ATLAS Liquid Argon Calorimeter Signal Feedthroughs

Slides:



Advertisements
Similar presentations
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Advertisements

22 September 1998 LAr WeekM. Lefebvre Signal Feedthrough Progress Report Pin Carriers FEA Update Presented by Terry Hodges TRIUMF and University of Victoria.
EDM Collaboration Meeting, October 5-7, 2006 Valve R&D Steve Williamson UIUC.
Signal Feedthrough Progress Report Pin Carrier Order Plans for Prototypes Endcap Integration Issues Schedule and Management Issues Michel Lefebvre University.
Vacuum Vessel Production Readiness Review
Magnet Cooldown Scheme 17 th February 2012 Roy Preece (STFC RAL)
Status of the AFC at RAL Tom Bradshaw John Cobb Wing Lau Matt Hills Elwyn Baynham Mike Courthold Victoria Bayliss MICE Project Board 28 th June 2011.
MUTAC Review, 9 April MuCOOL and MICE Coupling Magnet Status Michael A. Green Lawrence Berkeley Laboratory Berkeley CA
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
A. Bross Imperial College – 9/04 Status of VLPC Cryo-Cooler Cryostat Design Russ Rucinski (Alan Bross) Fermilab.
9/26/2003E.L.B. MICE Meeting 9/26/2003 Absorber design update Edgar L. Black IIT.
Status of VLPC Cryo-Cooler Cryostat Design Russ Rucinski (Alan Bross) Fermilab.
Cryostat Structural, Thermal, and Vacuum Systems 14 October 2008 Martin Nordby, Gary Guiffre, John Ku, John Hodgson.
GlueX Solenoid Update George Biallas May 12, 2010 GlueX Collaboration Meeting.
Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
LARG week 07/01 Paul Poffenberger University of Victoria Endcap Feedthrough Production at Victoria Status Summary.
ZTF Cryostat Finite Element Analysis Andrew Lambert ZTF Technical Meeting 1.
Date Event Global Design Effort 1 Technical System Review John Noonan, ANL Yusuke Suetsugu,KEK Paolo Michelato, INFN Milano.
Status overview of the cooling 31 August 2015 Bart Verlaat, Raphael Dumps 1.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
VELO workshop, Amsterdam, april ‘00M.Ferro-Luzzi Difficulties with current mechanical design recent FEA results: to obtain sufficient stiffness of center.
Ron Madaras, LBL U.S. Pixel Meeting, SCIPP, July 9-10, 2003 Patch Panel 1 (PP1) Brief Review Cost and Effort Estimate.
October 16th 2000 NSERC Site Visit M. Lefebvre1 ATLAS at the University of Victoria M. Lefebvre NSERC Site Visit October 16th 2000 The ATLAS Experiment.
Vacuum Fundamentals High-Vacuum Technology Course Week 6 Paul Nash HE Subject Leader (Engineering)
Work toward Stainless Steel SRF Helium Vessels at Fermilab Tom Peterson (presenter), Information from Jeff Brandt, Serena Barbanotti, Harry Carter, Sergei.
19 May 1999 LAr WeekM. Lefebvre Endcap Signal Feedthrough Steel Order –Order fully coordinated with BNL –The order was ready to go Monday May 10th to lowest.
Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.
Stress and Cool-down Analysis Yun HE MLC Internal Review 9/5/2012Yun HE, MLC Internal Review1.
1.3GHz Input Coupler for ILC
ATLAS Endcap Signal Feedthrough Project Status Report Pin carrier Procurement Summary Feedthrough Production QA/QC Shipment to CERN Reception Tests at.
Signal Feedthrough Progress Report New FEA Results on Pin Carriers Vacuum Cable Development in Canada Leak Test Station and Assembly Station in Victoria.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
Endcap Signal Feedthrough Overview Endcap Signal Feedthroughs are constructed and tested in Victoria by Victoria and TRIUMF staff. Each feedthrough unit.
Vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand LHCb Vertex Detector System: Status Report J.F.J. van den Brand.
D. M. Lee, LANL 1 07/10/07 Forward Vertex Detector Overview Technical Design Overview Design status.
LAr Week Feb 2000 M. Lefebvre Milestones and Schedule General Production Readiness Review  Passed in Jan 99 Leak Test Station and Electric Test.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
Mike Struik / LHC-CRI INSTRUMENTATION FEEDTHROUGH SYSTEM FOR LHC MACHINE ARC QUADRUPOLE MAGNETS. 123rd LHC Vacuum Design Meeting 19 April 1999.
Installation of the T600 at Fermilab CSN2, September 22,
ATLAS LAr Forward Calorimeters C. Zeitnitz (Universität Wuppertal) for the ATLAS LAr Community.
Single-Phase ProtoDUNE Construction Planning Jim Stewart LBNC January 11, 2016.
AT-ECR/C.FabreMay 31, 2007 Cryogenics for Liquid Argon Calorimeters Caroline Fabre on behalf of the ATLAS Liquid Argon Cryogenics Collaboration.
Superconducting Cryogen Free Splittable Quadrupole for Linear Accelerators Progress Report V. Kashikhin for the FNAL Superconducting Magnet Team (presented.
Installation of the T600 at Fermilab Fermilab, February 15,
SPHENIX Mechanical Don Lynch & Rich Ruggiero April 10, 2014.
WBS 1-7 System Assembly & Installation John Voirin August 10-11, 2011.
2005-Apr-04MPI Calorimeter Plans for SLHC1 ATLAS at SLHC Calorimeter R&D at MPI Three possible routes being investigated: Verify feasibility for high intensities.
EUDET HCAL prototype; mechanics Felix Sefkow Work by K.Gadow, K.Kschioneck CALIC collaboration meeting Daegu, Korea, February 20, 2009.
Teleconf ACS – FREIA 28th March 2017
Installation of the T600 at Fermilab
Mike Anerella December 17, 2013
He Plant, LN2 Systems and Commissioing
Stress and cool-down analysis of the cryomodule
Status of design and production of LEP connection cryostat
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Leak Detection Tutorial Work
Vertex Detector Mechanical R&D Design Questions and Issues
Testing and installation of prototype diode insulation system in MB2950 Florian Meuter, 3rd Meeting on Diode Consolidation during LS2,
Far Detector Activities Late 2017 – Early 2018
iSHELL Design Review Cryostat & Optics Bench
Challenges for FCC-ee MDI mechanical design
The Quench Detection-Wire-Feedthrough Plug-In of W7-X
ATLAS Canada Alberta Carleton McGill Montréal Simon Fraser Toronto
ATLAS Canada Collaboration
ATLAS Canada Alberta Carleton McGill Montréal Simon Fraser Toronto
UPPSALA UNIVERSITY_GERSEMI PROJECT
JLAB CHL 2K COLD BOX REPLACEMENT
Presentation transcript:

ATLAS Liquid Argon Calorimeter Signal Feedthroughs ATLAS Liquid Argon Calorimeter Workshop Schloß Ringberg September 27-30 1998 Brief Overview Prototypes Vacuum Cable Development Test Station Endcap Specific Issues Management Presented by Michel Lefebvre University of Victoria British Columbia, Canada M. Lefebvre 27-30 Sept 1998 Ringberg

Endcap Cryostat (transverse view) M. Lefebvre 27-30 Sept 1998 Ringberg

Signal Feedthroughs ambient flange bolt ring pin carriers bellows Over 180k signal channels in the LAr calorimetry High density and reliability required: 1920 pins per feedthrough unit barrel: 64 units endcaps: 50 units total ambient flange bolt ring pin carriers vacuum cables bellows cold flange pigtail cables funnel M. Lefebvre 27-30 Sept 1998 Ringberg

Design Issues The design of the feedthrough components must satisfy many constraints: gas and liquid pressure loads; stresses caused by temperature gradients; stresses caused by the cryostat deformations between warm and cold; the welding of the components together must not damage the pin carriers; the heat flow through the units must be kept at an acceptable level; the electrical properties must be adequate; radiation environment; Specific to the endcap signal feedthroughs: special cables are needed for the low voltage for the HEC preamplifier: special pigtails; special vacuum cables; special warm cables (not part of feedthrough project) the heat flow for these special cables will be higher than for normal signal cables, but must nevertheless be kept at a reasonable level. there are 4 different types of endcap feedthroughs 32 Standard EM 8 Special EM 8 HEC (HEC and some EM) 2 FCAL M. Lefebvre 27-30 Sept 1998 Ringberg

