640
Supply and distribution of Electrical Energy, Davide Bozzini Second and third source as well as uninterruptable supply are also defined 27-May-19 EDMS no: 1817640
Supply and distribution of Electrical Energy, Davide Bozzini 27-May-19 EDMS no: 1817640
A ventilation system for the FCC tunnel, M. Nonis, G. Peon 27-May-19 EDMS no: 1817640
A ventilation system for the FCC tunnel, M. Nonis, G. Peon 27-May-19 EDMS no: 1817640
A ventilation system for the FCC tunnel, M. Nonis, G. Peon 27-May-19 EDMS no: 1817640
A ventilation system for the FCC tunnel, M. Nonis, G. Peon 27-May-19 EDMS no: 1817640
A ventilation system for the FCC tunnel, M. Nonis, G. Peon Concept developed also for Cryo, d and b collimation, RF and beam dump points 27-May-19 EDMS no: 1817640
A ventilation system for the FCC tunnel, M. Nonis, G. Peon 27-May-19 EDMS no: 1817640
FCC availability studies, Andrea Apollonio, Arto Niemi Interesting approach: could be applied to safety systems; Note: accidental events (e.g. fire) were not included in the study; 27-May-19 EDMS no: 1817640
FCC safety strategy for the Conceptual Design Report, Th. Otto 27-May-19 EDMS no: 1817640
FCC safety strategy for the Conceptual Design Report, Th. Otto 27-May-19 EDMS no: 1817640
FCC safety strategy for the Conceptual Design Report, Th. Otto 27-May-19 EDMS no: 1817640
FCC safety strategy for the Conceptual Design Report, Th. Otto 27-May-19 EDMS no: 1817640
FCC safety strategy for the Conceptual Design Report, Th. Otto 27-May-19 EDMS no: 1817640
FCC safety strategy for the Conceptual Design Report, Th. Otto 27-May-19 EDMS no: 1817640
FCC safety strategy for the Conceptual Design Report, Th. Otto 27-May-19 EDMS no: 1817640
FCC safety strategy for the Conceptual Design Report, Th. Otto 27-May-19 EDMS no: 1817640
FCC safety strategy for the Conceptual Design Report, Th. Otto 27-May-19 EDMS no: 1817640
FCC safety strategy for the Conceptual Design Report, Th. Otto 27-May-19 EDMS no: 1817640
Open discussion Length of fire compartments; Compatibility of compartmentalization with Helium spill; Early fire extinguishing, guided evacuation and search & rescue by rail-mounted robots; Shaft cross section (protected stairs with no intermediate landings); Use of alcoves as rest areas (separate compartment); Hi voltage distribution in the tunnel / (dry) electrical transformers in the alcoves; Ventilation / smoke extraction system Safety approach Etc. 27-May-19 EDMS no: 1817640
Thank you for your attention! 27-May-19 EDMS no: 1817640
27-May-19 EDMS no: