Bunker Critical Design Review Welcome & Charge

Slides:



Advertisements
Similar presentations
Michael Scharfenstein FAC April 7, 2005 LCLS ES&H Process and Documentation.
Advertisements

Introduction and Charge to the Review of ESS Target building and Instrument Hall design requirements Roland Garoby November 2014, Lund
In-Kind Contribution Management Update Allen Weeks March 20, Lund.
LBNE Working Group Meeting December 20, :00– 5:00 PM Snake Pit.
7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.
Monolith design update – Emphasis on Neutron beam extraction design
Accelerator/program Mats Lindroos Head of accelerator April 21, 2015.
Proton-Driven Plasma Wakefield Acceleration CERN Project Structure Edda Gschwendtner, CERN Lisbon Meeting, 22 June 2012Edda Gschwendtner, CERN2.
ESS Annual Review Science Directorate - Dimitri Argyriou The challenge for 2016: Matching instrument scope with budget Andreas Schreyer European Spallation.
Electrical Engineering for NSS - Status and Planning- Thomas Gahl Electrical Engineering Group Leader February 26, 2014.
ESS | title of presentation | 2012-xx-xx | name of presenter Roles and Responsibilities sub title.
European Spallation Source Overview and Status Technical Advisory Committee 1-2 April 2015 James H. Yeck ESS CEO & Director General
Overview of the Neutron Instrument Construction Project Shane Kennedy NSS Project Leader, ESS IKON 10, Düsseldorf, 16 February.
Personnel Safety Systems Stuart Birch Senior Engineer, Personnel Safety Systems November 6 th, 2014.
Interfacing instrument teams with ESS and STAPs Ken Andersen ICB5, Copenhagen 7 th March 2016.
ESS Update TAC Meeting October 2015 James Yeck Director General
Instrument Construction Phase 1 and beyond Rob Connatser Chief Instrument Project Engineer September, 2014.
ESS Annual Review Science Directorate - Dimitri Argyriou ESS update Andreas Schreyer Director for Science European Spallation Source ERIC Engineering STAP.
ESS Annual Review Science Directorate - Dimitri Argyriou Science Directorate Update Andreas Schreyer European Spallation Source ERIC Instrument Collaboaration.
Rob Connatser NSS Instrument Work Packages and XLPM.
ACCSYS Design Reviews J. G. Weisend II Deputy Head of Accelerator Projects.
Director’s Progress Review Closeout Meeting
ESS licensing process and Readiness Reviews
2K Cold Box PDR Introduction
Director’s Progress Review Closeout Meeting
The European Spallation Source
Welcome & Charge for the Meeting
The European Spallation Source
Sample environment for Spectroscopy (TEFI, PREMP)
ESS Project Status Roland Garoby – Technical Director August 2018.
ESS Installation Binders Readiness Reviews Work Orders Mikael Jakobsson ESS Installation Manager Sep , 2018.
Instrument labs, ventilation and sample handling
NSS Instrument Project Tollgate Coordinator
STAP meeting for Imaging & Engineering October CHARGE & Organization
NSS Instrument Project Tollgate Coordinator
The Bunker Project Overview Zvonko Lazic
The Common Shielding Project
Basics for Bunker Installation Schedule Bunker CDR 2.0
Bunker Internal Review Welcome & Charge
Instruments Shielding Project Installation
Science Support Systems at ESS
MET Session workshop Job description Integration Engineer
Imaging & Engineering STAP Meeting 12th-13th of April 2018
BEER – General Update Nuclear Physics Institute CAS Přemysl Beran
Environment, Safety and Health
Large Scale Structures
Bunker -Target interfaces
Bunker Project Schedule/Budget
Instruments – Bunker Wall interfaces
Welcome Update on ESS Construction Project
Charge for CSPEC Detector Construction Workshop
TG3 Process /Part 2 Gábor László NSS Lead Instrument Engineer
Technical Updates Gábor László NSS Lead Instrument Engineer
NSS integrated installation plan workshop Introduction
Preliminary Project Execution Plan
Bunker Project Schedule/Budget
Spectroscopy STAP Meeting ESS, 8th of April 2019
Licensing update ESHAC #7, October 2017
Imaging & Engineering Diffraction STAP Meeting ESS, 21th of March 2019
Update on ESS Construction Project Charge to the SANS STAP
Lessons from the 1st Safety Readiness Review
Feedback from IKON 14 Spectroscopy.
Test Beamline System Requirements and Charge to PDR Committee
Introduction, Overview, Charge, Project Plan, Requirements
Plan for early Operation
ESHAC Meeting # Peter Jacobsson Head of ESH
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
Reflectometry STAP Meeting ESS, 29th of April 2019
Welcome and Charge for the Meeting
SKADI Current Status STAP-Meeting
Presentation transcript:

Bunker Critical Design Review Welcome & Charge Shane Kennedy NSS Project Leader www.europeanspallationsource.se Bunker CDR#2, Medicon Village, 15th October 2018

NSS Project scope: 15 neutron instruments + test beamline + support labs Nuclear Physics Institute BEER D07 D08 D04 E03 E04 + C-SPEC NMX BIFROST MIRACLES ODIN MAGIC DREAM T-REX HEIMDAL Test Beam Line VESPA FREIA LOKI ESS Lead Partners for instrument construction SKADI + ESTIA ESS In-Kind Partners also collaborate on sample environment, data management, lab fitout (D04, D08, E03 & E04) etc. ESS Instrument Layout (September 2017)

Recent history (CDR#1 -. CDR#2) Main changes needed after CDR#1 (i.e. Requirements, neutronics, documentation) Zvonko will discuss ESS Rebaselining: BOT shift from Oct 2019 to July 2022 consequences for bunker

Rebaseline schedule for Neutron Beam Instruments (V4 Rebaseline schedule for Neutron Beam Instruments (V4.0, 11th May 2018) from Installation workshop with teams building first 8 Instruments (8th May) Preliminary Design Detailed Design Manufacturing & Procurement Installation & Integration Hot Commissioning/Early science Operation West sector North sector East and South sectors Current date First access to NSS bldgs (E01) Start User Program (3NBI*) BOT & start HC of NBI* 8NBI* in User Program Safest instrument choices to be Ready for SOUP in West sector (BEER, CSPEC, BIFROST & MAGIC) & East (ESTIA) Most desirable instrument choices for early science highlights are in the South and North (ODIN, DREAM & LOKI). Selection of first NBI for SOUP in March 2023 Knock-on delays to NBI: 9 – 15 of ~ 1 yr and 16 – 22 of ~ 1 ½ yr 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 * NBI = Neutron Beam Instrument

CDR committee members External members: Internal (ESS) Members: Phil Ferguson (chair), SNS Tim Broome, STFC Romuald Hanslik, FZ-Jülich Internal (ESS) Members: Masa Arai, Technical Coordinator François Javier, ESH & Q Rikard Linander, Target Division

Charge for this review meeting Purpose: to assess whether bunker design satisfies all stated design requirements and whether it is defined at a level of detail consistent with release for engineering detailing and manufacturing, according to the procurement/production plan for the project: Specific questions: Are system requirements and interface requirements properly defined and complete? Have safety and hazards been properly considered and addressed? Do the System Design Description documents and related drawings adequately describe the design to the degree needed for fabrication or procurement; as per the project plan? Does the design satisfy the functional and performance requirements? Are the Manufacturing Plan, the Installation Plan, and System Analysis Reports finalized and do they support the stated design?

Agenda for CDR (1/3)

Agenda for CDR (2/3)

Agenda for CDR (3/3)