Lecture Network Analysis

Slides:



Advertisements
Similar presentations
Chapter 7 Project Management
Advertisements

CP Chapter 4 Schedule Planning.
Copyright © 2008 Pearson Education, Inc. Slide 13-1 Unit 13C Scheduling Problems.
PRJ566 Project Planning and Management Lecture: Dependencies and Network Diagrams.
Estimating, scheduling and budgeting
Based on the book: Managing Business Process Flows
Network Diagramming Network Analysis  The common term for network analysis is PERT  PERT stands for Program Evaluation and Review Technique  The word.
CSSE Sep.2008 Constructing and Analyzing the Project Network Diagram Chapter 6.
D1: Critical Events And Critical Paths. D1: Critical Events And Paths A critical path is the list of activities on an activity network that, if they are.
Advanced Project Management - CPH
Scheduling The Project  Scheduling Planning, budgeting and scheduling are all part of the same process Planning a project, developing a budget for it,
Copyright © 2008 Pearson Education, Inc. Slide 13-1 Unit 13C Scheduling Problems.
CSSE 372 Week 6 Day 2 Constructing and Analyzing the Project Network Diagram  PERT Chart PERT was invented for the Nautilus submarine project. Ok, maybe.
إدارة المشروعات Projects Management
Tutorial 2 Project Management Activity Charts (PERT Charts)
PREPARED BY : NOR AZAH BINTI AZIZ KOLEJ MATRIKULASI TEKNIKAL KEDAH PROJECT NETWORK DIAGRAM.
5.8 Project Management Chapter 37 HL - Only.
CPA A house is to have new carpets fitted throughout. The work involved has been divided into a number of tasks, as shown in the table.
Managing time ‘Time is nature’s way of stopping everything happening at once’ Hughes & Cotterell 2002 Production Process.
Network planning Learning objectives After these lectures you should be able to: - Produce and analyse activities networks - Calculate earliest and latest.
Analysing the AoA network Project Management. Total Project Time The minimum time in which the project can be completed. Calculation: forward pass Forward.
Module 5 – Networks and Decision Mathematics Chapter 24 – Directed Graphs.
Precedence Network Calculations the basic information that should be calculated in the precedence network are: 1) Early activity start (ES) 2) Early activity.
CS3773 Software Engineering Lecture 8 Software Planning and Estimation.
15C Backward scanning and crashing
Project Management Lecture Resource Analysis. Introduction Project planning Gantt chart and WBS Project planning Network analysis I Project planning Network.
Lecture Network Analysis
Project Management Chapter 3 BUSI 2106 – Operations Management.
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
ERT461 BIOSYSTEMS ENGINEERING DESIGN 1 ERT424 BIOPROCESS PLANT DESIGN 1.
George’s Bicycle Creating a Gantt Chart.
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
Software Project Management Task Estimating and Scheduling
PROJECT MANAGEMENT Syllabus Outcomes : Construct and interpret a network, identify the critical path, and calculate the free and total float. Evaluate.
ENGM91 ACTIVITY PLANNING Unit 2
© Pearson Education Limited 2004 OHT 8.1 Cadle and Yeates: Project Management for Information Systems, 4th edition Critical Path Method(CPM)
1 Selected Topics on Project Management The Critical Path Dr Marc Conrad 1Marc Conrad.
Business Department Session 6 Exam Question –Draw Network diagram –Identify Critical path –Sketch Gantt Chart –‘Crash’ the project Reduce the project completion.
Analysing the AoN network Project Management (seminar)
University of Sunderland CIFM02 Unit 2 COMM02 Activity Planning Unit 2.
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
 Chapter 6: Activity Planning – Part 3 NET481: Project Management Afnan Albahli.
A2 Operations Management Critical Path Analysis. How long will it take? n Walls have decided to launch a new Magnum ice cream. Machine delivery will take.
 Chapter 6: Activity Planning – Part 2 NET481: Project Management Afnan Albahli.
Scheduling and Budgeting Engineers Without Frontiers CEE 402.
Chapter 4 MIS Project Management Lecturer Sihem Smida Sihem Smida Developing a project plan.
IE 366 Chapter 6, Section 10 Project Planning and Scheduling.
Critical Path Analysis (CPA)
Critical Path Method(CPM)
UNIT II Scheduling Procedures & Techniques FLOAT
Project Scheduling Lecture # 1.
Project planning Unit 3 Employability and Professional Development
Project Management for Business
Critical Path Analysis (CPA)
Multiple dependency activity on node networks
Analysing the AoA network
SE Tasks for a Concept Development Project
Analysing the AoA network
Analysing the AoA network
Activity on Node Approach to CPM Scheduling
Analysing the AoA network
BEST VIEWED IN SLIDE SHOW MODE
Project Management (lecture)
Project Planning By Phaik San Liew.
Project Management (lecture)
Exercise – A small building.
Analysing the AoA network
Project Management (lecture)
Project Management (lecture)
Multiple dependency activity on node (AoN) networks
Presentation transcript:

