Critical Path Analysis Activity duration Shower3 Dry hair8 Fetch car7 Iron clothes12 Dress and make-up10 Drive to interview20 Example 4.1 textbook pages.

Slides:



Advertisements
Similar presentations
3 Project Management PowerPoint presentation to accompany
Advertisements

Critical Path Analysis. Why Is CPA Important? CPA is arguably the piece of maths used most often, outside of basic arithmetic. Important not only in commerce.
Precedence Diagramming
WBS: Lowest level OBS: Lowest level
Developing a Project Plan CHAPTER SIX Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
IE 2030 Lecture 5: Project Management Drawing Gantt Charts Time on horizontal axis, Activities on vertical axis. 1 bar per activity Length of bar = required.
Chapter 10 Project Scheduling: PERT/CPM
Developing a Project Plan CHAPTER SIX Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Associate Professor MIS Department UNLV
CP Chapter 4 Schedule Planning.
Chapter 6: Developing a Project Plan
Project Management 6e..
Developing the Project Plan
Project Management Projects are unique, one-time operations designed to accomplish a specific set of objectives in a limited timeframe Project managers.
Start D finish A B C E I G H F J KL N M ActivityDescription AExcavate BFoundation CRough wall DRoof EExterior plumbing FInterior.
Where We Are Now Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved.
Project Management Project Management
Developing a Project Plan Chapter 6 Luck favors to a prepared mind….. Louis Pasteur.
Developing a Project Plan
1 1 Slide © 2006 Thomson South-Western. All Rights Reserved. Slides prepared by JOHN LOUCKS St. Edwards University.
Chapter 13 Project Scheduling: PERT/CPM
Chapter 9 Project Scheduling: PERT/CPM
Chapter 3 Project Management.
Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects. Use.
Prosjektstyring A 5 WEEKS B 10 WEEKS C 12 WEEKS D 8 WEEKS E 6 WEEKS ACTIVITY (t) ESEF FL LS LF We have a network with.
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edwards University.
Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.
D1: Critical Events And Critical Paths. D1: Critical Events And Paths A critical path is the list of activities on an activity network that, if they are.
Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack amount.
1 1 Slide © 2004 Thomson/South-Western Chapter 12 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
Tutorial 2 Project Management Activity Charts (PERT Charts)
CPA A house is to have new carpets fitted throughout. The work involved has been divided into a number of tasks, as shown in the table.
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
D1: Event Times.
Activity networks – Example 1 TaskDuration (hours)Immediate predecessors A3- B4- C6- D5A E1B F6B G7C, D, E The table below shows the tasks involved in.
___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry Project Management Example -
Critical Path Analysis Activity Duration mins Shower3 Dry hair8 Fetch car7 Iron clothes12 Dress and make-up10 Drive to interview20.
Module 5 – Networks and Decision Mathematics Chapter 24 – Directed Graphs.
15C Backward scanning and crashing
Prof. Awad Hanna Estimating Activity Duration Time Interval  Time Interval is selected according to the nature of the activity (seconds - minutes…) 
___________________________________________________________________________ Operations Research  Jan Fábry Project Management.
Lesson Objective Understand what critical path analysis is Be able to prioritise events and create a precedence table Begin to use the precedence table.
Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 PROJECT MANAGEMENT 18-1 Project Management.
Critical Path Example: Preparing for an interview.
 Chapter 6: Activity Planning – Part 3 NET481: Project Management Afnan Albahli.
15B Critical path analysis. In a critical path analysis, edges represent activities. Nodes (vertices) represent the end of one activity and the start.
 Chapter 6: Activity Planning – Part 2 NET481: Project Management Afnan Albahli.
Project Management – Part 1. Overview What is a project? Project management techniques Activity lists Network diagrams Critical path analysis Gant charts.
IE 366 Chapter 6, Section 10 Project Planning and Scheduling.
Activity networks – Example 1
Project Scheduling Lecture # 1.
Analysing the AoA network
Critical Path Analysis
Project Management CPM Method Tutorial-p1
PERT - The Program Evaluation and Review Technique
Lesson Objective Understand Cascade diagrams and be able to use them to draw resource histograms.
BEST VIEWED IN SLIDE SHOW MODE
Project Management (lecture)
Activity Networks
Critical Path Analysis
Critical Path Analysis
Activity Networks
Slides Prepared by JOHN LOUCKS
Critical Path Analysis
Lesson Objective Understand Cascade diagrams and be able to use them to draw resource histograms.
Exercise – A small building.
Project Management (lecture)
Operations Research Lecture 8.
Critical Path Analysis
Presentation transcript:

Critical Path Analysis Activity duration Shower3 Dry hair8 Fetch car7 Iron clothes12 Dress and make-up10 Drive to interview20 Example 4.1 textbook pages

Precedence table Activity Immediately preceding activities duration AShower-3 BDry hairA8 CFetch car-7 DIron clothes-12 EDress and make-upB,D10 FDrive to interviewC,E20 The last activities that must be completed before an activity can begin

Activity on Arc Network A(3) D(12) B(8) E(10) C(7) F(20) The network will build up with each mouse click, in the order you would construct it on paper.

Event Times A(3) D(12) B(8) E(10) C(7) F(20) Earliest event time EET Latest event time LET Each event node needs two boxes, to mark in the event times.

Earliest Event Times A(3) D(12) B(8) E(10) C(7) F(20) To find EETs, work forwards through the network from the start node to the finish node. The EET for an event occurs when all activities leading into that event are complete.

Latest Event Times A(3) D(12) B(8) E(10) C(7) F(20) To find LETs, work backwards through the network from the finish node to the start node. The LET for an event is the latest it can occur without delaying subsequent events.

Critical Activities A(3) D(12) B(8) E(10) C(7) F(20) Critical activities are activities that cannot run late. For critical activities: Latest finish Earliest start = length of activity The green arrows mark the critical activities, which form the critical path. The critical path(s) must form a continuous route from the start node to the finish node.

Float Total Float latest finish – earliest start – length of activity Independent Float earliest finish – latest start – length of activity Interfering Float Total float – Independent float TotalIndependentInterfering A B C It is useful to represent float in a table.

Float (answers) TotalIndependentInterfering A101 B101 C15 0 Hint: Total is maximum possible float so take outside no.s Independent is minimum possible float so take inside no.s