Single Phase Pole Mounted

Slides:



Advertisements
Similar presentations
Electrical Safety.
Advertisements

Electrical Safety Safety Training Series
Module 3 Worksite Inspection Checklist Days to a Safe and Healthy Workplace - Days
Electrical Safety.
1a.  Exposed part  Live or energized part  De-energized part 1a.
Electrical Safety, Subpart K
Working On or Near Energized Conductors and FR Clothing.
Employee Safety Orientation
Personal Protective Equipment
A4 Insulator Changeout.
Electrical Safety.
Cutting an In-Line Dead-end Single Phase
Voltage Regulator Bypass
Wye/Wye 120/208 4 wire Transformer Bank
Wye/Delta 240/480 4 wire Transformer Bank
Voltage Regulator Bypass
Protective Grounding Three Phase Tangent
A 3 Insulator Changeout with Jib
Project Committee - JSA’s
Wye/Delta 120/240 4 wire Transformer Bank
C 4 Insulator Changeout With Hoists
Protective Grounding Single Phase Tangent
Emergency Action Plans
Wye/Delta 120/240 4 wire Transformer Bank
Wye/Wye 120/208 4 wire Transformer Bank
C5.21L Three Phase Dead End Insulator Changeout
A4 Insulator Changeout © 2018 Iowa Association of Electric Cooperatives.
Cutting in Bells Single Phase
Cutting in Bells Three Phase
C3 Insulator Changeout With Jib
A 3 Insulator Changeout With Hoists
Wye/Delta 120/240 Open 4 wire Transformer Bank
Relocating a Three Phase Transformer Bank
A1 Pole Changeout Energized
URD Radial Feed Transformer Changeout
Adding an A5 tap to an A1 © 2018 Iowa Association of Electric Cooperatives DISCLAIMER: This job hazard analysis (JHA) has been made available for informational.
Voltage Regulator Bypass
A 3 Insulator Changeout with Jib
C3 Insulator Changeout With Jib
C3 Insulator Changeout With Hoists
Wye/Wye 277/480 4 wire Transformer Bank
Line Down Single phase © 2018 Iowa Association of Electric Cooperatives.
Wye/Wye 120/208 4 wire Transformer Bank
Cutting an In-Line Dead-end Single Phase
A1 to A6 Conversion Tangent to Double Dead End
A5 Insulator Change Transformer Pole
A2 Pole Changeout Energized
A1 Pole Changeout Energized
A 3 Insulator Changeout with Jib
Wye/Wye 277/480 4 wire Transformer Bank
Open Wye-Wye 120/208 4 wire.
Installing a single phase tap on an existing C1.11
C1 Insulator Changeout © 2018 Iowa Association of Electric Cooperatives DISCLAIMER: This job hazard analysis (JHA) has been made available for informational.
A1 Insulator Changeout Energized
A4 Insulator Changeout © 2018 Iowa Association of Electric Cooperatives DISCLAIMER: This job hazard analysis (JHA) has been made available for informational.
Cutting an In-Line Dead-end Single Phase
Protective Grounding Single Phase Tangent
A5 Insulator Change Transformer Pole
C5.21L Three Phase Dead End Insulator Changeout
Wye/Delta 120/240 4 wire Transformer Bank
Pad mounted 120/240 open 4 wire service
Adding an A5 tap to an A1 © 2018 Iowa Association of Electric Cooperatives.
Voltage Regulator Bypass
Wye/Delta 120/240 4 wire Transformer Bank
A2 Insulator Changeout Energized
C1 Insulator Changeout © 2018 Iowa Association of Electric Cooperatives.
Wye/Delta 120/240 4 wire Transformer Bank
A1 Insulator Changeout Energized
Relocating a Three Phase Transformer Bank
Wye/Wye 277/480 4 wire Transformer Bank
Presentation transcript:

Single Phase Pole Mounted Recloser Bypass Single Phase Pole Mounted © 2018 Iowa Association of Electric Cooperatives DISCLAIMER: This job hazard analysis (JHA) has been made available for informational and educational purposes only. The IAEC does not make any representation or warranty with respect to the accuracy, applicability, fitness, or completeness of the JHA. The IAEC hereby disclaims any and all liability to any party for any direct, indirect, implied, punitive, special, incidental or other consequential damages arising directly or indirectly from any use of this JHA which is provided as is.

