Missouri Stringless Paving: I-35 Unbonded Concrete Overlay

Slides:



Advertisements
Similar presentations
Volvo Construction Equipment Road Institute Paving Principles.
Advertisements

2014 Chip Seal Training Contract Administration Issues.
2D vs. 3D Grade Control Systems
County Road Administration Board Presenters: Mike Hasslbauer Technology Solutions Manager Western States Equipment Company
Pavements. Concrete –Rigid pavement Used where strength is an issue Runways, interstates and major roads –Continuous reinforcing Must have a good base.
Regional Asphalt Seminars Pavement Wedge Guidelines and Specifications EMMETT R. HELTZEL, P.E. STATE MAINTENANCE ENGINEER.
 Narrow roadway, with no shoulders  Poor pavement condition  AADT 405/150 – Low Traffic Volume  Ideal candidate for P.I.P.
1 PAVEMENT DATA ITEMS. 2 Climate_Shapes (4 LTPP zones) Soil_Shapes Metadata Estimates Section level data HPMS Pavement Data Summary level data.
Alternate Bidding in Missouri Transportation Estimators Association Annual Conference November 2-4, 2005 – Daytona Beach, FL Interstate 44 … South-Central.
ESTIMATING EARTHWORK Prof Awad S. Hanna.
Dr. Sophia Hassiotis.  Laboratory set up  Personal Protective equipment  Directions for mixing  Slump test  Cylinder casting  Cleaning up your station.
Composite Functions Consider a person working for a concrete contractor. One of his jobs is to estimate the cost for the product to put in a concrete driveway.
Partial Underground Analysis– TRTP Project Project Segment 8A Corridor October 29, 2011.
Profile elevations Sometimes the profile is too steep to illustrate on our profile sheet so we have to break the profile. This partial profile illustrates.
Bell Work: Becky reduced the size of the image on the computer screen by 40%. By what percent was the area of the image reduced?
Working with 3D Models in Design & Construction Panel Discussion 1.
Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.
Principles of Paving rev Principles of Paving.
I. Advantages of Smooth Pavements: Longer Life Public Opinion Save Fuel Less Surface Maintenance II. Ways to Ensure Smooth Pavements Subgrade and Subbase.
Florida Department of Transportation T EMPORARY B ARRIERS AND C RASH C USHIONS 1.
Pavement Preservation Protecting the Investment and the Environment R. Gary Hicks CP2 Center, Chico, CA Prepared for CEAC 2014 Conference March 26-28,
I-69 Team 3. Introduction History of project Proposed Route Challenges.
Wes Marshall, P.E. University of Connecticut March 2007
TEA, Portland, Maine Travis Koestner Missouri Department of Transportation October 20, 2006 Alternate Paving Update $$ Cost Control at MoDOT $$
Landscape Business Concepts
Planning for Earthwork Construction
Date Roadway Designer Resurfacing Restoration and Rehabilitation Kevin Jackson, Technical Director, TLI Bentley Systems, Inc.
Kersten Stelmach, Maggie Bailey, Hailey Frankland.
Sec. 7.4: Lengths of Curves. HOW CAN WE FIND THE EXACT LENGTH OF THE CURVE??
How to do proportions. How many feet are in 5 yards? Proportion STEPS Keep same units on top, same units on bottom. 1.and 2. What measurements you already.
ESTIMATING EARTHWORK DR. Nabil Dmaidi.
4/25/2017 9:25 AM Inertial Profiler Forum Intro to the Inertial Profiler Implementation September 28, 2015 © 2015 California Department of Transportation.
