ESS Spoke cryomodule testing: cryogenic experience

Slides:



Advertisements
Similar presentations
Mar 13, Low-energy RHIC electron Cooler (LEReC) CRYOGENICS Mar 13, 2014.
Advertisements

The Use of Small Coolers for Hydrogen and Helium Liquefaction
February 17-18, 2010 R&D ERL Roberto Than R&D ERL Cryogenics Roberto Than February 17-18, 2010 CRYOGENICS.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
ORNL is managed by UT-Battelle for the US Department of Energy Commissioning and Operation of the Horizontal Test Apparatus at SNS Presented at: CEC/ICMC.
ESS Cryogenic System Process Design Philipp Arnold Section Leader Cryogenics CEC – ICMC 2015 June 29, 2015.
ESS cavities interfaces
July LEReC Review July 2014 Low Energy RHIC electron Cooling Roberto Than CRYOGENICS SYSTEM.
Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1.
ERL: G-5/e-Gun Cryogenic & Pressure Safety Committee Review ERL G-5/e-gun Beam Line Vacuum Failure Analysis April 24, 2009.
Test plan for SPL short cryomodule O. Brunner, W. Weingarten WW 1SPL cryo-module meeting 19 October 2010.
MICE Coupling Coil Testing at Fermilab All Experimenters Meeting Ruben Carcagno March 19, R. Carcagno - MICE CC Testing at Fermilab3/19/2012.
Spoke test in vertical cryostat IPNO-UU Meeting on spoke test program, 2 nd -3 st October 2013 IPNO Team.
Medium beta cavities Paolo Michelato, Paolo Pierini, Carlo Pagani INFN Milano - LASA.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
TE-CRG Activities D. Delikaris, TE-CRG.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
SPL cryomodule specification meeting, CERN 19th October 2010 SPL cryomodule specification: Goals of the meeting SPL cryomodule specification: Goals of.
Guillaume Olry, Sébastien Bousson CNRS/IN2P3/ IPN Orsay – Paris-Sud University Experience on Spiral2 cavity cleanliness degradation during clean room assembly.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
Wish list from ESS Christine Darve H-ECCTD Kick-off meeting 16 March
Spoke section of the ESS linac: - the Spoke cryomodules - the cryogenic distribution system P. DUTHIL (CNRS-IN2P3 IPN Orsay / Division Accélérateurs) on.
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
FC Status CM39 1/20 June 2014 OXFORDRALDARESBURY V. BlackmoreV. BaylissT. Hartnett J. CobbT. BradshawS. Griffiths W. LauM. CourtholdI. Mullacrane R. PreeceA.
JLAB Cryomodule Assembly Facilities Visit Report Tug Arkan, Yuriy Orlov March 26, 2012.
FCC Infrastructure & Operation Update on the cryogenics study Laurent Tavian CERN, TE-CRG 28 October 2015.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
P. Bosland CEA-Saclay Collaboration Board meeting Copenhagen 14/04/ Status of the French activities under the responsibility of CEA Philippe CHOMAZ.
ESS | Helium Distribution | | Torsten Koettig Linac – Helium distribution 1.
Design Status of the Spoke Cryomodule for MYRRHA SLHIPP Louvain la Neuve 17-18/04/2013 Design Status of the Spoke Cryomodule for MYRRHA SLHIPP Louvain.
Guillaume Olry on behalf the IPN Orsay SPIRAL2 team TTC Meeting – Milan, 28 Feb-3 March 2011.
Vishy Ravindranath LCLS-II 2 K Cold Box FDR March 9, 2017
Final Design Cryogenic and mechanical configurations
Status CO2 Cooling IBBelle: Reconnection after Belle II Roll in
How Does HNOSS Operate? Rocío Santiago Kern 20th May 2016.
Status of the M-ECCTD F. Peauger - P. Bosland
Existing Prototype Test Facility (PTF) and planned Series Test Facility Schroeder, Claus Cryo-Review Darmstadt
Cryomodule test stand at ESS site
Process Simulation for the LCLS-II Cryogenic Systems
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
FRIB Cryogenic Support
at STFC Daresbury laboratory
T5.2: Harmonization - Material and Component Reference
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
Project Manager’s Report + DC/MoM Report
SPS cryogenic proximity equipment and SM18 validation
The LHC - Status Is COLD Is almost fully commissioned
CRYOGENICS – strategy, unavailability root causes and limitations
Update on HW commissioning
Functional interfaces
Hongyu Bai LCLS-II 2 K Cold Box FDR March 9, 2017
ESS RF Development at Uppsala University
Status of the cryogenic system for B180
The HIE—ISOLDE Cryogenic System, its Infrastructure and Considerations for Phase 3 O. Pirotte (TE/CRG)
Operation experience of cryogenic system and cryomodules for the superconducting linear accelerator at IUAC, New Delhi. T S Datta ( On behalf of Cryogenics.
Teleconference ACS – FREIA 20th February 2018
IHEP Cryomodule Status
IHEP ILC Cavity Status Jiyuan Zhai (IHEP)
Cryomodules Challenges for PERLE
Prototype cryomodule development
Double-Spoke Cavities
WP11: CDS-SL CDR Overview
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
Teleconference ACS – FREIA 19th June 2017
Prototype cavities development
UPPSALA UNIVERSITY_GERSEMI PROJECT
Burst Disc Review Closeout 21 May 2019 J.G. Weisend II, Chairman.
Presentation transcript:

