FCC Week 2019 Civil Engineering Summary

Slides:



Advertisements
Similar presentations
MODULE TRANSPORT CLIC Module Working Group 27 September 2010 Keith Kershaw CERN EN-HE.
Advertisements

CFS challenges for a linear collider J.Osborne CERN ILC-GDE Dubna - 4 June 2008 OUTLINE : Introduction Civil Engineering -Geology (water, stability issues.
1 DOE Annual Review -June 15,2005 An Overview of Conventional Facilities (Civil Construction) U. S. ILC Civil studies and cost issues for Snowmass Fred.
John Osborne GS/SE March 2013
Infrastructure & Operation 27 th May 2015 Infrastructure & Operation 27 th May 2015 Update on optimisation of tunnel footprint and location Charlie Cook.
Investigation of FCC position Impacts on Hadron Injectors John Osborne, Charlie Cook, Yung Loo (ARUP) 16/09/2014.
TOT-FCC: Tunnel Optimisation Tool for the Future Circular Collider Introduction and lessons learnt C. Cook, J. Osborne, P. Lebrun, Y. Robert, M. Jones,
Geotechnical & Civil Engineering Studies Future Circular Colliders (FCC)
CES Status J.Osborne 6 November 2009 Status Report from Civil Engineering and Services Working Group J.Osborne GS/SEM for CES Working Group.
1. Civil Engineering works for Linear Colliders* : -Brief introduction on the overall machine layout (just for CLIC at this stage) -Experimental Area.
FCC Tunnel Civil Engineering and Geology John Osborne (CERN GS-SE) 4 April 2014.
LCWS14 - Belgrade October 6-10, 2014 Conventional Facilities & Siting Working Group Summary V Kuchler, M Miyahara, J Osborne.
LCFOA Meeting at SLAC Linear Collider Forum of the Americas 1 LINEAR COLLIDER FORUM OF THE AMERICAS CONVENTIONAL FACILITIES OVERVIEW Victor R. Kuchler.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
Introduction / CLICdp news (CLICdp - CLIC detector and physics) -- CLICdp meeting at AWLC14, 13 May Konrad Elsener, CLICdp session, AWLC14 1 Konrad.
TDR Status of Asian CFS Team Part II: The ILC Baseline Reference Ch.SectionSubsectionsAuthor1 st draft 112: Asian Region Siting Studies Overview Location.
Report from ILC CFS and Cryogenics Workshop
10/2010 IWLC2010 Global Design Effort 1 Brief Overview of Interaction Region Conventional Facilities in RDR Times Presenter Tom Lackowski.
Civil Engineering and Services - drawings for CDR - CDR chapter J.Osborne and M.Gastal for CES WG 1.
Activities and news Last meeting: 2015 CERN budget allocations as expected, now distributed on accounts Annual report done, and MTP (Medium Term Plan)
Global Design Effort - CFS GDE Plenary Session 1 LCWS10 GDE Plenary Session SB 2009 ILC CONVENTIONAL FACILITIES AND SITING GROUP A. Enomoto, V.
Global Design Effort - CFS TILC08 Working Group 1 - March 5, CFS Cost Reductions Conventional Facilities and Siting Group A. Enomoto, V.
John Osborne : GS-SEM Civil Engineering 18 May 2009 CES 9 June News from ILC Japan CFS review 1-3 June 2010 :
Global Design Effort - CFS ILC Global Systems Meeting 1 ILC GLOBAL SYSTEMS MEETING CONVENTIONAL FACILITIES AND SITING GROUP STATUS REPORT V. Kuchler,
ILC D RAFT P ROJECT S CHEDULE K LYCLUSTER 500GeV K Foraz & M Gastal ILC Mechanical & Electrical Review and CFS Baseline Technical Review Many thanks to.
1 Future Circular Collider Study Preparatory Collaboration Board Meeting September 2014 R-D Heuer Global Future Circular Collider (FCC) Study Goals and.
General Infrastructures Services Department Civil Engineering planning for LSS4 Option, presented at review workshop 30/7/ months Planning and Resources:
FHI 32: FCC tunnel layout and transferline update Tuesday, 9 February 2016 CE Updates: Comparison of 100km Intersecting and Non-Intersecting options New.
CLIC - CDR Status (Volume 2) Hermann Schmickler, ILCW2010.
MDI 9 th Meeting - 22 nd January 2016 FCC Experimental Caverns - Feasibility and Excavation C. Cook (GS), J. Osborne (GS),
Infrastructure and Operation meeting 20 th January 2016 Amberg’s Report Summary : Comparison of 100km Intersecting and Non-Intersecting options C. Cook.
Survey Meeting John Osborne, CERN 8 February 2016
Review of FCC tunnel footprint & implementation Introduction & scope Philippe Lebrun Review of FCC tunnel footprint & implementation CERN, 11 June 2015.
CENF CIVIL ENGINEERING UPDATE : - SITE INVESTIGATION - CALL FOR TENDER FOR DESIGN & CONTRACT ADMINISTRATION SERVICES - 3D VISUALS FOR SURFACE STRUCTURES.
CENF CIVIL ENGINEERING UPDATE : - SITE INVESTIGATION - CALL FOR TENDER FOR DESIGN & CONTRACT ADMINISTRATION SERVICES John Osborne GS/SE 16 May 2013.
CES Studies at CERN for the Interaction Region : -Summary of Linear Collider IR meeting at CERN held on 16 February Design Brief for external design.
LCLS-II Project Overview David Schultz LCLS-II Deputy Project Director March 19, 2012.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
Global Design Effort - CFS ILC CFS and Global Systems Meeting 1 ILC CFS AND GLOBAL SYSTEMS MEETING CONVENTIONAL FACILITIES AND SITING GROUP CFS.
RISK ASSESSMENT FCC draft, 2. September 2015.
FCC Underground Infrastructure
Civil Engineering for FCC-eh and LHeC
LHeC Coordination Meeting, 9 June 2017
Civil Engineering update - alignment configuration
FCC Civil Engineering Optimisation and Design Development
CLIC Civil Engineering Update
Conventional Facility & Siting (CF&S) Overview for the Positron Source
CLIC Civil Engineering Update
FCC Civil Engineering John Osborne, Jo Stanyard, Matt Stuart(SMB - Site Engineering - FAS Section) Cost & schedule Phase 3 - specification 10th May 2017.
1st FCC Infrastructure & Operation meeting
CLIC Civil Engineering & Infrastructure
FCC Civil Engineering John Osborne & Jo Stanyard (SMB - Site Engineering - FAS Section) FCC week outline 10th May 2017.
Acknowledgements to all FCC study teams
Selected comments and recommendations of the International Advisory Committee - Comments/replies from IOWG Resulting actions V. Mertens IOWG
Future Circular Collider
CLIC / ILC Collaboration for CFS works
5th FCC Infrastructure & Operation meeting
FCC Civil Engineering update
Latest ILC tunnel cross section May 2017
CDR preparation V. Mertens IOWG
FCC-ee MDI Civil Engineering update
Status of Cryogenics Facilities Design
Civil Engineering for FCC-eh IR
Preparation of FCC Week 2018 (programme, attendance)
Upgrade Strategy for the Experimental Vacuum Systems
Future Collider Projects at CERN
CLIC Civil Engineering Update
Workshop on fire protection for physics research facilities
FCC study – Fire collaboration WP4 Status & Update
FCC Week 2019 ( ) V. Mertens IOWG
Presentation transcript:

