XRN Nov 19 Release - Status Update

Slides:



Advertisements
Similar presentations
XRN4361 – UK Link Release 2 - Delivery
Advertisements

XRN4572 – UK Link Release 3 - Design
Overall Project RAG Status
Overall Project RAG Status
Release 3 Plan Options Decision
Overall Project RAG Status:
Release 3 Update December 2018.
XRN4340 – UK Link Future Release 1.1
Overall Project RAG Status
R&N Timeline Release 2 Release 3 Feb-19 June-19
Release 3 Update November 2018.
XRN4361 – UK Link Release 2 - Delivery
EUC Project Timelines Key Upcoming Dates:
XRN4361 – UK Link Release 2 - Delivery
Release 3 Plan Options Analysis
Overall Project RAG Status
XRN4361 – UK Link Release 2 - Delivery
Release 3 Update 9th January 2019.
Overall Project RAG Status:
R&N Timeline June-19 Sept-19 (EUC) Nov-19 Minor Release D4
xrn4340 – UK Link Future Release 1.1
Release 3 Update 13th February 2019.
Potential Minor Release Drop 4 Timeline & Scope
DSC ChMC CSS Consequential Update 13th March 2019
Overall Project RAG Status:
XRN Nov 19 Release - Status Update
XRN Nov 19 Release - Status Update
June 19 Timelines Key Upcoming Dates:
4361 – UK Link Future Release 2
Release 3 Update 07th March 2018.
Release 3 Scope & Proposed Plan
Change Management Committee – Retail & Networks Update
XRN4361 – UK Link Release 2 Project Status Update
Overall Project RAG Status
Minor Release Drop 3 Timeline
4361 – UK Link Future Release 2
4340 – UK Link Future Release 2
Overall Project RAG Status:
Overall Project RAG Status:
XRN4361 – UK Link Future Release 2
Overall Project RAG Status
XRN June 19 Release - Status Update
XRN Feb 19 Minor Release - Status Update
June 19 Timelines Key Upcoming Dates:
XRN4361 – UK Link Release 2 - Delivery
XRN Nov 19 Release - Status Update
Release 3 Update 07th March 2018.
XRN4361 – UK Link Release 2 - Delivery
Retail & Networks ChMC Update
XRN4361 – UK Link Release 2 - Delivery
Overall Project RAG Status:
XRN November 2019 Release - Status Update
4340 – UK Link Future Release 1.1
UIG Task Force Progress Report
XRN June 19 Release - Status Update
Potential Minor Release Drop 4 Timeline & Scope
Minor Release Drop 3 Timeline
DSC ChMC Switching Programme Update 10th July 2019
XRN4361 – UK Link Release 2 - Delivery
XRN Nov 19 Release - Status Update
UK Link Timeline June-19 Sept-19 (EUC) Nov-19
UK Link Change Impacts and Release Update
XRN 4954 – MiR Drop 5 - Status Update
XRN 4927 – MiR Drop 4 - Status Update
Overall Project RAG Status:
XRN June 19 Release - Status Update
XRN June 19 Release - Status Update
XRN Nov 19 Release - Status Update
XRN4361 – UK Link Release 2 - Delivery
7.1 XRN4665 End User Categories (EUC) – Project Update
Presentation transcript:

XRN4828 - Nov 19 Release - Status Update 1st April 2019 Overall Project RAG Status: Schedule Risks and Issues Cost Resources RAG Status Status Justification Start Up and Initiation phase in progress and on track to complete in April Detailed Design plan to be finalised Market Trials phase discussed at ChMC and agreement reached in principle that this is not required for November 19 release. Consensus at DSG on 1st April was that a Test Summary report published by Xoserve would be sufficient Change Packs on track to be approved by 8th May Funding: BER for full delivery to be presented to ChMC in April 2019 Risk: There is a risk that the Nov 19 Release may be impacted by Pre-Production environment congestion due to multiple deliveries running in parallel Risk: There is a risk that due to multiple UKLink deliveries running in parallel there may be limited access to resources. The BER with full delivery costs will be presented to ChMC in April 2019. Weekly monitoring of Xoserve SME resources supporting multiple demands (e.g. BAU defects, Future Releases etc) is ongoing

XRN4828 - Nov 19 Release Timelines Key Milestone Dates: Receive supplier responses – 13/02/19 Supplier contract approval – 05/04/19 Approve and issue EQR – 04/02/19 Gain Business Case approval at IRC - 13/03/19 PID approval 12/04/19 Detailed Delivery Plan approved – 05/04/19 BER Approval – 10/04/19 Design Change Packs Approval –08/05/19 Test Plan approval – 05/04/19 2019 Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec XRN4828 Nov-19 HLD & Change Pack Production Design Build & FUT ST & SIT UAT RT PT Test Cont. IDR PIS GO LIVE 08/11/19 - TBC 04/02: EQR Approval 10/04: BER Approval 08/05: Change Pack Approval