Prototype Fabrication, Economic and Flight Test Plan PDR ORION AEROSPACE Prototype Fabrication, Economic and Flight Test Plan PDR October 26, 2000 Patrick Dempsey Bridget Fitzpatrick Heather Garber Jong Soo Mok Keith Hout
ORION AEROSPACE Objectives Schedule Economic Plan Flight Test Plan
Schedule October 25 – Order Parts October 31 – CDR ORION AEROSPACE Schedule October 25 – Order Parts October 31 – CDR November 1-4 – Complete and test wing section November 4-12 – Construction of SID5 November 12-15 – Prepare SID5 for Flight Readiness November 16 – FRR November 17 – Begin Test Phase November 21 – First Official Flight
Economic Plan Wing Test Materials ~ $90 SID5 Materials ~ $189.89 ORION AEROSPACE Economic Plan Wing Test Materials ~ $90 SID5 Materials ~ $189.89 Man Hours (estimate) ~ 2300 Labor ($150/hour) ~ $345,000
ORION AEROSPACE Price Breakdown of SID5
Flight Test Plan Glide Test Straight Crooked ORION AEROSPACE Flight Test Plan Glide Test Straight Crooked 2. Taxi test (Low and High Speed) 3. Go and Touch (or the Reverse Touch and Go) -Short Hops 4. Take-off and Fly basic Pattern (Racetrack) 5. Land - Inspect SID5/Change Battery 6. Take-off and try some “Fun Stuff” 7. Don’t Crash
Check List Prior to First Official Flight ORION AEROSPACE Check List Prior to First Official Flight Steps 1-7 “Check out OK’(Especially Step #7) Complete Inspection of SID5 Ready SID5 for unveiling to Public Double Check Everything Double Check Double Check
ORION AEROSPACE Questions?