Fully-grouted repair, ready for Diamond Grinding.
Agriculture Mechanics I.  The volume of a triangular prism is equal to the area of the triangle times the length of the prism. ◦ V = ( ½ (b x h)) x l.
Stacy Hagenbucher.  Process Improvements  Clarification  Trends  Finals Tracking  Trends  Why Missing Dates  Additional Resource  Issues on sites.
IRI T ESTING IN N ORTH C AROLINA Presented by Christopher Bacchi, PE Vice President, Trimat Materials Testing, Inc. Raleigh, NC.
Using Reflective Crack Interlayer-
PCS900 AccuGrade 3D Paving Training 3D Design Models & SVO/AGO & TBC
How are Highway Designs Actually Represented in Surface Models for Automated Machine Guidance and How Should We Control Them? Alan Vonderohe Construction.
© Awad S. Hanna, PhD, P.E.1 Estimating and Scheduling CEE 492 Lecture 5 ESTIMATING EARTHWORK.
Retaining Wall Construction Building A Block Retaining Wall Developed by: Dr. Teri Hamlin Georgia Department of Education.
John Donahue, P.E. Missouri DOT 5 th Annual Building Green with Concrete Workshop June 21, 2012.
Jerry L. Larson IRMCA Indiana LTAP Basics of a Good Road
Port Huron, Michigan Gregg Aukeman Andrew Dobbs Adam Mueller Manuel Torreira.
Brookeville Bypass Final Design Presentation Initech May 6, 2004.
Evergreen Highway Corridor Update Planning Commission Workshop March 22, 2016 Jennifer Campos, Senior Planner.
Micro-milling The Economics A Rehabilitative Strategy for Savings Presented By: Sheila Hines Georgia Department of Transportation.
Quantity Calculations Module 3. Quantity Calculations  Specifications  Post Bid Quantity Calculations  Production Quantity Calculations –Checking Yield.
CITY OF BELLEVILLE ROAD IMPROVEMENTS PROGRAM
Alabama Asphalt Pavement Association
TOTAL BRIDGE REPLACEMENT OF M-13 OVER CHEBOYGANING CREEK
Profile Leveling.
Site Grading Site Grading Civil Engineering and Architecture
Austin Bridge & Road Paving the 1st Formula One Purpose Track in the United States The 1st Formula One Track in the World to be 3D Paved In this session,
CONCRETE PAVEMENTS.
Estimating the Cost for the Concrete Pad
ACP Inspector Certification Homework (oops, not homework) Solutions
Transitioning to IRI for Pavement Smoothness
2018 Pavement Workshop May 23-24, 2018
Rectangular Coordinates Level control in trenches
Introduction Persons engaged in surveying are often called to determine volumes of various types of material. The most common unit of volume is cubic having.
Introduction Persons engaged in surveying are often called to determine volumes of various types of material. The most common unit of volume is cubic having.
ESTIMATING EARTHWORK Prof Awad S. Hanna.
Introduction Persons engaged in surveying are often called to determine volumes of various types of material. The most common unit of volume is cubic having.
Introduction Persons engaged in surveying are often called to determine volumes of various types of material. The most common unit of volume is cubic having.
ESTIMATING EARTHWORK Prof Awad S. Hanna.
NRRA Pavement Workshop 2019
NRRA Pavement Workshop 2019
ACEC Designer Training
Industry’s Perspective on Stringless Paving in Iowa: Research, Trials & Implementation Dan King, E.I.T. Iowa Concrete Paving Association.
Presentation transcript:

