Earned Value $$$.

Slides:



Advertisements
Similar presentations
Connoizor Enabling Performance for Businesses through Software Website: Contact:
Advertisements

Presenter: Sohel Akhter, PMP, CCNA,ISMS
Budget Management. 57 Budget Management Budget Development Good scheduling skills and abilities Understanding of the project scope Well developed WBS.
 Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration.
© The McGraw-Hill Companies, Software Project Management 4th Edition Monitoring and control Chapter 9.
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
Microsoft Project 2002 Sessions 5-6. Entering Tasks During this first session we will enter a set of tasks that comprise building a shed – data sheet.
Chapter 10: Monitoring and Controlling Change
Monitoring and Controlling
Earned Value Project Management: a powerful tool for software projects
Project Monitoring and Control. Introduction Goal: ensuring that the project is on time and on budget and/or highlight any deviation from the plan Areas.
IIPM1 TIPS AND TECHNIQUES FOR PMP EXAM Tip # 1. Tense Verification - Verify the TENSE of the question before answering. International Institute of Project.
Earned Value Management
Chapter 10 Project Monitoring and Control
Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.
Project Monitoring and Control. Monitoring – collecting, recording, and reporting information concerning project performance that project manger and others.
Project Management Methodology Project monitoring and control.
1 ev14a Interactive Session 4 u Tuesday, July 17 7pm to 10pm u Build a sqa plan for the dental office software u Assume a 3-person, development team, a.
1. Earned Value Analysis (EVA) Earned value is a measure of progress enables us to assess the “percent of completeness” of a project using quantitative.
Earned Value JOEL VIRAY TOPICS What is Earned Value Management? –Why do I need it? –How do I do it? Earned Value Reporting Earned.
Monitoring and Information Systems
Chapter 15 Cost Control.
EARNED VALUE MANAGEMENT (EVM)
Earned Value Management System (EVMS). Given: –total budget of $100,000 –12 month effort –produce 20 units Status: –spent to date: $64,000 –time elapsed:
10/19/ :26 AM 1 Project Cost Control. 10/19/ :26 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
Earned Value SOS section Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much.
Chapter 9 Project Development. What to manager Client experience  Clients are very important  Happy or not is largely dependent on their expectations.
1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost.
Information Investment Subcommittee Meeting EVM SLIDE ONLY December 20, 2007.
MEASURING AND FORECASTING COMPLETION. PROGRESS BY DISCIPLINE.
Ev3 1 In House Software Development:… Verner, etal IEEE Software, Jan?feb 2005.
Introduction To Earned Value November 14, Definition Earned Value is a method for measuring project performance. It compares the amount of work.
Earned Value Analysis Tracking Project Progress. Introduction | Components | Project Scenario | Values | Calculations | Forecasts | Summary l What Is.
Project Management Information System What?? Objective: –Record & report relevant information and status of various components of project –Highlight the.
1 Earned value analysis Planned value (PV) or Budgeted cost of work scheduled (BCWS) – original estimate of the effort/cost to complete a task (compare.
Schedule Control (Earned Value)
Project Cost Con trol. 1.To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2.To forecast.
Project Management 1 Project Control. Project Management 2 Topics Project Control Status Reporting Earned Value Analysis.
Earned Value Management
Measuring Progress HNC Project Management. Measuring Schedule Performance Break project tasks up into small work units. Work units that are too large.
CPMGT 300 Week 4 DQ 1 Check this A+ tutorial guideline at T-300/CPMGT-300-Week-4-DQ-1 Your project budget is 80% spent.
Performance Measurement Baseline Contract Price (Project Price)
Earned Value Analysis by Miles M. Hamby, PhD Copyright©2014 Miles M
Project Monitoring
TOPIC-8B- PROJECT COST CONTROL
PROJECT MANAGEMENT AND CONTROL
CHAPTER:7 Project Cost Management
Earned Value Management
Project Management – PTM712S
PROJECT MANAGEMENT AND CONTROL
Performance Measurement Baseline Contract Price (Project Price)
Earned Value Management
Project Cost Management
Work Packages / Deliverables Completed
Contract Performance Charts
Progress and Performance Measurement and Evaluation
Earned Value - What is it
Earned Value Analysis It is a continuous comparison between the plan of the project data and the actual data. Budgeted and Committed Cost: Variance = Budgeted.
An Introduction to Earned Value Performance Measurement
Implementing EV in IT A Three Step Approach John Chapman Touchstone Ltd
Problem solving.
Earned Value Measures Planned Value (PV) Earned Value (EV)
ENGINEERING MANAGEMENT (GE 404)
فرآيند كنترل پروژه.
Earned Value Management
MS Project Add-on for Earned Value Analysis Reporting
Project Cost Control.
Project Management Life Cycle
Monitoring and Controlling
Chapter 13: Software Project Management
Presentation transcript:

Earned Value $$$

Earned Value Measure of Project Performance Overall for All Activities Measured at Particular Point in Times 13

Computing Earned Value EV = (% Completed Work) (Planned Cost) E.G. EV = .75 x 100 = 75 EV Also Known as: Budgeted Cost of Work Performed to Date (BCWP) 13

Using Earned Value Cost Variance (CV) = EV (BCWP) – Actual Cost of Work Performed (ACWP) E.G. CV = 75 – 100 = -25 (Over Budget) Schedule Variance (SV) = EV (BCWP) - Budget Cost of Work Scheduled (BCWS) E.G. SV = 75 – 125 = -50 (Costs behind Schedule) Time Variance (TV) = Scheduled Time Work Performed (STWP) – Actual Time Work Performed (ATWP) E.G. TV = 20 – 25 = -5 (Behind Schedule) 13

Example: Problem 3.8 EV = (% Completed) (Planned Cost) EV = (Actual Progress/Scheduled Progress) (100) CR = (Actual Progress/Scheduled Progress) (Budget Cost/Actual Cost) CR = (EV/100) (100/Actual Cost) CR = EV/Actual Cost 13

CR for A: Over 6 Days Day A:EV A:Cost A: CR 1 90 95 .947 2 92 98 .939 1 90 95 .947 2 92 98 .939 3 94 101 .931 4 98 106 .925 5 104 116 .897 6 112 126 .889 13

CR for B: Over 6 Days Day B:EV B:Cost B: CR 1 90 95 .947 2 88 94 .936 1 90 95 .947 2 88 94 .936 3 95 102 .931 4 101 109 .927 5 89 99 .899 6 105 118 .890 13