Radiation Environment Up to 1016 n/cm2/yr and 2x106 Gy/y in the FCAL Less than 1012 n/cm2/yr and 20 Gy/y at the EM electronics location Less than 5x1012 n/cm2/yr and 50 Gy/y at the Hadronic Endcap electronics location M. Lefebvre 27-30 Sept 1998 Ringberg

Pin Carrier Design M. Lefebvre 27-30 Sept 1998 Ringberg

Finite Element Analysis of Feedthroughs Ambient Flange unit M. Lefebvre 27-30 Sept 1998 Ringberg

Finite Element Analysis of Feedthroughs Cold Flange Deflection under 3.5 bar pressure load maximum deflection of 68 microns M. Lefebvre 27-30 Sept 1998 Ringberg

Finite Element Analysis of Feedthroughs Cold Flange (Von Mises) Stress under 3.5 bar pressure load, seen from the LAr side maximum (Von Mises) stress of 115MPa localized in the corner of the weld region of the pin carrier Yield and ultimate stress value for the flange and pin carrier material (AISI 304L stainless steel) are about 230MPa and 483MPa respectively M. Lefebvre 27-30 Sept 1998 Ringberg

Finite Element Analysis of Feedthroughs FEA model of the Funnel and bi-metallic joint. Simulated forces: 5387N for 3.5 bar internal pressure and 695N lateral force for the cryostats relative movements (barrel only) Stainless steel Al M. Lefebvre 27-30 Sept 1998 Ringberg

Finite Element Analysis of Feedthroughs Resulting Funnel (Von Mises) Stress max stress of 114MPa M. Lefebvre 27-30 Sept 1998 Ringberg

Pin Carrier Order for Prototypes BNL and Victoria plan to produce 2 or 3 feedthrough units each Total Order: Glasseal 20 pin carriers BNL 20 pin carriers Victoria These will be gold-plated Pacific Coast Technologies 10 pin carriers BNL 10 pin carriers Victoria These will NOT be gold-plated Costs 448 pins: US$ 1455 each for 20 + US$ 40 for Au 512 pins: US$ 1621 each for 20 + US$ 47 for Au 448 pins: US$ 593 each for 500 512 pins: US$ 659 each for 500 PCT 448 pins: US$ 3872 each for 10 + US$ 1400 for Au 512 pins: US$ 3961 each for 10 + US$ 1400 for Au 448 pins: US$ 1997 each for 500 + US$ 200 for Au 512 pins: US$ 2027 each for 500 + US$ 200 for Au Other Mechanical Components for Prototypes All flanges expected late September 3 bellows expected 27th September funnel assemblies ordered, expected early October M. Lefebvre 27-30 Sept 1998 Ringberg

Pin Carrier Technology Choice One of the most important goal of the prototyping work is to gather sufficient evidence for a pin carrier technology choice; A series of tests have been devised, inlcuding visual inspection; ambient leak testing; controlled temperature cycling, and leak tests; welding of pin carriers in flanges, and leak tests; complete feedthrough assembly, and leak tests; severe tests on a few pin carriers; high pressure; rapid and/or repeated temperature cycling M. Lefebvre 27-30 Sept 1998 Ringberg

Vacuum Cable Development in Canada Signal Cables All-Flex design cables made up of 2 flexible microstrip lines rigid part of the connector are assembled around the two strip lines Aim at simpler and cheaper design Design work: E. Neuheimer (CRPP Carleton) G. Hoeppel (Strataflex, Toronto) Connector design retained: plated-through plastic spacers (Strataflex proposition) 20 Prototypes in hand one to BNL and one to Orsay for comments one was recently irradiated in Grenoble (thanks to J. Collot) Many thanks to Don Makowiecki for assistance Work towards pre-production (100) order ongoing Desired schedule: soon Get comments from BNL and Orsay 11/98 Place pre-production order 02/98 Test on pre-production cables 03/99 Place production order 05/99 First delivery for ECC (aggressive…) 11/00 First delivery for ECA Comments: We anticipate dates of last deliveries to be non critical M. Lefebvre 27-30 Sept 1998 Ringberg

Vacuum Cable Development in Canada M. Lefebvre 27-30 Sept 1998 Ringberg

Vacuum Cable Development in Canada Microstrip line Conductive spacer Sockets M. Lefebvre 27-30 Sept 1998 Ringberg

Vacuum Cable Development in Canada Insertion of a one-piece centre spacer Connector with a two-piece centre spacer M. Lefebvre 27-30 Sept 1998 Ringberg

