NRS 048-9 Ed.1: 2010 National Code of Practice: Emergency Load Reduction and System Restoration Practices CHECKLIST
Check list Legal and Regulatory status: Load shedding Check list Legal and Regulatory status: Are you aware that “Code of Practice” – NRS 048-9 Ed.1 has been implemented as a NERSA licence condition for emergency load shedding & curtailment ? Are you aware that NERSA requires you to submit your implementation plans in April. Implementation status - schedules: Have you decided whether you will shed your own load or be shed by Eskom ? If so, have you engaged/notified Eskom of this decision If you plan to shed your own load: Have you developed your Stage 1-4 schedules in accordance with NRS 048-9 Are your control staff aware that Eskom will call for Stages and NOT for MW’s? Have your schedules been published / made available to your customers Have you identified critical loads as defined by NRS 048-9 (e.g. hospitals, metrol rail, stadiums, water supplies, airports, etc) If so, have you implemented the measures called for each of these by NRS 048-9