Project Scheduling: Lagging, Crashing and Activity Networks Chapter 10 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall10-1.

Slides:



Advertisements
Similar presentations
Chapter 3 Managing the Information Systems Project
Advertisements

Copyright © 2003 Pearson Education, Inc. Slide 1 Computer Systems Organization & Architecture Chapters 8-12 John D. Carpinelli.
Copyright © 2011, Elsevier Inc. All rights reserved. Chapter 6 Author: Julia Richards and R. Scott Hawley.
Author: Julia Richards and R. Scott Hawley
1 Copyright © 2010, Elsevier Inc. All rights Reserved Fig 2.1 Chapter 2.
3 Project Management PowerPoint presentation to accompany
Precedence Diagramming
Lecture 4 – PERT Diagrams & CPM
WBS: Lowest level OBS: Lowest level
Project Scheduling: Lagging, Crashing and Activity Networks Chapter 10 © 2007 Pearson Education.
Developing a Project Plan CHAPTER SIX Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
IE 2030 Lecture 5: Project Management Drawing Gantt Charts Time on horizontal axis, Activities on vertical axis. 1 bar per activity Length of bar = required.
Chapter 10 Project Scheduling: PERT/CPM
Chapter 7 Project Management
Developing a Project Plan CHAPTER SIX Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
CP Chapter 4 Schedule Planning.
CIS 480 Systems Analysis and Design
Chapter 6: Developing a Project Plan
Project Management 6e..
Project Management from Simple to Complex
Chapter 17 Project Management McGraw-Hill/Irwin
Chapter 6 Time Planning & Networks
Richard Fisher 1 The University of Texas at Dallas Project Management BA 4320 Richard Fisher The University of Texas at Dallas.
Developing the Project Plan
9-1 ELC 347 project management Day 19. Agenda Integrative Project –IP part 4 not graded yet –Part 5 Due Nov 22 (page 318) –Any of the first five sections.
Project Management Projects are unique, one-time operations designed to accomplish a specific set of objectives in a limited timeframe Project managers.
Where We Are Now Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved.
Project Management Project Management
Finding the Critical Path
Developing a Project Plan
SE503 Advanced Project Management
Project Scheduling: Lagging, Crashing, and Activity Networks
Project Scheduling: Lagging, Crashing and Activity Networks
Chapter 9 Project Scheduling: PERT/CPM
Day 19 ELC 347/BUS 348/PSA 347.
Managing Projects Chapter 14.
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edwards University.
Analyzing Genes and Genomes
Essential Cell Biology
Intracellular Compartments and Transport
PSSA Preparation.
Essential Cell Biology
Energy Generation in Mitochondria and Chlorplasts
Introduction to Management Science
ELC 347 project management Week 11. Agenda Integrative Project –3rd part Graded –4 th part due next week –Outline of deliverables (posted in WebCT)Outline.
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
Project Scheduling: Networks, Duration estimation, and Critical Path.
9-1 Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
5/4/20151 NETWORK SCHEDULING TECHNIQUES. 5/4/20152 Network Diagrams  PMI defines the scheduling process as: “the identification of the project objectives.
Project Scheduling: Networks, Duration Estimation, and Critical Path
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Day 15.
Project Scheduling: Networks, Duration estimation, and Critical Path
Project Management Dr. Everette S. Gardner, Jr.. Project Management2 PERT / CPM advantages 1. Disciplined planning 2. Realistic objectives 3. Unambiguous.
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall o P.I.I.M.T o American University of Leadership Ahmed Hanane, MBA, Eng, CMA, Partner.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall8-1 Cost Estimation and Budgeting.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
PowerPoint presentation to accompany Heizer/Render – Principles of Operations Management, 5e, and Operations Management, 7e © 2004 by Prentice Hall, Inc.,
Lags in Precedence Relationships
ENGM 631 Optimization Ch. 10: PERT/CPM. Great Pyriamid of Cheops (2,500 B.C.) 42,300,000 Stone Blocks 440 Stories 4Accuracy of 0.04 inch 413 acres level.
Project Management MGT 30725
Project Planning & Scheduling
P.I.I.M.T American University of Leadership
The Project Schedule and Budget
Project Scheduling Lecture # 1.
Project scheduling Chapter 10 Copyright ©2016 Pearson Education, Inc.
Project Planning and Budgeting
Project Scheduling: networks, duration estimation, and critical path
Project Scheduling: Lagging, Crashing and Activity Networks
ELC 347 project management
Presentation transcript:

