STATUS of INFN contribution to ESS-accelerator

Slides:



Advertisements
Similar presentations
Laboratori Nazionali di Legnaro (Italy) DTL design status A. Pisent.
Advertisements

Status of the SPL cavities at CERN I.Aviles & N. Valverde on behalf of SPL team 1I. Aviles & N. ValverdeLund, 11 December 2013.
Question 27: Outline the key steps for industrialization of machine components and the likely remaining vulnerabilities in achieving them. Achieving industrialization.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
WU1 - Management S. Gammino (INFN). WU1 Management and TDR preparation: overview and criticalities 2 The WP6 aim is to define the best design of the Warm.
Summary of WG 2 - cavities W. Weingarten 15th SPL Collaboration Meeting CERN - 25/26 Nov Cavity WG.
1 Status of the CLIC two-beam module program A. Samochkine, G. Riddone Acknowledgements to the Module WG members 4 February 2014 CLIC Workshop 2014 (3-7.
D.Proch, DESY; GDE meeting Vancouver 06 Technical systems: Cavity Report Overview on costing activities for ILC –European costing method Overview industrial.
The ESS Linear Accelerator
LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.
Accelerator/ Medium Beta Cavities Paolo Michelato INFN Milano - LASA April 21, 2015.
Medium Beta Cavities Paolo Michelato, Paolo Pierini, and Carlo Pagani INFN Milano - LASA.
Medium beta cavities Paolo Michelato, Paolo Pierini, Carlo Pagani INFN Milano - LASA.
ESS RFQ PROJECT RISKS Anne-Catherine CHAUVEAU 14 January 2016.
Proposal for ESS DTL Roadmap. Divide Into Four Phases 1.Conceptual Design Phase (In progress) 2.Technical Design Phase 3.Prototyping Phase 4.Construction.
THE LINAC4 RFQ – Experience with Design, Fabrication and Tuning C. Rossi and the RFQ Project Team GSI Review – 20 November 2013.
Details on the Accelerator Installation Plan E. Sargsyan & L. Lari 20 April 2016.
Wolfgang Vinzenz FAIR Proton Linac 10 th FAIR MAC November 25 th and 26 th 2013 Proton Linac 1 Status Buncher Design  Rectangular design, longitudinal.
ESS The INFN in-kind contribution to the accelerator of the European Spallation Source.
Pierre Bosland 4 TH OF FEBRUARY 2016 COORDINATION COMMITTEE FR-SW AGREEMENT STATUS OF THE FRENCH ACTIVITIES UNDER THE RESPONSIBILITY OF CEA.
DTL prototype summary and production sequence F.Grespan LNL _06_22 CDR.
LASA status for medium-beta cavity Paolo Michelato.
Drift Tube Linac CDR Introduction, general aspects
ESS DTL: Prototyping M.Comunian - F. Grespan – P. Mereu Lund– 10/04/2013F.Grespan.
M. Munoz April 2, 2014 Beam Commissioning at ESS.
Accelerator/ Medium Beta Cavities Rocco Paparella on behalf of INFN Milano – LASA ESS Team April 21st, 2016.
H-ECCTD KICK-OFF DEVELOPMENT PLAN AND SCHEDULE 16/03/2016.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
ELENA installation progress F. Butin / ELENA collaboration.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
P. Bosland CEA-Saclay Collaboration Board meeting Copenhagen 14/04/ Status of the French activities under the responsibility of CEA Philippe CHOMAZ.
DTL F.Grespan – A.Pisent – P.Mereu – M.Poggi-M.Comunian-R.De Prisco LNL– 05/05/2014F. Grespan.
Laboratori Nazionali di Legnaro (Italy) DTL design A.Pisent ESS LNL 2012.
ISTCInternational Science and technology Center, MoscowOfficial Coordinator BINPBudker Institute of Nuclear Physics of Siberian Branch of Russian Academy.
CERN – ENGINEERING DEPARTMENT: A. Dallocchio on behalf of EN-MME
ESS Program Plan and Schedule Update
WP High Beta Cavities Delivery
Linac4 & SPL Status of preparation and Opportunities M. Vretenar (R
Status of the M-ECCTD F. Peauger - P. Bosland
High energy beam transport.
Bruno POTTIN, Anne-Catherine CHAUVEAU
NCFE and Interfaces Meeting: DTL
RF cell Anders Sunesson RF group leader
Cryomodule test stand at ESS site
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
ESS cavity procurement via in-kind contributions
STATUS OF CIEMAT CONTRIBUTION TO CTF3 ( )
Francois and Lau EATM 17 July 2012
CSP 25th November 2010 Technical agreement number 3: overview
WP-46 XFEL 3rd harmonic system XFEL Project Progress Report (1-2010)
Complementary ISTC Projects #3888, 3889p
FCC R&D WP5 Cavity Fabrication Status May 2017 M
on behalf of the RF group
TBL, Status, Plans, Experiments
TIARA WP8 Status M. Biagini, INFN-LNF, for WP8 TIARA Mid-Term Meeting
Proton Source and LEBT Luigi Celona & Lorenzo Neri
Highlights from EU Global Design Effort
HIE-LINAC status report
IHEP Cryomodule Status
A. Bignami on behalf of LASA SRF Group
Ciprian Plostinar Workshop on Testing and Commissioning
Daresbury ESS In-Kind Contributions
Elettra – Sincrotrone Trieste S.C.p.A.
(Beam) Commissioning Plan
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
Accelerator NCFE Liaison Officer
Status of the ESS High Power RF Systems
ThomX – Commissioning Meeting – 25/01/2018
Accelerator Installation Schedule
Paolo Michelato LASA - Status of cavity documentation, fabrication, inspection and NCRs Laura Monaco INFN – LASA 10° ESS SRF Collaboration Meeting, 25.
Presentation transcript:

STATUS of INFN contribution to ESS-accelerator S. Gammino for INFN Oct .3rd, 2018

LNS-Catania: Ion Source and Low-Energy Beam Transport; ITALY I.N.F.N. LNS-Catania: Ion Source and Low-Energy Beam Transport; LNL-Legnaro: Drift Tube LINAC; LASA-Milano: Medium Beta Cavities; LNL-Legnaro: DTL Control System Elettra Sincrotrone Linac Magnets; Wire scanner Acquisition; Spoke RF Power Stations; Linac Magnets Power Converters; C.N.R. T-Rex VESPA WP2 Regional Hubs

2017-11-09 Source fully commissioned at INFN-LNS Milestones 1/3 2017-11-09 Source fully commissioned at INFN-LNS

Site Acceptance Review Back tracing simulation under going Stable EMU was not provided in time

2018-02-01 Source fully assembled in Lund by INFN-LNS team Milestones 2/3 2018-02-01 Source fully assembled in Lund by INFN-LNS team

2018-08-03 Source ready for commissioning in Lund Milestones 3/3 2018-08-03 Source ready for commissioning in Lund

Installation in Lund

ISRC&LEBT Documentations INFN is providing a shared folder collecting: Drawings Diagrams Cable specifications Manuals Factory acceptance test Guides Certification of conformities Interface drawings Non conformity reports The documentation is collected in folders organized following the Product Breackdown Structure. product breackdown structure e visione sito cloud: isrc-estrazione-drawings+ps+certificato rame, insulating column-drawings+certificato vuoto, magneti sorgente con documento completo, magnetron con manuale, lebt solenoidi drawings+ps+fat, chopper+disegni+diagramma blocchi+schematics+signal list, irisdisegni+manuale,supporti-disegni, base-disegni, fug, cavi, Interfacce documento edgar, cartella interfacce Standard dentro i disegni, guide, slide andrea+ornella^2 700 MB of documentations

Summer’18 till now Safety procedures approved Plasma on Beam tests under way Beam commissioning to be completed in mid-November Long run test in January

DTL IK contribution

DTL Layout 3.6 MeV 89 MeV

DTL layout 6 2

RFI dates (2018) Tank RFI Tank 4 20/03/2019 Tank 1 5/06/2019 Tank 3 3/10/2019 Tank 2 13/01/2020 Tank 5 19/03/2020 Note: the tank 4 completion is not critical, since the first tank to see RF will be tank 1