FCC Week 2019 Civil Engineering Summary J. Osborne A. Tudora IOWG – 5.6.2019 Future Circular Collider Study FCC Week 2019 Alexandra Tudora, IOWG, 5 June 2019

FCC Week CE summary Contents of CE talk Description of CE for baseline design (CDR layout) Show 3D schematic, longitudinal profile, tunnel cross sections (showing different lining types) Risk Factors Main risks for underground works: tunnelling in karst and fault zones, overburden, Encountering hydrocarbons, water ingress during tunnelling) Geological uncertainty Results of ILF Cost and Schedule Studies Latest design updates (cavern layout at experimental points, inclined tunnels) Overview of construction schedule Mention additional ILF studies: cash flow consideration, spoil volume per site, HL-LHC cost comparison (similar unit prices) Schedule for preparatory phase Phases and types of site investigations Cost comparison HE-LHC? Brief summary of CE updates and proposed structures (cryo caverns, buildings, tunnel enlargements, sector 3-4 refurbishment) Ongoing work and future steps Alignment optimisation following review of surface sites Site investigations Design of injection tunnels Exploring GIS tools and alignment optimisation software – Workshop with industries at CERN Future Circular Collider Study FCC Week 2019 Alexandra Tudora, IOWG, 5 June 2019 Future Circular Collider Study FCC Week 2019 Alexandra Tudora, IOWG, 5 June 2019

Drawings and Figures Tunnel Cross section Longitudinal profile FCC 3D schematic HE-LHC 3D schematic Future Circular Collider Study FCC Week 2019 Alexandra Tudora, IOWG, 5 June 2019 Future Circular Collider Study FCC Week 2019 Alexandra Tudora, IOWG, 5 June 2019

Schedule for preparatory phase European Strategy Update 2020 Conceptual Design Report Future Circular Collider Study FCC Week 2019 Alexandra Tudora, IOWG, 5 June 2019 Future Circular Collider Study FCC Week 2019 Alexandra Tudora, IOWG, 5 June 2019