Antietam Road Sidewalk Updates: Plans approved by VDOT in April 2016. All needed Right-of-Way and Easements attained in April 2016. Issues: During construction, the shoulder on the opposite side of the road will be available for pedestrian usage. Construction hours will be from 9:00am to 1:45pm Monday-Friday. Barricades will be placed to denote walking area. Timeline: Acquisition of VSMP and Site Development permits received in June 2016. Preparation of bid document to start in Summer 2016. Construction expected to begin late Summer 2016. Occoquan Magisterial District Quarterly Transportation Report | Tuesday, June 21, 2016