Leak Test Setup in Victoria Leak detection using He leak detector supported by an RGA Leak detector services warm and cold test stations Cooling by cryo-cooler or LN2 All assembled, in use M. Lefebvre 27-30 Sept 1998 Ringberg

Leak Test Setup in Victoria RGA Ion Pump Cold Tests Ambient Test Platter He Leak Tester M. Lefebvre 27-30 Sept 1998 Ringberg

Leak Test Setup in Victoria Cold Tests Vessel (Pigtail bucket not shown) M. Lefebvre 27-30 Sept 1998 Ringberg

Leak Test Setup in Victoria Cold Tests Vessel (Pigtail bucket not shown) Ion Pump RGA Cryocooler Turbo and Scroll Pump Roughing Pump M. Lefebvre 27-30 Sept 1998 Ringberg

Leak Test Setup in Victoria RGA Ambient Test Platter Base Turbo Pump He Leak Tester M. Lefebvre 27-30 Sept 1998 Ringberg

Leak Test Setup in Victoria Ambient Test Platter Base He Injection Cover not shown M. Lefebvre 27-30 Sept 1998 Ringberg

Leak Test Setup in Victoria Controlled Temperature Cycling Refrigerator for pin carriers All assembled Capacity of 12 pin carriers Cooled by Cryocooler or LN2 M. Lefebvre 27-30 Sept 1998 Ringberg

Leak Test Setup in Victoria Refrigerator for Temperature Cycling M. Lefebvre 27-30 Sept 1998 Ringberg

Assembly Jig in Victoria Rotation about horizontal and vertical axis possible Various assembly scenarios under study Being assembled M. Lefebvre 27-30 Sept 1998 Ringberg

Endcap Signal Feedthrough Project Canadian Responsibilities Design Fabrication Signal Pigtails purchased from Orsay Low Voltage Pigtails purchased from MPI Commissioning Transport Assistance during installation: Considering to cover the cost of an orbital cutter Assistance during welding on the cryostat Assistance for leak testing during installation DC Electrical tests during the installation M. Lefebvre 27-30 Sept 1998 Ringberg

Endcap Signal Feedthrough Team Paul Birney Senior Technologist, TRIUMF Leak test station Assembly tooling Margret Fincke Research Associate, Victoria Electric test station Vacuum cable development Terry Hodges Chief Engineer, TRIUMF Feedthrough unit design Finite element analysis Aaron Dowling Junior Technologist, Victoria Richard Keeler Faculty, Victoria Test stations Roy Langstaff Senior Draftsman, TRIUMF Procurement issues Michel Lefebvre Faculty, Victoria Project leader Mark Lenckowski Draftsman, TRIUMF Ernie Neuheimer Research Scientist, CRPP Carleton Paul Poffenberger Production Manager, Victoria Vacuum system Greg Vowles Junior Technologist, Victoria On a consultant basis: Randy Sobie Faculty, Victoria DAQ M. Lefebvre 27-30 Sept 1998 Ringberg

Endcap Signal Feedthrough Project Top PBS Levels 4.n for ATLAS Canada corresponds to 4.2.2.1.n in the TDR M. Lefebvre 27-30 Sept 1998 Ringberg

Endcap Signal Feedthrough Project Installation Dates Assumed (CB of 11/06/98) 24/11/00 for 90 days Installation on ECC 22/02/02 for 90 days Installation on ECA M. Lefebvre 27-30 Sept 1998 Ringberg

Endcap Signal Feedthrough Project Schedule: Mechanical Components Pin Carriers ordered shortly after PRR Contract preparation to start in 1998 M. Lefebvre 27-30 Sept 1998 Ringberg

Endcap Signal Feedthrough Project Schedule: Electrical Components Critical dates: Pigtails last delivery dates for EEC and ECA Currently, no contingency... M. Lefebvre 27-30 Sept 1998 Ringberg

Endcap Signal Feedthrough Project Project Setup Details M. Lefebvre 27-30 Sept 1998 Ringberg

Endcap Signal Feedthrough Project Design Finalized Prototypes under construction pin carrier technology choice no pigtails for prototypes Some vacuum cables Vacuum cable development progressing Assembly and test stations near completion Critical path items: pigtail procurement vacuum cable development Ongoing Low voltage special cables (pigtails, low voltage) flange insulation issues M. Lefebvre 27-30 Sept 1998 Ringberg