Monday :15 fill 3523 dumped by BPMs IP6

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
Plan for start-up with beam Friday  19:00 Machine closed. Ramp for powering tests & pre-cycle  22:00 Pilots through nominal cycle up to collisions. Measure.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
:00 meetingEBH 1  8:40 – 9:30 access for MKB (dilution kicker) LBDS B2 – PLC exchange  Pre-cycle  11:17 – 12:50 RF problem with ion injection.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
28/01/2013LHC 8:30 meeting Summary of Week 4 pPb physics Machine Coordination: Mike Lamont & Jan Uythoven Ion coordination: John Jowett.
LHC Status Sat Morning 30-June Bernhard Holzer, Jan Uythoven Status Friday Late: preparing restart some issues... LHCb dipole tripped / router problem.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Wednesday
Wednesday 8.9 External crossing angles:
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Saturday 24 March 2012.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Saturday 30th June - Sunday: Rocky !
LHC Progress Week 6 Coordination: G. Arduini, E.B. Holzer
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Tue :25 Beams dumped due to RF vacuum interlock
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Tuesday TOTEM and transverse loss map (1) OK
LHC Morning Meeting - G. Arduini
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
LHC commissioning Week 38
Thursday morning 09:30 Dump of pPb fill.
Lost at 12:05 to power converter (RTQX2.R1) problem
Note: squeeze in Atlas, CMS, LHCb and Alice on going
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Mike Lamont, Jorg Wenninger
Week 36 plan Todo’s: And also: 12+b injection.
Week 35 – Technical Stop and Restart
Summary of Week 26 Main aims: G. Arduini, B. Holzer, M. Lamont
Friday morning 10:30 Optics measurements and corrections.
LHC Morning Meeting - G. Arduini
LHC progress report Week
Sunday
Saturday 7th May Sat – Sun night
Summary Thursday h21: Stable beams fill #1303.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Aims for the week Recover from technical stop and precycle at 10A/s
Monday :20 beta beat corrections during squeeze for flat machine finished Afterwards fixing issues at injection: BPM rephrasing for B2 solved.
Monday 24 October hours of 25ns MD
Thu 6/4 End of fill #2470. ~1 pb-1 in 4 hours. Dumped by CMS BCM.
Summary week 18 Intensity ramp up & production
90m "proper" VdM scans in the 90m/10m optics
Thursday – Morning Energy matching at injection with H CODs
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Saturday :42 stable beams fill 3541
Plan for 1 m b* J. Uythoven & J. Wenninger
Saturday 12 March Morning: problem on RSD1.A12B2 – flow rate problem on the cooling water for the converter. 14:00: Loss map -500 Hz (positive energy offset)
LHC Morning Meeting - G. Arduini
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Saturday 06/11 Triplet R8 tripped during ramp for collision setup.
Tuesday – Morning and Evening
LHC Morning Meeting - G. Arduini
Another Immortal Fill….
Wednesday morning / afternoon
Monday 14th May 00:03UFO at BLMQI.06R8.B2E10_MQML. Beam dump Re-steering required for TI2 03:28 STABLE BEAMS # e11 ppb, 4.11e33 cm-2s-1 13:36.
Tuesday
HI2011 Commissioning Status
Monday 152 bunch operation summary
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Monday 4.2.2013 8:15 fill 3523 dumped by BPMs IP6 9:50 OFB gain settings increased by a factor 5, which corresponds to a reduction of orbit perturbations by a factor of 2.  Losses at max of 21% of BLM dump threshold 11:14 stable beams 3524 11:27 TOTEM and ALFA roman pots moved to physics setting 13:22 start testing B1 horizontal orbit bump in IP7, around RQ11.R7B1 Check if losses in this area can be spread more longitudinally 13:55 back to stable beams again 15:01 fill dumped by BPMs IP6

15:27 Interlock threshold relaxed on BPMSB. A4R6 15:27 Interlock threshold relaxed on BPMSB.A4R6.B1 (the one which dumped the last couple of fills)

Evening Filling 338 Pb 338 p with 5% less Pb intensity and marginally reduced transverse emittance from the injectors Losses up to 54% on MQ 11R7 18:52 stable beams fill 3525 19:30 RF TOT VOLT increased to 14 MV (plan further increase to 16 MV after a couple of hours) 21:02 beam dump: Trip of RQTL9.R3B2, no fully understood, EPC piquet suspects an overvoltage in the line that made the power converter trip During ramp down: reboot bpm crates (as recommended by Ralph Steinhagen)

Fast BCT B1 JJ. Gras: The problem with the fast BCT on beam 1 as been investigated. It looks like beam 1 high gain acquisition chain saturates for bunches around 1.6e10p. I forced BCTFR beam 1 to low gain chain and it behaved correctly during following fill. Fine tuning of the phase and scaling factors still need to be done...

Night 0:04 dump of fill 3526 after cogging by BLM 11R7: Orbit drift when switching on the OFB by 60-90um (BPMs flickering pink during the fill already) Problem with TOTEM: they will stay OUT till fixed during daytime Ralph Steinhagen was called: reboot cfv-ccr-ctlbst1 and cfv-ccr-ctlbst2 restarts OFSU and the feedback controller reboot the BPMLHCCONC_M under cfc-ccr-bqbpmlhc publication of position data still slow, otherwise all ok 3:12 stable beams fill 3527 3:23 RF voltage from 12 to 14 MV 7:35 beam dump of fill 3527 by BPMS in IP6

Stable Beams Statistics Fill Day Peak L [cm-2s-1] Stable beam [h] Int L [nb-1] Dump 3523 Mon 4/2 7.2E+28 4:22 0.74 BPMs IP6 Pb: 192; p: 216 3524 7.4E+28 3:14 (+0:33) 0.43 3525 10E+28 2:09 0.64 Trip of RQTL9.R3B2 Pb: 338; p: 338 3527 Tue 5/2 1.04

