Finishing Projects Fast

Slides:



Advertisements
Similar presentations
6-1 Goldratt’s Critical Chain  In 1997, Goldratt introduced the Critical Chain Project Management (CCPM) methodology to apply the theory of constraints.
Advertisements

Defining activities – Activity list containing activity name, identifier, attributes, and brief description Sequencing activities – determining the dependencies.
Critical Path and Gantt
Computer Engineering 203 R Smith Project Tracking 12/ Project Tracking Why do we want to track a project? What is the projects MOV? – Why is tracking.
Project Management Workshop By Jonathan W. Powell, CGFM, PMP.
Chapter 9: Reducing Project Duration
Reducing Project Duration
Review for Final in ISQS 4350 Final will take place: Tuesday, December 10, 2013, p.m., this room – BA 021.
4.0 CRITICAL CHANGE IN PROJECT MANAGEMENT 4.1 Why should there be need other methods for Project Management to replace or change? Given the level of project.
Reducing Project Duration
Applied Software Project Management 1 Introduction Dr. Mengxia Zhu Computer Science Department Southern Illinois University Carbondale.
Software Project Management Lecture # 8. Outline Earned Value Analysis (Chapter 24) Topics from Chapter 25.
Introduction to the Theory of Constraints (TOC) & Critical Chain Project Management (CCPM) Major Mark McNabb.
Critical Chain A Novel by Eliyahu Goldratt Product lifetimes are diminishing fast u Projects to create new products must be shortened drastically u Consider.
When Things Go Right Cornell’s PeopleSoft 8.9 Upgrade Lisa Stensland Manager, CIT Project Management Office May 15, 2008.
Critical Chain From “Theory of Constraints” Developed by Elihu Goldratt in 1984 Goldratt – Many of his key ideas were first explained via “business novels”
Quick Recap.
Chapter 9: Reducing Project Duration
File:CCPGS05 CC present Page: 1 ETXPGS
IS 556 Enterprise Project Management 1IS 556 -Spring 2008 Lecture 2 Apr 7, 2008 //48.
Project Management Part 6 Project Control. Part 6 - Project Control2 Topic Outline: Project Control Project control steps Measuring and monitoring system.
Introducing Project Management Update December 2011.
Reducing Project Duration CHAPTER NINE Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Reducing Project Duration CHAPTER NINE Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Project Time Management
1 Allocating Resources to the Project Expediting a Project Fast-Tracking a Project Resource Loading Allocating Scare Resources.
1 Finishing Projects Fast James R. Burns Professor of Operations Management and Information Technology Texas Tech University.
Critical Chain A Novel by Eliyahu Goldratt Copyright 1997.
Critical Chain A Novel by Eliyahu Goldratt Copyright 1997.
SE503 Advanced Project Management Dr. Ahmed Sameh, Ph.D. Professor, CS & IS Critical Chain Project Management.
1 Finishing Projects Fast James R. Burns Professor of Operations Management and Information Technology Texas Tech University.
1 Finishing Projects Fast James R. Burns Professor of Operations Management and Information Technology Texas Tech University.
1 Finishing Projects Fast James R. Burns Professor of Operations Management and Information Technology Texas Tech University.
Project Management Finals Lesson 1 - Principles - Techniques - Tools.
Measuring Progress HNC Project Management. Measuring Schedule Performance Break project tasks up into small work units. Work units that are too large.
Project Management 6e..
Reducing Project Duration
Chapter 16 – Project Management
Introduction to Project Management Chapter 7 Managing Project Resources Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George.
Introduction to the Theory of Constraints (TOC) & Critical Chain Project Management (CCPM) Major Mark McNabb.
Strategic Capacity Management
Stage 4: Termination and Closure
Real Metrics for Real Decisions
Class 27: Project Management Part II
Reducing Project Duration
Mike Cohn - Agile Estimating and Planning
Earned Value - What is it
Constraint Management
The value of a project-oriented approach to IT and how we do it in IBM
Taking an Iteration Down to Code
Request for Proposal & Proposal
Review for Final in ISQS 4350
Lecture # 3 Software Development Project Management
Finishing Projects Fast
Finishing Projects Fast
Project Management How to access the power of projects!
Fine-Tuning your plan and obtaining approval
Reducing Project Duration
Setting up a project file
Setting up a project file
Finishing Projects Fast
A Novel by Eliyahu Goldratt
Software Testing Lifecycle Practice
Time Scheduling and Project management
Where We Are Now. Where We Are Now Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity.
Where We Are Now. Where We Are Now Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity.
“BPR AS A MEANS OF REINVENTING THE ORGANIZATION: AN OVERVIEW”
Where We Are Now. Where We Are Now Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity.
Presentation transcript:

Finishing Projects Fast James R. Burns Professor of Operations Management and Information Technology Texas Tech University

Presentation by James R. Burns Outline--Sources Generalities Goldratt concepts Mascitelli concepts McCONNELL concepts Kerzner concepts Maturity concepts Other sources Presentation by James R. Burns

Presentation by James R. Burns Goal: Make some suggestions as to how projects can be completed fast and frugally Presentation by James R. Burns

Presentation by James R. Burns Most firms Recognize project management to be a core competence today Have established project management centers of excellence for training and development of project managers and project management careers Encourage their employees to propose project initiatives with simple one-page statements of work Presentation by James R. Burns

Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity usually incurs additional direct costs. Cost-time solutions focus on reducing (crashing) activities on the critical path to shorten overall duration of the project. Reasons for imposed project duration dates: Time-to-market pressures Unforeseen delays Incentive contracts (bonuses for early completion) Imposed deadlines and contract commitments Overhead and public goodwill costs Pressure to move resources to other projects

Options for Accelerating Project Completion Resources Not Constrained Adding resources Outsourcing project work Scheduling overtime Establishing a core project team Do it twice—fast and then correctly Resources Constrained Fast-tracking Critical-chain concepts Reducing project scope Compromise quality (not really)

Notes on shortening project durations (Most of this must be done in the Planning and Budgeting stage) Crashing Reducing the duration of tasks on the critical path by adding resources Fast-tracking Starting tasks sooner Checking for parallelism opportunities in the schedule Pull as much work off of the critical path as you can Be aware of critical chain issues Presentation by James R. Burns

More Tips on shortening project durations REUSE, REUSE, REUSE Do it right the first time Eliminate non-value-added work activities Make projects lean Avoid changes to requirements But what if the requirements are unstable?? Presentation by James R. Burns

Presentation by James R. Burns Knowledge Reuse… Requirements Reuse Based on a Classification of projects Mapped/Programmed Projects--Everything is driven by and proceeds from the requirements Project Plan Functional Specification Design Document Code Tests and Test Documentation ALL OF WHICH CAN BE REUSED Presentation by James R. Burns

The Quality View on FAST projects: Do it Right the First Time!!! The further down the lifecycle the defects are found, the more expensive and time consuming they are to fix. Presentation by James R. Burns

The problem of Complexity In the early days of simpler code, it used to take a day or less to fix a bug Now, with greatly increased code complexity, it takes weeks sometimes. Complexity greatly increases time and cost Presentation by James R. Burns

Avoid changes to requirements If possible freeze requirements during execution and control stage Presentation by James R. Burns

Lean Project Management Customer-perceived value should drive everything What is the value proposition?? If we were to advertise in the WSJ that we have twice as many walkthroughs as our closest competition, would that garner any additional customers for us? Remove what does not add value Presentation by James R. Burns

Principles of Lean Concepts Applied to Projects Precisely specify the value of the project Identify the value stream for each project Allow value to flow without interruptions Let the customer pull value from the project team Continuously pursue perfection Presentation by James R. Burns

Which of the following adds value? Conducting a weekly team coordination Hunting for needed information Presenting Project status to upper management Creating formal project documents Gaining multiple approvals for a project document Waiting in queues for available resources Presentation by James R. Burns

Time Batching--Another Time Waster Analysis paralysis Approval cycles Formal document release Regularly scheduled meetings Planning cycles Work queues Presentation by James R. Burns

More techniques for shortening projects Scrub the requirements during or prior to the planning phase Remove from the requirements those items that add little or no value Remember the Pareto principle—80% of the value comes from 20% of the functionality REMOVE SAFETY—GOLDRATT Resist multitasking and student syndrome Presentation by James R. Burns

Presentation by James R. Burns Safety Extra time placed in an estimated task time Remove safety and put it in a time buffer at the end of the project Safety, when its buried in the tasks of the project, is a bad thing because of…. Multitasking, also a bad thing Student syndrome Task dependencies Can’t be passed along or accumulated Presentation by James R. Burns

Everybody overestimates the time required to do their task According to Goldratt (This is called SAFETY, as we said) Does anybody want to talk about how much safety they put into their estimates? Is this true in software development? It is if you have an expert doing the estimating, who really knows how long it will take him Presentation by James R. Burns

What happens after that--a possible scenario The team leader adds safety time to the task to cover his responsibilities The project leader adds more safety time The project manager may add still more safety time Presentation by James R. Burns

Implication>>> Most of the time we have built into our projects is ….. Safety Safety Safety Presentation by James R. Burns