Deep drilling rough machining Drilling holes and heat treatment Tank Production Module Forged Deep drilling rough machining Drilling holes and heat treatment Final fine machining Metrology Delivery Cu-plating T4-M1 T4-M2 @ CERN T4-M3 T4-M4 T1-M1 T1-M2 T1-M3 T1-M4 T3-M1 T3-M2 T3-M3 T3-M4 T2-M1 T2-M2 T2-M3 T2-M4 T5-M1 T5-M2 T5-M3 T5-M4 Comment: Delivery Rate from CINEL approx. 1module/month F.Grespan

DT production Comments: 8 DT batches based on brazing oven capability Machinining Copper parts Machining SS parts Machining Stems (UMAS) Cu plating stems (Tobaldini) Brazing Test and metrology Re-machining EBW (Zanon) Final Machining, test, Metrology T4-1 (1-8) T4-2 (9-16) T4-3 (17-23) T1-1 (1-8) T1-2 (16-24) T1-3 (25-32) T1-4 (33-40) T1-5 (41-48) T1-6 (49-54) T3 (26 DTs) T2 (30 DTs) T5 (20 DTs) Comments: 8 DT batches based on brazing oven capability Machining optimized to 1 part/day Some delay from Stem cu-plating supplier Last 5 steps (BrazingFinal test) to be optimized to 3 weeks DT-BPM outsourced (CINEL)

Main Tenders Done On-going To be Done Forged Tubes Tank & Girder Machining Cu-Plating Tank RF windows LNL and TO milling machine Power couplers 2018 BPM connectors BPM cables DT – BPM DT-EBW CMM @LNL Stems 2019 Trolley Skid Tuners, Posts Movable tuners End Plates Brazing, sealing material Cooling material

Other activities Assembly test at LNL Sealing Alignment Mounting procedures

Other activities Bead pull on full scale DTL model Bead pull hardware and procedures personnel trained to measurements Stabilization and tuning demonstration

Conclusions The tank 1 RF tests are foreseen in fall 2019. To achieve this The high precision tank module and girder machining is proceeding and seems not critical in the schedule. The DT production has started, all the main beam elements are delivered, the exact production rate is being consolidated. The RF window tender is ongoing (summer 2018 we should have the two windows necessary). Concerning power couplers, end plates and other minor components the specs are ready and tenders are programmed within the end of 2018. The DTLW has been specified (and ESS is realizing it) while the logistic components (supports, trolley, dummy tuners…….) are under control. The tuning procedure was debugged on a low power model of tank2, and the sealing test has been mounted. The copper plating of the tanks is critical, since GSI has not accepted the contract. The production schedule for the other tanks fits with RFI dates (except for copper plating)

DTL MB contribution

ESS Medium Beta – Niobium Procurement The Niobium procurement was completed in September 2018. All the 482 sheets were scanned at DESY for inclusion of foreign materials and geometrical defects before delivery to cavity manufacturing company. The first batch was delivered to the company in January 2018. The second batch was delivered to the company in April 2018. Water Cut Sheets Surface Roughness Niobium Batch Boxes Niobium Ingot

COmponent COntrol DEvice ESS Medium Beta – Cavity fabrication Subcomponents production in full progress Half-Cells: IC, PC, EC Dumb-Bell: ID, TD End Group: EGP, EGC First cavities foreseen by November 2018 Ancilleries all in house End Group Coupler side Dumb Bells Pick Up Antennas EGC Details COmponent COntrol DEvice EGP Tuner rings

ESS Medium Beta Preliminary test and documentation Successful test on MBLG002 cavity (already tested at LASA) done at DESY to test the infrastructure Incoming control Cold test and related data exchange Outgoing control Successful test of documentation portal and data display dashboard om first half-cells and dumb-bells Document Management System based on INFN Alfresco ESS Dashboard developed in the framework of the European Brightness Program in collaboration with LNS colleagues

Cavities manufacturing at the company ESS Medium Beta - Planning First six cavities (for the M-ECCTD) First two cavities available 2017 2018 2019 2020 Cavities manufacturing at the company Last cavity delivered First two cavities test at DESY