OSHA Required Tailgate Discussion Topics Hazards Associate with the job Work Procedures Involved Special Precautions Energy Source Controls PPE Required The five topics required by OSHA to discuss in the tailgate. First letter from each topic = How Well Should Everyone Plan © 2018 Iowa Association of Electric Cooperatives

Work Procedures Involved Hazards associated with the job Special Precautions Energy Source Controls Personal Protective Equipment Be sure to record your emergency location and post in a location everyone on the crew knows. Have your PPE and First Aid kit available Be sure your AED is accessible. A safe job begins with a thorough inspection of… Tools Be certain all of your tools are in good shape. Equipment Make sure your trucks are all in working order take time to preflight your equipment and insure there are no surprise. Line/Structure Look over the line and structure. Are there any potential hazards? (Broken insulators, damaged wire, clearances over roads or from trees?) Be aware of your work area, be sure to cover anything you can reach touch or fall into. And anything that can reach touch or fall into you! Discuss all PPE needed for the job and wear your PPE. Be sure to inspect your equipment prior to use. Identify all voltages you are exposed to. Be sure to have all of your Arc-Flash protective gear on. Identify a dedicated observer Working in traffic exposes you to hazards that are difficult to control. Give the vehicles plenty of time to see and avoid you! Follow the manual of traffic control for your area. Slips trips and falls are some of the most common injuries, look for hazards that could cause this. Be sure to inspect and wear your fall arrest harness. Here are the five topics again with signs and bubbles to jump start tailgate discussion!! Click on the icon to bring up a text box. Click on the icon again to make the text box go away Gets the crew involved. Gives the feeling of knowing it is ok to ask questions, give suggestions, see something, say something! The next slides will get directly into the task at hand. Visual, written and audio will all be used here! There are suggestions in the notes as to what to discuss. This will get the Team involved, creating communication channels to open! © 2018 Iowa Association of Electric Cooperatives

Visually inspect the recloser for damage Visually inspect the recloser for damage. Look to be sure all of the jumpers are in good shape. Visually inspect the recloser for damage. Look to be sure all of the jumpers are in good shape. © 2018 Iowa Association of Electric Cooperatives

Remove the bypass fuse from the hanger and move it to the bypass cutout. © 2018 Iowa Association of Electric Cooperatives

Close the bypass fuse. Close the bypass fuse. © 2018 Iowa Association of Electric Cooperatives

Be sure the bypass is complete. © 2018 Iowa Association of Electric Cooperatives

Open the recloser handle. © 2018 Iowa Association of Electric Cooperatives

Be sure you listened and heard the internal operation. © 2018 Iowa Association of Electric Cooperatives

Install the jumper insulated stand-off. © 2018 Iowa Association of Electric Cooperatives

Install the jumper insulated stand-off. © 2018 Iowa Association of Electric Cooperatives

© 2018 Iowa Association of Electric Cooperatives

Remove the source side jumper and place it on the insulated stand-off. © 2018 Iowa Association of Electric Cooperatives

© 2018 Iowa Association of Electric Cooperatives

© 2018 Iowa Association of Electric Cooperatives

Take the load side jumper down and place it on the system neutral. © 2018 Iowa Association of Electric Cooperatives

© 2018 Iowa Association of Electric Cooperatives

© 2018 Iowa Association of Electric Cooperatives

Remove the source side jumper from the insulated stand-off and place it on the system neutral. © 2018 Iowa Association of Electric Cooperatives

© 2018 Iowa Association of Electric Cooperatives

You can now disconnect the case ground and remove the recloser from the pole. © 2018 Iowa Association of Electric Cooperatives

© 2018 Iowa Association of Electric Cooperatives

Install the new recloser and connect the case grounds first Install the new recloser and connect the case grounds first. Be sure the control handle is in the open position. Install the new recloser and connect the case grounds first. Be sure the control handle is in the open position. © 2018 Iowa Association of Electric Cooperatives

Move the source side jumper to the insulated stand-off. © 2018 Iowa Association of Electric Cooperatives

© 2018 Iowa Association of Electric Cooperatives

© 2018 Iowa Association of Electric Cooperatives

Connect the load side jumper to the load side line. © 2018 Iowa Association of Electric Cooperatives

© 2018 Iowa Association of Electric Cooperatives

© 2018 Iowa Association of Electric Cooperatives

Move the source side jumper to the source line. © 2018 Iowa Association of Electric Cooperatives

© 2018 Iowa Association of Electric Cooperatives

© 2018 Iowa Association of Electric Cooperatives

Remove the insulated stand-off. © 2018 Iowa Association of Electric Cooperatives

© 2018 Iowa Association of Electric Cooperatives

Close the recloser control handle. © 2018 Iowa Association of Electric Cooperatives

© 2018 Iowa Association of Electric Cooperatives

Open the bypass fuse. Open the bypass fuse. © 2018 Iowa Association of Electric Cooperatives

© 2018 Iowa Association of Electric Cooperatives

Remove the fuse door. Leaving it hanging open will cause it to fill with contaminants. © 2018 Iowa Association of Electric Cooperatives

Place the bypass fuse back in it’s storage location with the open end down. This will prevent it from filling with contaminants. Place the bypass fuse back in it’s storage location with the open end down. This will prevent it from filling with contaminants. © 2018 Iowa Association of Electric Cooperatives

The job is complete. The job is complete. © 2018 Iowa Association of Electric Cooperatives