Lecture Network Analysis Project Management Lecture Network Analysis

Plan Introduction Project planning Project planning Risk management Network analysis I Network analysis II Introduction Project planning Gantt chart and WBS Network analysis I Network analysis II Project planning Resource analysis Risk management Quality Budgets and cost control Project teams

Why Network Diagrams? Splits up the decision making process into Method/logic - the order in which tasks have to be completed Time – estimates for the time to completion can be added to each task Resources – these can be added and then analysis carried out

Project Exercise 1

Project Exercise 1

Why Network Diagrams? Splits up the decision making process into Method/logic - the order in which tasks have to be completed Time – estimates for the time to completion can be added to each task Resources – these can be added and then analysis carried out

Two Parts to the Analysis Forward Pass Calculates the Duration of the Project Backward Pass Calculates the slack/float for each task and shows the critical path

Forward Pass In a game of rugby it is a means of cheating often missed by referees (BBC, 2005)

Forward Pass …but in project management it is used To calculate the total duration of the Project… For each task: Take the earliest start time (EST) Calculate the Earliest finish time (EFT): EFT = EST+Duration

What’s in the box? Earliest Start Estimated Duration Earliest Finish Activity Number Activity Description Latest Start Float Latest Finish Earliest Start Estimated Duration Earliest Finish Activity Number Activity Description Latest Start Float Latest Finish Earliest Start Estimated Duration Earliest Finish Activity Number Activity Description Latest Start Float Latest Finish

Forward Pass

Forward Pass

Project Exercise 1

Exercise 1 – Forward Pass Carry out a forward pass on Project in Exercise 1

Project Exercise 1

Project Exercise 1 Dangler Dangler Dangler

Start and Finish Nodes

What’s in the box? Earliest Start Estimated Duration Earliest Finish Activity Number Activity Description Latest Start Float Latest Finish Earliest Start Estimated Duration Earliest Finish Activity Number Activity Description Latest Start Float Latest Finish Earliest Start Estimated Duration Earliest Finish Activity Number Activity Description Latest Start Float Latest Finish

Backward Pass To calculate the float for each task? For each task: Take the latest start time (LST) Calculate the latest finish time (LFT): LST = LFT-Duration

Backward Pass

Backward Pass

Project Exercise 1

Exercise 1 – Backward Pass Carry out a backward pass on project exercise 1

Ex1 - After Backward Pass

What about the float? Float = LFT-EFT Or Float = LST-EST

What about the float? Float represents the amount of time that the task can be delayed without affecting the outcome of the project A task with zero float cannot be delayed and is therefore critical to the timely completion of the project

What about the float? A time optimised project will have a sequence of tasks from start to finish that have zero float This sequence of tasks is called the critical path

Project Exercise 1

Exercise 1 – Critical Path Calculate the float for each task and identify the critical path through the project

Ex1 – Float

Ex1 – Critical Path

Questions My Project has no critical path. What does this mean? My programmer has broken his big toe in a skiing accident and cannot type for two weeks (he has a valid sick note). How will this affect my software delivery date?

Directed Study Find the critical path for Project Exercise 2 (see Lecture 3). Find the critical path for the large project in Exercise 3.

Plan Project planning Introduction Project planning Project planning Network analysis I Network analysis II Introduction Project planning Gantt chart and WBS Network analysis I Network analysis II Project planning Resource analysis Risk management Quality Budgets and cost control Project teams Project planning Resource analysis Risk management Quality Budgets and cost control Project teams