Lessons from the 1st Safety Readiness Review

Slides:



Advertisements
Similar presentations
1 BROOKHAVEN SCIENCE ASSOCIATES Environment, Safety and Health Steve Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting March 29, 2012.
Advertisements

Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
Unit 8: Tests, Training, and Exercises Unit Introduction and Overview Unit objectives:  Define and explain the terms tests, training, and exercises. 
Tipologie di Audit e loro caratteristiche Riunione sottogruppo GCP-GIQAR 21 Marzo 2006 Francesca Bucchi.
M. Scharfenstein - ES&H Coordinator 8 June 2009
The ESS vacuum team has overall responsibility for all technical vacuum systems used on the: Accelerator, Target and Neutron Scattering Instruments and.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Edward T. Lessard ESHQ.
1 1. Some recent views ( ) 2 Linac tunnel
A Few Pointers from the Linac4 Beam Commissioning of Warm Linac Yngve Levinsen Beam Physics Section 05/02/16.
LINAC4 COMMISSIONING 1 LESSONS LEARNT DURING MY VISIT AT LINAC4 COMMISSIONING Evangelia Vaena, 02/02/2016.
Details on the Accelerator Installation Plan E. Sargsyan & L. Lari 20 April 2016.
Glendale Community College Why LEED? Why Commissioning? Blair Seibert, AIA, LEED AP, CSBA VERDE CONCEPTS Los Angeles.
Personnel Safety Systems Stuart Birch Senior Engineer, Personnel Safety Systems November 6 th, 2014.
PIP-II Environment, Safety, Health & Quality Assurance Strategy John Anderson Jr. DOE Independent Project Review of PIP-II 16 June 2015.
Accelerator Systems Integration Stephen Molloy Section Leader for Accelerator Integration April, 2016.
M. Munoz April 2, 2014 Beam Commissioning at ESS.
Accelerator Installation Plan: Graphical representation E. Sargsyan & L. Lari DRAFT - March March 2016.
ACCSYS Design Reviews J. G. Weisend II Deputy Head of Accelerator Projects.
Planning for Succession
ESS licensing process and Readiness Reviews
ESS cavity procurement via in-kind contributions
RAF9038 Final Coordination Meeting
Accelerator Operations Department Readiness (Part 2)
LINAC4 50 MeV phase BIS STATUS
FC facilitation of Installations
EP Experiments safety validation process Safety Permits
Project Charter <Project Name>
Project Charter START IT! By Catherine B. Calio, PMP
Statistics Governance and Quality Assurance: the Experience of FAO
Andreas Jansson, Lali Tchelidze
How to keep your Enterprise GIS Project on Track
Communication Plan PPT Template
Licensing update ESHAC #9, October 2018
Management System - update -
ESHAC #9 Safety Readiness Review “Lessons learned”
ESHAC meeting October 1-2, 2018
Mikael Jakobsson ESS Installation Manager
ESS Project Status Roland Garoby – Technical Director August 2018.
M. Scharfenstein - ES&H Coordinator 14 May 2009
Electron Beam Systems ETC and Methodology
RF systems introduction
Operations/Control room organization during commissioning
Ciprian Plostinar Workshop on Testing and Commissioning
Ian Evans SSRL Safety Office
Operations Section Leader
Bunker Internal Review Welcome & Charge
Welcome and charge to the committee
Testing Coordination at ESS
Integrated Safety and Environmental Management
PSS verification and validation
Configuration Management
Upgraded Injector Test Facility
ESS Management System SSM visit 24th October
PSS Verification and validation
On behalf of protection systems
Internal Audits Management Review Meetings
Radiation Protection Handbook
Safety Readiness Review (SRR) Thomas Hansson, ESH
Radiation Protection Updates
Preliminary Project Execution Plan
High Level Readiness Reviews
Licensing update ESHAC #7, October 2017
Critical Design Review Personnel Safety System: PSS0
ESHAC Meeting # Peter Jacobsson Head of ESH
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
Radiation fields During 1st stage beam commissioning
The Management System at Work (Ion Source and LEBT commissioning)
Accelerator Installation Schedule
Machine All Hands meeting #4 WoW-Ways of Working
Stuart Birch On behalf of Protection Systems Group
Presentation transcript:

Lessons from the 1st Safety Readiness Review Lali Tchelidze Operations Section Leader Accelerator Division October 18, 2018

INTRODUCTION

Commissioning stages Ion source and LEBT (75 keV), beam to FC - ongoing RFQ and MEBT (3.6 MeV), beam to FC DTL1 (22 MeV), beam to FC DTL2 to DTL4 (40 MeV, 57 MeV, 74 MeV), beam to FC DTL5 and SCL, beam to Beam Dump Full accelerator, beam to Target

Process to get to beam commissioning License Safety Readiness Review Beam Permit Beam commissioning/operation Hardware testing

Safety Readiness Review SRR process at ESS is equivalent of the Accelerator Readiness Review process for the national labs in the US. The purpose of the SRR process it to review the readiness to safely commission and operate a system. The SRR is a process by which hardware, personnel and procedures associated with commissioning and operation of the system is verified. SRR is organized by ESH&Q using external and internal (independent) reviewers. SRR1 (for ion source and LEBT) was performed on July 2018.

Beam Permit Pre-start items were finished, relevant equipment was handed over to the operations section and the beam permit was signed by the laboratory management on September 19th Final pre-requisites for beam permit are equipment handover and Operational Limits and Conditions (OLC). SSM observed SRR and SSM came for a surveillance meeting to ESS in early September.

LESSONS LEARNED

What went well We got beam! We have seen a very good team spirit and high degree of involvement and commitment from system owners. The weekly preparation and follow-up meetings were effective at getting the team together and working against the same goals. The vacuum sub-system commissioning, documentation and testing was very good and could be used as an example for how to do system development and commissioning. PSS0 system operating instructions and training was very good, the shift leaders have good experience as we have not had a single trip in a month. Equipment handover and release forms, also beam permit and revocation forms were successfully introduced. Morning standing meetings were successfully introduced and are been exercised, this enhanced coordination with the area coordinators.

What didn’t go well Sorting out the ability to energize systems was extremely and inexplicably delayed. The situation and discussions around the masking of interlocks highlighted the lack of clearly defined guidance and ownership.

What we should do better Give an authority (not just downwards but also upwards) and clear mandate to a person responsible for overall coordination and strategic planning across AD and ICS. Establish a good plan (consider dependencies, prerequisites, etc.) and allow more time to complete planned activities. For the next stage, don’t underestimate effort to re-install and re-test systems used today, as the set-up changes almost completely. Involve ESH earlier. Account for delays (e.g. if the electrical installation is delayed 3 weeks, move the SRR for 3 weeks). Establish core team. Ensure that the test results from partners are comprehensively documented. Follow the defined test plans and if some tests need to be omitted, justify by analyzing impact on safety or machine.

What we should do better Plan for longer time and more resources for commissioning activities. Base the future commissioning plan (number of people and time) on experience from this stage of commissioning. Put stricter requirements on documentation going into commissioning. Re-discuss and define the meaning/purpose of the equipment handover and have a staged approach. Perform handover before the SRR. Clearly define operations role and involvement in hardware testing and beam commissioning. Clarify the purpose and scope of the SRR, ensure that the beam readiness is included. The name is confusing.

Campus Thank you!