Missouri Stringless Paving: I-35 Unbonded Concrete Overlay 2019 NRRA Pavement Workshop May 23, 2019 John P. Donahue, P.E. MoDOT

I-35 in Clay County Northeast of Kansas City Project length approximately 8.3 miles in both NB and SB directions. Constructed in 2010. Existing pavement consisted of 4-8 inches of HMA on 9-inch JRCP (circa 1966).

I-35 in Clay County Pavement Design Mill HMA completely off. Install geotextile interlayer. Place 8-inch UBOL on over 7 miles of pavement in both directions ~ 200,000 yd2. Remaining 1+ mile of pavement at bridge approaches and underpasses reconstructed with 10-inch JPCP.

Project Limits

Estimating PCC Quantities Existing surfaces will have irregularities. Estimating for a surface that has yet to be uncovered even more daunting. ½” added to I-35 UBOL – part of contract furnishing quantities, but still considered (acceptable) overrun.

How to Pay for a Concrete Overlay Cubic yards for furnishing and placing Contractor has no risk Agency faces possible high overruns Asphalt already paid for this way (tonnage) Square yards for furnishing and placing Great for agency, no overruns High risk for contractor, especially on roads with a lot of surface irregularities

How to Pay for a Concrete Overlay Square yards for placing / cubic yards for furnishing Shared risk for agency and contractor Happy medium? Method of payment for I-35 UBOL

Optimum Profile vs. Minimum plan (or structural) thickness Minimum vertical curve length Conventional cross-slope Regular smoothness criteria vs. No significant overruns

Very difficult to reconcile competing issues!! Optimum Profile Very difficult to reconcile competing issues!! I-35 UBOL project set standard.

Post-Milling Problems Milled roadbed shot at 10-foot intervals with Leica Total Stations. Not surprisingly, old PCC did not consistently exhibit original plan sheet cross-slope of 1.56% (3/16” per foot). Applying 2.00% cross-slope, minimum 300-foot curve length and design thickness would have yielded ~ 25% PCC overrun (1/2” waste factor allowed ~ 6% overrun).

12

Profile Solutions MoDOT allowed Cross-slope to fluctuate between 1.56% and 2.25% Spot milling (emphasize ‘spot’) up to 2.5 inches in old PCC

Profile Solutions Carlson Road Rehab software run in milling mode to create best fit profile. Bottom of proposed pavement compared to top of existing pavement @ 10-foot intervals to check milling and leveling thicknesses.

Profile Solutions Cross-slope changes moderated to eliminate ‘butterfly’ effect.

Profile Solutions Profile raised or lowered accordingly until excess PCC reduced to ~ 6%. Milling depth checked for 2.5 inch limit. Saved 8500 cy or over $600,000 worth of overruns.

Impact of Profile Elevation Change on Total SB Project Length Elevation Above Control Profile Cut Volume (CY) Fill Volume (CY) 0” 3,044 211 ½” 1,998 507 1” 1,176 1,027 1 ½” 612 1,805 2” 280 2,815 2 ½” 111 3,987

Volumes by Triangulation (Prisms) Segment Example Volumes by Triangulation (Prisms) May 13 2010 Sta 829-90 to 907-74 Raise baseline profile 1.5 inches Cut volume: 149.90 C.Y. Fill volume: 224.79 C.Y. Area in Cut : 7,129.5 S.Y. Area in Fill: 13,626.7 S.Y. Total inclusion area: 20,756.2 S.Y. Average Cut Depth: 0.06 feet Average Fill Depth: 0.05 feet Cut (C.Y.) / Area (S.Y.): 0.021 Fill (C.Y.) / Area (S.Y.): 0.016 8-inch UBOL Qty: 4612.1 Concrete Overrun: 4.89%

Stringline Problems Strings are always corded pin to pin therefore they never truly follow a design profile Catenary effect (slack in string) Always in the way Must be checked constantly Limit job site access

Stringless Paving Advantages Eliminate time and effort of staking Reduce clutter Improve safety and mobility in work area Improve speed of construction

Guidance Systems Gomaco 2800 4-track paver equipped with a Leica PaveSmart 3D Machine Control System CAT 140H Motor Grader equipped with a Leica PowerGrade 3D Machine Control System 8 Leica TPS1200 Total Stations

Total Stations were placed approximately every 300 feet for line-of-sight with prisms. Transition time between Total Stations less than one minute. Line of Site

Final Profile Geometric criteria met. Minimum structural thickness obtained. Furnishing PCC overrun limited to ~ 6%. Paved surface diamond ground. IRI ranged from 20 to 37 in/mi.

Thank You! Questions? john.donahue@modot.mo.gov (573)526-4334