Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
17/09/2012LHC 8:30 meeting LHC Summary Week 37 Coordination: Jorg Wenninger & Jan Uythoven.
Plan for start-up with beam Friday  19:00 Machine closed. Ramp for powering tests & pre-cycle  22:00 Pilots through nominal cycle up to collisions. Measure.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Tuesday 24 th July - morning 10:15 Operator dump of fill 2873  Initial luminosity: 5.83e33 cm-2s-1  12 hours stable beams  151 pb-1 delivered  Initial.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
– Machine closed. Ramp for powering tests & pre-cycle – Pilots through nominal cycle up to collisions. Measure chroma during squeeze. Check dump of pilots.
LHC Status Sat Morning 30-June Bernhard Holzer, Jan Uythoven Status Friday Late: preparing restart some issues... LHCb dipole tripped / router problem.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Wednesday 3rd October - morning
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Friday 30th September 06:00 Operator dump fill #2171, int. lumi about 75 pb-1 Previous operator dump from physics was on 14 September ! 07:00 Start of.
Summary of week 7 Hardware Commissioning:
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Tuesday 11th September LHCb dipole presently fault off
Saturday 30th June - Sunday: Rocky !
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Tue :25 Beams dumped due to RF vacuum interlock
LHC Morning Meeting - G. Arduini
Tuesday 22nd January - morning
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Wednesday 31 October: Morning
Tuesday Fill 1494 dumped by operations at (~ 0.25 ub-1 in ~6.5 h): LSS6 BPM interlock test 13:00 Fill 1495 dumped by RF dump (cavity quench) 14:00-17:30.
Thursday morning 09:30 Dump of pPb fill.
Lost at 12:05 to power converter (RTQX2.R1) problem
Friday 31st August & night
Friday day 00:51 Fill #1862 Beams lost to inner triplet skew quad power converter fault. Delivered lumi 33 pb-1 Access required for repair RQSX3.L1 converter.
LHC Morning Meeting - G. Arduini
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Tuesday 20 March 2012.
Week 35 – Technical Stop and Restart
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Friday :00 machine setup for luminosity run. Better b-to-b stability from injectors. 01:58 stable run with 228 bunches 11:00 luminosity leveling.
Friday morning 10:30 Optics measurements and corrections.
Wire almost entirely through beam before BLM triggers dump
LHC Morning Meeting - G. Arduini
Not the most productive 24 hours on record
Friday Morning 7:30 injection for fill 2908
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Wednesday 9:08 Fill 3214 dumped by OP after 5:26 hours in stable beams
Thursday morning 7:20 – 12:30 faults of BLM sanity check, RQX.L8 QPS trip and iris scanner in UJ47. Access: Pt 8 for ELQA on RQX.L8 (The voltage.
Monday – Morning Fill 3265 stable beams since 1:31
Aims for the week Recover from technical stop and precycle at 10A/s
Monday 24 October hours of 25ns MD
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Saturday 3rd November - morning
Saturday Nov Stop proton operation. Switch back to ions
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Thursday 26th July 13:21 Fill 2880 beam dumped
Thursday – Morning Energy matching at injection with H CODs
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Monday 11th June 08:10 Beam dumped in the ramp by OP. OFB did not start its function and kept the injection orbit. 08:50 Switch LHCb polarity to negative.
Thursday 22 September 2011.
Saturday :42 stable beams fill 3541
Monday :15 fill 3523 dumped by BPMs IP6
LHC Morning Meeting - G. Arduini
Tuesday In the morning test cycle with probe for Q’ measurement.
Wednesday 16th May 03:05 beam dump, RF fault crowbar problem on module M1B2 06:09 Another crowbar at injection. Access for RF; problem Beam Imminent Warning.
Wednesday 23/2 Thanks CRYO!!!.
Thursday
Wednesday h18: 228b fill lost just before start of ramp.
Another Immortal Fill….
Wednesday morning Waiting for PS – problem on RF cavity.
Monday 14th May 00:03UFO at BLMQI.06R8.B2E10_MQML. Beam dump Re-steering required for TI2 03:28 STABLE BEAMS # e11 ppb, 4.11e33 cm-2s-1 13:36.
Tuesday
Presentation transcript:

Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams colliding at 1 km. Start of collimator and RP setup. 12:45 Dump. Access for RF, line 2B1. Access LHCb. 17:30 pPb MD. Problems to inject 200 ns p+ beam. BPMS IP6 interlock About 1 hour no beam from PS. 21:30 Again trip of line 2B1: isolate system Struggle with interlock BPMS o-night. 04:20 all p+ bunches injected. 04:35 Dumped pn BPMS: pPb did not make it, but important lesson learned Changed LHCb polarity and commission new collision beam process 06:38 Ramped with 2 x 2 x 6 bunches 08:12 Dump. 15/09/2012 LHC 8:30 meeting

Second part of b* = 1000 m Dump at 12:45 Optics check with 2 x 3 pilots done o-night. Dumped at 7:00. Filled with 2 x 3 small indivs of about 3e10 p+ for collisions TOTEM and ALFA collimator and pot set-up. Scraping and some retraction to take some data. Dump at 12:45 TOTEM @ 0.521 mm ALFA touching the beam 15/09/2012 LHC 8:30 meeting

RF klystron 2B1 Good part of the afternoon access for RF power team to repair the klystron of line 2B1 Same problem since a few days Switched back on end of the afternoon Tripped again in the evening Decided to isolate the klystron again and run without Cannot take high intensity beams like due to cavity beam loading 15/09/2012 LHC 8:30 meeting

pPb MD Plan to inject 318 p+, max 2e10, against 4 Pb bunches Pb injection fine, problems with RF/bucket/super cycle seem to be fixed p+ injection difficult. Dumped by BPMS in IP6 Struggle throughout the night Rhodri came in for BPMS. Reduce bunch intensity. BPMSA.A4L6.B1 vertical channel shows additional triggers even with one probe of 1e10. This channel more sensitive than others. 04:20 all p+ bunches injected. 04:35 Dumped on BPMS: pPb did not make it, but important lesson learned: needs work from BI and see which additional BPMS attenuators will be needed for the proton – ion run 15/09/2012 LHC 8:30 meeting

Test ramp with 2 batches of 8 Reversed LHCb polarity to negative Split beam process: going into collision first in point 1 and 5, then in 8 Quite some corrections for going into collisions in 1 and 5 Beam position at collimator Needs to be corrected – reason for tests 15/09/2012 LHC 8:30 meeting

The Plan This morning: Switch SPS to Q20 optics and set-up injection into the LHC End morning / beginning afternoon: RF module repair of line 2B1 Cable replacement by RF piquet Two options If RF module fixed go to physics with Q20 optics but lowish bunch intensity as collision in 1 and 5 might not be optimum If RF module not fixed, no high intensity (physics) beams until the TS3 on Monday morning. Will go to MD program until Monday morning 15/09/2012 LHC 8:30 meeting