ESS Spoke cryomodule testing: cryogenic experience …on the past year Patxi DUTHIL Guillaume OLRY

Outline From June 2017 to now: one year of ups and downs Status of today Future work Few comments JUMPER VALVE BOX CRYOMODULE

Setting of the experiment [1] Main differences wrt the machine configuration: Thermal shield cooled with saturated LN2 (no pressurized He) Supply with saturated LHe (not pressurized) Heat intercept along the RF double wall coupler is done by use of cold saturated vapours instead of Supercritical He A lot of instrumentation (T° sensors: 60 CX + 110 PT100; 69 heaters, etc)

Setting of the experiment [2] Main differences wrt the series cryomodule configuration: Cav1: Giulietta + tuner + magnetic shield + 2 antennas Test the tuner. Get the Qo value of the cavity to evaluate the efficiency of the magnetic shield Cav2: Dummy cav + magnetic shield + double-wall tube Direct measurement of the magnetic field inside the cavity Test the cooling of the DW tube GIULIETTA DUMMY CAV

June 2017 Valve box Cryomodule Helium production facility . Ready for cryo tests after several repair operations Cryomodule . Assembly of the cryomodule was under progress (all components repaired) . Repairing action on the VLP branch line of the cryogenic jumper of the cryomodule repaired by the manufacturer and delivered on June 14th; integration done by IPNO. Helium production facility . Not (fully) available due to supervision defects  valve box cryo tests was postponed to July

July 2017 Valve box Cryomodule Helium production facility . Cryogenic tests performed = cool-down and 4 K mode: C&C tested (PLC controls such as regulation loops, etc.) + cryofluids consumption  Good results @4K i.e. the valve box was operated and works as expected; Cryomodule . Cryomodule assembled and leak tested; . Cryomodule installed in the Supratech experimental platform; . Repaired VLP line of the cryogenic jumper was too long prevented the cryomodule from its connection to the valve box Helium production facility . Supervision temporally repaired (new server and OS environment needed)

August 2017 Valve box Cryomodule Helium production facility . Standby (waiting for the cryomodule) Cryomodule . VLP line of the cryogenic jumper was shortened (internal action); . Cryomodule was connected to the valve box  A lot of He leak tests of this connection (multichannel cryogenic line) were carried out Helium production facility . New server and OS environment installed . Re-qualification process of the He high pressure storage started (Pressure Equipment Directive): storage sectors have been successively removed from service for qualification tests.  Temporary shutdowns will affect the experiment

September 2017 Operation at 4 K Operation at 2 K (18-22/09) Finally, first cool-down of the valve box and the cryomodule happened! Operation at 4 K  C&C tests: diagnostic debugging (T° sensors), tuning of the regulation parameters Operation at 2 K (18-22/09) cavities operated at 2 K during some hours continuous and regulated transfer of superfluid from the valve box into the cryomodule operated during 1.5 h cooling of the double wall of the coupler with saturated helium operated during 1 day (but no usable data) RF test of Giulietta cavity  (@low field) Q0 of 1.8 1010 , Eacc max =8.8 MV/m (limited by field emission) Tuner tested without any hysteresis erroneous indication of some temperature sensors within the valve box (due to bad thermal contacts)