Planning To be decided – possible measures to further reduce BLM loss/threshold ratio in cells 9R7 and 11R7: BLM threshold increase Local orbit bump Tuesday: LHCb polarity switch Wednesday: VdM scan ALICE polarity reversal TBD pending decision on pp intermediate energy run High intensity test for BSRT 4 hours (+ 2 hours access if no pp intermediate energy run)

1.38 TeV configuration and setting up Jorg Wenninger / BE-OP-LHC W. Herr, S. Redaelli, M. Lamont

No change wrt injection 2013 1.38 TeV run configuration J. Wenninger 50 ns beam, full machine, not pushed. Un-squeezed optics (b* = 10/11 m). Crossing angles ±170 mrad (also IR8). Separation ±1.5 mm. LHCb in good polarity, ALICE in negative polarity (PC). Beam size ~120 mm. Provides ≥ 10 times larger L than in 2011. Pre-cycle maintained at 4 TeV (also ramp down from 4 TeV). With 10x larger luminosity than 2011 we need ~24 hours of stable beams for 2 pb-1 No change wrt injection Run Nb Ib Nc b* e (mm) L (cm-2s-1) Stored E (kJ) Pile-up 2011 80 1.20E+11 68 11 2.7 4.34E+30 2122 0.45 2012 1374 1000 2.2 7.75E+31 36451 0.54 5/30/2019 LHC 8:30 meeting

Setup J. Wenninger Offline: Online: Setup time ~ 24+ hours. Prepare ramp to 1.38 TeV based on truncated 4 TeV ramp. Collision BP. Settings of IR7(3) collimators to be defined. Online: Reverting to high-intensity proton OP  1 shift ? 1 cycle with probes for checkout, optics measurements. 1 cycle with 3 nominal bunches for collimator setup (TCTs), collision setup, first loss maps & asynch. dump test in collision.  1½ - 2 shifts. 2 cycles to complete off-p /betatron loss maps  1 shift. Setup time ~ 24+ hours. Plus 2 hours of access to set-up for the higher intensity 5/30/2019 LHC 8:30 meeting

Recap 2011 Thursday 17th March : 1 shift of setup. ‘Run’: Thursday 24th March evening – Monday 28th March 06:00. Un-squeezed, ~80 bunches, ~1011 ppb, Lp~ 4-5x1030 cm-2s-1, 35 hours of SB, Lint ~ 0.3 pb-1. Issues with interlock BPMs IR6 (bunch intensity too low). 5/30/2019 LHC 8:30 meeting

2013 scenario 1 50 ns beam, not pushed. Still to clarify radiation issues (injectors) – should be OK. Filling scheme? Here assume 1000 bunch crossings. Un-squeezed optics (b* = 10/11 m). Crossing angles 170 mrad (to be confirmed). Beam size ~120 mm. Provides ≥ 10 times larger L than in 2011. Run Nb Ib Nc b* e (mm) L (cm-2s-1) Stored E (kJ) Pile-up 2011 80 1.20E+11 68 11 2.7 4.34E+30 2122 0.45 2012 1374 1000 2.2 7.75E+31 36451 0.54 5/30/2019 LHC 8:30 meeting

2013 scenario 2 No 50 ns beam, single bunch schema. Squeezed optics. Beam size in triplet  b* limit ~2.5 m (scaling 0.9 m from 4 TeV). Standard coll. settings. No crossing angle needed. Provides ~10 times larger L than in 2011. To confirm: b* limit. Run Nb Ib Nc b* e (mm) L (cm-2s-1) Stored E (kJ) Pile-up 2011 80 1.20E+11 68 11 2.7 4.34E+30 2122 0.45 2012 /1 1374 1000 2.2 7.75E+31 36451 0.54 2012 /2 150 120 2.5 4.13E+31 3979 2.4 5/30/2019 LHC 8:30 meeting

Comments It is obviously possible to mix 1+2. 50 ns squeezed (with Xing angles). 50 ns beam situation to be confirmed. Radiation in the injectors just before LS1 start. b* limit to be confirmed. Depends on details of collimator settings. With 10x larger luminosity than 2011 we need ~24 hours of stable beams for 2 pb-1. 5/30/2019 LHC 8:30 meeting

Setup Offline : Online: Prepare ramp to 1.38 TeV based on truncated 4 TeV ramp. (Squeeze and) collision BP. Settings of IR7(3) collimators to be defined. Online: Cycle(s) with probes for checkout, optics measurements & corrections. Unsqueezed: 1 cycle / 1 shift. Squeezed: 1-2 cycles / 1-2 shifts. 1 cycle with 3 nominal bunches for collimator setup (TCTs), collision setup, first loss maps & asynch. dump test in collision.  2-3 shifts. 5/30/2019 LHC 8:30 meeting

Validation Validation time: Summary of setup time: Configuration Betatron H+V Off-momentum - Off-momentum + Asynch dump Flat top X ? Squeezed Collisions Validation time: Un-squeezed: 4-5 additional cycles. Squeezed: 6-8 additional cycles. Summary of setup time: Un-squeezed: 1.5-2 x 24 hours Squeezed: 2-3 x 24 hours 5/30/2019 LHC 8:30 meeting

Recap VdM setup Rather similar to un-squeezed, but no new ‘flat top’. But no optics work. Setup time: Started Monday 16th July at 10:00 Finished same day at 24:00. Validation: Betatron H+V, off-mom +/-, asynch dump test (in collision).  2 shifts – 100% machine availability. 5/30/2019 LHC 8:30 meeting