Project management Ray Veness.

Slides:



Advertisements
Similar presentations
11-13/10/2007 ILC BDS Kick-Off Meeting, SLAC, US 1 BDS Vacuum System Dr. Oleg B. Malyshev ASTeC Daresbury Laboratory.
Advertisements

HLTC 15 th April 2014 EDMS: Y. Muttoni EN-MEF-INT with the contribution of P. Fessia.
SPS New Wire Scanner Mechanics Review
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
Date Event Global Design Effort 1 Technical System Review John Noonan, ANL Yusuke Suetsugu,KEK Paolo Michelato, INFN Milano.
Impact on Project Planning and Cost. Agenda CERN Project Budget Planning Summary E. Gschwendtner, 9 April
VELO workshop, Amsterdam, april ‘00M.Ferro-Luzzi Difficulties with current mechanical design recent FEA results: to obtain sufficient stiffness of center.
In-Kind Contribution Management Update Allen Weeks March 20, Lund.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
WP3 Required interfaces for cryostat design / integration Patxi DUTHIL SPL 3 rd Collaboration Meeting, CERN, Geneva November 12 th 2009.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
Training in Vacuum Technology for JUAS 2013 Students
Compressor status AWAKE Technical Board meeting 19 August 2015.
Update on the Laser Beam Line
OLAV3 Engineering Integration and installation of experimental beam pipes: the case of LHC 7/8/20111P.Lepeule for VSC group.
Beam Instrumentation during LS1 Ray Veness on behalf of the BE/BI group.
Interface of FP420 to LHC FP420 meeting 28-Sep-2006.
Proton-Driven Plasma Wakefield Acceleration CERN Project Structure Edda Gschwendtner, CERN Lisbon Meeting, 22 June 2012Edda Gschwendtner, CERN2.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
TE-CRG Activities D. Delikaris, TE-CRG.
LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness.
O. Kester, NuSTAR annual meeting, 27/02/2013
Laser Line work package (WP6) AWAKE Technical Board meeting 19 May 2014.
Cost and schedule for ELENA Beam Transfer Systems W. Bartmann, J. Borburgh, E. Carlier, L. Ducimetiere, T. Fowler, M. Hourican, R. Ostojic, L. Sermeus.
Lucio Rossi for the LARP Internal Project Review Via videlink, June 10, 2013.
ELENA installation progress F. Butin / ELENA collaboration.
WP High Beta Cavities Delivery
Vacuum System P. Chiggiato TE-VSC
Crab Cavity Technical Coordination meeting:
LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
Beam-Gas Curtain (BGC) profile monitor tests in the LHC
Teleconference ACS – FREIA 31th May 2017
Plans towards CC in the LHC a US – centric perspective
Instrumentation for Accelerators Technologies for the HL-LHC
Brief Status SPS Prototype PSB Prototype Installed in LS1
Francois and Lau EATM 17 July 2012
HIE-ISOLDE HEBT vacuum system
ELENA installation and commissioning status
Gas jet based diagnostics for beam monitoring
LIU Wire Scanner Milestones June 2017
Installation of an Instrument on a CERN machine
CERN R&D plans and Infrastructures
Configuration Management and Layout Database ELENA Project
on behalf of the RF group
LHC Experimental Vacuum Systems Status October ‘07
Production and commissioning of the 2nd BGC
HL-LHC-UK: UK contribution to HL-LHC Crab Cavities and evolution
Wire Scanner Mechanics
Status of Questions and Actions from the meeting of 10/2016
Consolidation and Upgrade of the LHC Experimental Vacuum Systems
Target and Horn status report
ART-Review Schedule, Strategies and Conclusion
Upgrade Strategy for the Experimental Vacuum Systems
Beam-Gas Jet profile monitor for the e-lens
Beam-Gas Curtain (BGC) profile monitor: Project Overview and Status
STFC Contributions to the FCC Study
HL-LHC Safety Assessment Process
Beam Gas Ionization Monitor (BGI)
Status of the PANDA Cluster-Jet Target Quarter 1/2018
Installation of Photon Beam Transport to FEH
Daresbury ESS In-Kind Contributions
BGC Collaboration Meeting –
ThomX – Commissioning Meeting – 25/01/2018
Vacuum Controls Stephen Schuh Tom Porter 25 October 2006
Production Cryo HL-LHC BPMs
Outsourcing for the BGC
CERN-FAIR Steering Committee
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

Project management Ray Veness

Collaboration Agreements Cockcroft Formal collaboration agreement KE/3298/BE/HL-LHC Drafted in 2015, but finally signed in June 2017 Two final deliverables remain: Design report for a final gas-jet for HL-LHC (June 2018) Full prototype adapted for testing in the LHC (June 2019) GSI Two collaboration agreements, the latest being KE3036/BE addendum #1 Signed in July 2017 Deliverable was the Milestone 1.6 report for December 2017 Approved by CERN, needs to be published in CDS

Budget Core budget for the v3 prototype instrument 50/50 collaboration between CERN and STFC (UK) with Liverpool (Carsten) as budget holder Budget for specific LHC integration items (being) negotiated with HL- LHC Eg, cabling, vacuum sector activities. Budget for e-lens test stand Does this cover diagnostics?

Draft ‘who does what’ list   Budget Manpower Infrastructure for LHC     DIF (fibres) CERN     DIC (cables)     DIR (racks)     Gas piping     Cooling water for chips (?) Design deliverables   v3  Instrument design (CERN Design office) Cockcroft both     Engineering for integration (fellow/student)    LHC Integration design and drawings     ECRs and other CERN documentation Performance qualification documentation Instrument design document Validation on e-lens test bench     Integration drawing/work Both     Experimental operation (fellow?)     Cabling and services     Diagnostics for the e-lens bench?      Vacuum for LHC New LHC sector with vacuum pumps, gauges, valves and manpower CERN (VSC)     Vacuum cleaning, leak-test, acceptance of intermediate items     New vacuum beam pipes and sector (price from VSC) Control and operation     Control system and software for CCC operation     Control hardware Instrument hardware (Phase 1)   Interaction vacuum chamber, with any coatings Cockcroft CERN? RF insert and non-reflective coatings CERN Vacuum valves on the instrument (all-metal non-RF type) Instrument hardware (Phase 2)     Gas jet vacuum chambers (production, test) Flat nozzles, skimmers, baffles, Nozzle/skimmer alignment jig Special (CD etc.) nozzles     Optics, including lenses, MCP, camera, intensifier etc     Vacuum pumps and gauges for v3 (agreed with VSC)     Support structures in the LHC (design and manufacture) Ongoing development costs     Hardened optics     SR background (coatings etc)     instrument alignment     LHC diagnostics?