October to mid-November 2017 Helium infrastructures (25/09-16/10) 3 weeks of shutdown: re-qualification of the He high pressure storage and helium gas buffer In the meanwhile… Valve box was opened & accessible temperature sensors were disassembled thermal supports of the T° sensors were cleaned and properly greased T° sensors were mounted properly and VB closed again, ready for new tests  Then.. second cool-down (16/10-10/11) Operation at 2 K good regulation of the superfluid level in the cryomodule was achieved: He level of 62.5 cm: cavities completely filled up; no significant change of the magnetic shield efficiency during the cooling down to 100K); Again…temperatures measured at some locations within the valve box and cryomodule are not as expected = discrepancy with our estimations was observed;

Mid-November 2017 to Feb 2018 WINTER BREAK…LONG PERIOD OF DISASSEMBLY, REPAIR, INSPECTION, CONTROL, UPGRADE, MAINTENANCE, REASSEMBLY… Endoscopy in the cryogenic jumpers of the cryomodule and the valve box  contacts between the cryogenic branch lines and parts of the thermal shield. Cryomodule and jumpers disassembly Reroutine of some cryolines MLI corrections Improvements of the thermal contacts between the magnetic shield and the cooling circuit Control of the 156 internal sensors (including heaters and RF) Opening if the valve box Detection (endoscopy) and correction of thermal contacts at the vacuum barrier Repair of a leak in the thermal shield circuit Reassembly of the cryomodule, the jumper and the valve box. …

Feb to end of March 2018 06/02  Cryomodule was connected to the valve box in the experimental areas and ready for cryo (under vacuum) But … Stand-by for 4 weeks because of co-workers absences and resignation the cooldown was postponed to the end of March 05/03: restart of the activities to finish the modifications of the supervision and PLC program

April 2018 [1]  Third cool-down Timeline: 2 K op 4 K op 2 K op Coupler cooling circuit and RF cavity tests 4 K op 4 K op Std-by mode (20-60 K) Slow cool-down + Std-by mode (20-66 K) Weekend Weekend Weekend Compressed air failure

April 2018 [2] Some constraints Limited liquefier capability LHe production~70 L/h Transfer efficiency to fill in the dewars from the liquefier: 60%  42 L/h Short operating time @ 2K of about 1 hour max per run Space configuration: from the dewar into the cryomodule ~ 10 m long flexible line  ~7 W losses (measured) Use of “small” 500L dewars: 2 (to 3) per day + small volume of LHe in the cryomodule: ~150 L No long cycles with LHe regulations Limited time for RF test of the cavity

April 2018 [3] Typical run over a day 7h 1h 4 K regul 2 K regul Filling up the CM 4 K to 2 K Nominal CM LHe level Small cool down Dewar 2 empty replacement Dewar 1 empty replacement Filling up the VB 7h 1h

April 2018 [4] 1st cryogenic results (data are being processed) Some indicated temperatures not physical Investigation is under progress: control of the sensors + thermal test of the sensor anchoring Cryogenics at 2 K +35 % of He consumption at 2 K (TBC) Efficiency of the JT is thought to be not enough efficient  Investigation is under progress (loads on the CM jumper, thermal contacts) Coupler double wall cooling Reduction of the heat loads by conduction of about 15 W as calculated Heating power at the coupler warm flange: ~70 W as calculated

April 2018 [5] RF test of Giulietta cavity  (@low field) Q0 > 2 1010 , Eacc max =8 MV/m (limited by field emission, no quench) Magnetic shield temperature cooled down to 30K: the residual magnetic field is unchanged  no need of active cooling

Status of today & future work Valve box Has been open again. Accessible Temp sensors will be controlled again, especially those of the heat exchanger. The cryo line, formerly dedicated to the magnetic shield, will be removed VB is planned be tested again in July before shipment to UU in August Cryomodule The cavity string assembly has started in clean room and should be finished end of June Problem of seizure (tooling) Bad orientation of the couplers / DW tubes Pollution (Particles size > 10µm) of one gate valve Final assembly outside the clean room is planned in July Shipment to UU is also scheduled in August

Few comments… Manufacturing issues had (and still have) big impacts on the initial test plan  internal resources reallocation to fix most of the problems  non visible defects which make the measurements barely understandable Staff resignation and turnover The complexity of the experiment and overall time needed for the cryogenic testing were obviously underestimated Same people taking care of the prototypes experiments and the time consuming “activities” of the series (call for tender, production follow-up, reporting, meetings…)

Thank you for your attention