The project manager must stay focused Or the project will not be finished on time, within budget This means applying the Pareto principle 80% of the benefit comes from 20% of the activities By the time progress reports indicate something is wrong, its usually too late Progress reports tell you that 90% of the project is finished in 90% of the required time. However, another equal period of time is required to complete the remaining “10%,” in many cases Presentation by James R. Burns

It is hard to stay focused when: There are too many project paths on-going, in parallel There are many critical or near critical paths There are many projects being managed concurrently Presentation by James R. Burns

Measurements are a major problem with projects Measurements should induce the parts to do what is good for the system as a whole Measurements should direct managers to the point that needs their attention So often it occurs that we measure the wrong thing. The wrong measure leads to the wrong behavior Tell me how you measure me and I will show you how I behave Presentation by James R. Burns

More Measurements -- EVA -5 -5 -5 +15 Presentation by James R. Burns

Projects are like chains Each task in sequence is a link in a chain Each link has two things weight, to which cost is analogous strength, to which throughput (time) is analogous Presentation by James R. Burns

Presentation by James R. Burns Cost vs Throughput Goldratt maintains that management in the cost world is a mirage efficiency becomes paramount local improvements are necessary to get global ones Goldratt suggests the managers should manage in the throughput world, a totally different paradigm must find the constraint--the weakest link concentrate on that By the way, what is the ultimate constraint??? Presentation by James R. Burns

Remember the five steps of TOC IDENTIFY the project constraint--the critical path Decide how to EXPLOIT that constraint SUBORDINATE everything to that decision ELEVATE the systems’ constraint Go back to step 1, and find another constraint Presentation by James R. Burns

Presentation by James R. Burns Safety Safety is however much time is added on to a task beyond its mean time of completion Presentation by James R. Burns

Probabilistic task durations Late durations tend to accumulate and may increase the length of the project Early durations do not show up This explains why safety disappears Presentation by James R. Burns

Presentation by James R. Burns More Measurements -5 -5 -5 +15 Presentation by James R. Burns

Other problems with safety Is wasted by the “student syndrome” Basically, this is procrastination Is wasted by multitasking (a person who works on several tasks at the same time) With each change of task, a set up is required Is wasted by dependencies between steps These dependencies cause delays to accumulate, but advances are wasted Delays get passed on; advances don’t Presentation by James R. Burns

Problems other than safety Early start vs. late start Existing measurements are worthless because they are based on a cost world mentality, according to Goldratt Existing measurements (Earned Value Analysis) do not take into consideration the critical path We’re talking about BCWP, BCWS, ACWP, CV, SV, CPI, SPI, BAC, EAC, etc. Presentation by James R. Burns

Early Start vs. Late Start B 5 A 5 E 10 D 10 C 10 Presentation by James R. Burns

How much Safety is there likely to be? Will project professionals admit how much safety they are putting into their estimates? What happens when these professionals are asked to cut their durations by 10%, next time? These professionals want to be 100% sure of getting finished on time Therefore, the durations are likely to be twice as long as they should be So CUT THEM IN HALF Presentation by James R. Burns

Presentation by James R. Burns Solutions Take the safety out of the individual tasks and put it at the end of the critical path in the time buffer, called a project buffer This means making the tasks roughly 50-60% as long as they would otherwise be. Presentation by James R. Burns

Presentation by James R. Burns More solutions At the point where each feeding path intersects with the critical path, place another time buffer, called a feeding buffer. The feeding buffer protects the critical path from delays occurring in the corresponding non-critical paths. When resources are needed on the critical path, these resources are advised ahead of time exactly when they must make themselves available. When that time comes, they must drop everything else and do the required critical tasks. Presentation by James R. Burns

Measurement solutions Measure progress only on the critical path; what percent of the critical path we have already completed. This is all we care about!! Have a project leader measure progress on a non critical path in terms of unused buffer days Presentation by James R. Burns

Shrinking the task time: Effects There is less procrastination There is much more focus There is less multitasking Presentation by James R. Burns

Presentation by James R. Burns More Suggestions Put your “BEST” people on the critical path Watch out for critical chains Presentation by James R. Burns

Presentation by James R. Burns What are the ramifications of a delayed software product, intended for commercial sale? Less market share Less profit; maybe no profit Lower analyst profit expectations Declining share price Out of business? How many firms has Microsoft driven out of business? Ask Philippe Khan (founder of Borland) what the implications of getting a product late to the marketplace are Presentation by James R. Burns

What about Procurement Most firms enter into LOSE/LOSE Strategies A fixed-price lowest bidder contract is LOSE/LOSE Strategy This forces Contractors to under bid their costs, hoping to make it back on the changes to the requirements that the customer will have to pay for Instead, Contractors should be induced to deliver product on time, with as much functionality as possible How would you do this? Presentation by James R. Burns