Project Scheduling: Lagging, Crashing and Activity Networks Chapter 10 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall10-1

Lags in Precedence Relationships The logical relationship between the start and finish of one activity and the start and finish of another activity. Four logical relationships between tasks 1.Finish to Start 2.Finish to Finish 3.Start to Start 4.Start to Finish Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall10-2

Finish to Start Lag Most common type of sequencing Shown on the line joining the modes –Added during forward pass –Subtracted during backward pass 0 A 6 Spec Design 6 6 B 11 Design Check 5 15 C 22 Blueprinting 7 Lag 4 This lag is not the same as activity slack Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall10-3

Finish to Finish Lag Two activities share a similar completion point –The mechanical inspection cannot happen until wiring, plumbing, and HVAC installation are complete 10 A 16 Plumbing 6 16 B 21 HVAC 5 21 C 22 Inspection 1 15 D 21 Wiring 6 Lag 3 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall10-4

Start to Start Lag Logic must be maintained by both forward and backward pass Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall A 33 Plumbing 6 33 B 36 HVAC 5 36 C 37 Inspection 1 30 D 36 Wiring 6 Lag 3

Start to Finish Lag Least common type of lag relationship Successors finish dependent on predecessors start 22 A 28 Plumbing 6 28 B 33 HVAC 5 33 C 34 Inspection 1 30 D 36 Wiring 6 Lag 3 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall10-6

Gantt Charts Establish a time-phased network Can be used as a tracking tool Benefits of Gantt charts 1.Easy to create and comprehend 2.Identify the schedule baseline network 3.Allow for updating and control 4.Identify resource needs Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall10-7

Create a Gantt chart based on the activities listed in the table. TaskTimePredTaskTimePred Z8--U3W Y5ZT6V X8ZS7U,T W4Y,XR9S V5W Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall10-8

Gantt Chart With Resources in MS Project Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall10-9

Crashing The process of accelerating a project Principal methods for crashing Improving existing resources productivity Changing work methods Increasing the quantity of resources Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall10-10

Managerial Considerations Determine activity fixed and variable costs The crash point is the fully expedited activity Optimize time-cost tradeoffs Shorten activities on the critical path Cease crashing when –the target completion time is reached –the crashing cost exceeds the penalty cost Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall10-11

What is the lowest cost to complete this project in 53 weeks? Times are in weeks and costs in dollars. ActivityPredNormal Time Min Time Normal Cost Crash Cost A BA CA DB, C ED FD GE, F HG Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall10-12

Activity on Arrow Networks Activities represented by arrows Widely used in construction Event nodes easy to flag Forward and backward pass logic similar to AON Two activities may not begin and end at common nodes Dummy activities may be required Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall10-13

1.Use AOA to sketch the network that represents the project as described in the table. 2.Calculate early and late start and finish times for all activities. ActivityTimePredActivityTimePred A4--F4D B2AG15D C10AH7E,F,G D3B,CK11G E15B Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall10-14

Activity on Arrow Network Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall10-15 A H F E D C B K G

Controversies in the Use of Networks Networks can be too complex Poor network construction creates problems Networks may be used inappropriately When employing subcontractors –The master network must be available to them –All sub-networks must use common methods Positive bias exists in PERT networks Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall10-16

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall10-17