BRIEFING THE PORTFOLIO COMMITTEE ON WATER AND SANITATION ON UNFINISHED INFRASTRUCTURE PROJECTS DDG: IBOM.

Slides:



Advertisements
Similar presentations
DEBT OWED TO MUNICIPALITIES PRESENTATION TO THE PORTFOLIO COMMITTEE ON COOPERATIVE GOVERNANCE AND TRADITIONAL AFFAIRS.
Advertisements

DWA CORPORATE IDENTITY Presented by: Johan Maree Deputy Director: Media Production 12 December 2012 RBIG, NTP, ACIP, MWIG Quarterly Workshop North West.
BUCKET ERADICATION PROGRESS SELECT COMMITTEE ON LAND AND ENVIRONMENTAL AFFAIRS HEARINGS 22 & 23 February 2007 Presented by Ms. T. Mpotulo Department of.
SIP 18 WATER AND SANITATION MASTER PLAN Water and Sanitation Master Plan NDHS and DWA Water & Sanitation Master Plan.
PRESENTATION TO THE PORTFOLIO COMMITTEE ON POLICE 14 August 2012.
WS Infrastructure Programme Quarterly Workshop North West Presented by: Neo Thulo Programme Manager North West Date: 31 October 2013.
Water Services Bulk Infrastructure Programme January 2008.
WS Infrastructure Programme
1 ALLOCATIONS for the Integrated National Electrification Programme 2009/10 Presentation to the Select Committee on Finance 25 February 2009.
STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February Briefing by Department of Water Affairs.
TECHNICAL OVERSIGHT MONITORING AND SUPPORT VISITS ON REGIONAL PROJECTS: 2014/15 Prepared by: R. Gillmer Chief Engineer : Technical Support 21 August 2014.
DWA CORPORATE IDENTITY Presented by: Johan Maree Deputy Director: Media Production 12 December 2012 RBIG, NTP, ACIP, MWIG Quarterly Workshop Northern Cape.
1 Water Services to Schools and Clinics Programme 20 June 2007 Presentation to Select Committee on Education and Recreation By DWAF.
DWA CORPORATE IDENTITY Presented by: Johan Maree Deputy Director: Media Production 12 December 2012 RBIG, NTP, ACIP, MWIG Quarterly Workshop Western Cape.
WS Infrastructure Programme Quarterly Workshop GAUTENG REGION Presented by: Jabulani Maluleke RBIG Project Manager: Date: 31 – 01 October 2013.
DCoG Presentation to the Appropriations Committee HEARINGS ON THE MEDIUM TERM BUDGET POLICY STATEMENT 2 November 2010.
LIMPOPO INFRASTRUCTURE SUMMIT 5 th – 6 th October 2010 Polokwane: Peter Mokaba Stadium Draft Resolutions.
MASIBAMBANE CO-ORDINATING COMMITTEE MEETING PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP) 22 nd JUNE 2012 MASIBAMBANE CO-ORDINATING.
Presentation of the Property Rates Debt to the Port Folio Committee on Cooperative Governance & Traditional Affairs 25 October 2011 Presented by: Cathy.
Presentation to Portfolio Committee Progress on the Departmental Under-Expenditure and Recovery Plans -Mr. T. Zulu Director-General 1.
Presentation to the Select Committee on Finance 26 FEBRUARY 2006.
NATIONAL DEPARTMENT OF HEALTH National Health Insurance Grant Select Committee on Appropriations Hearing on 3 rd and 4 th Quarter Expenditure 4 th June.
STANDING COMMITTEE ON APPROPRIATIONS Water Trading Entity 1 Briefing on the 4 th Quarter Expenditure Report for the Financial Year 2011/12.
QUARTERLY PERFORMANCE OF THE MUNICIPAL INFRASTRUCTURE GRANT (MIG) – 2005/06 AND 2006/07 FINANCIAL YEARS Presentation to the Select Committee On Finance.
6/3/11 1 DEPARTMENT OF WATER AFFAIRS “Progress in the Accelerated Community Infrastructure Programme (ACIP)” Briefing to the Select Committee on Land and.
Presentation to the Portfolio Committee: Water and Environmental Affairs Presentation by Department of Water Affairs 30 – 31 March 2011 Budget allocation.
Performance of the Integrated National Electrification Programme as at 30 June 2008 (4 rd Quarter) Presentation to the Select Committee on Finance 14 August.
Public Hearings on Division of Revenue Bill, 25 February 2009 Presentation by Department of Water Affairs and Forestry 1.
Parliamentary submission on the eradication of the Bucket Toilet System 22 & 23 February 2007 Cllr. Derrick Ndlovu.
PRESENTATION TITLE Presented by: Name Surname Directorate Date Briefing the Portfolio Committee on Water and Sanitation on Interventions to improve water.
1 Select Committee on Economic Development Progress relating to the implementation of Integrated National Electrification Programme (INEP)
Commission on Restitution of Land Rights
Presentation to the Portfolio Committee on Energy
Portfolio committee May 2007 MEC JF van Wyk
National Treasury Special Pensions Administration
Eastern Cape :2016/17 Stopping Considerations
PRESENTATION TO THE TRANSPORT PORTFOLIO COMMITTEE BUS SUBSIDY BUDGET SHORTFALL 2008/09 03 FEBRUARY
Overview of the CoJ Water & Sanitation Master Plan
Briefing on Current Expenditure and their Performance Trends
PORTFOLIO COMMITTEE ON WATER AFFAIRS AND FORESTRY
Trevor Balzer: Acting CFO Helgard Muller : CD Water Services
BRIEFING THE PORTFOLIO COMMITTEE ON WATER AND SANITATION
PORTFOLIO COMMITTE PRESENTATION
North West provincial Treasury presentation on Conditional Grants and Capital Expenditure as at 30 June 2008.
PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC AND BUSINESS DEVELOPMENT ANNUAL PERFORMANCE REPORT OF THE COMPENSATION FUND FOR THE FINANCIAL YEAR
Mr Ntandazo Vimba and Henri Marais
FIRST QUARTER ANALYSIS REPORT
Presentation of the 2009/10 Annual Report
SELECT COMMITTEE ON PUBLIC SERVICE: REPORT ON QUALITY SANITATION TO HOUSEHOLDS PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP)
Responses to issues raised: report as submitted on 4 April 2018
Water and Sanitation Portfolio Committee
Bucket eradication in formal settlements
portfolio committee on ON the Independent development trust
PRESENTATION ON THE FINANCIAL MANAGEMENT INFORMATION 3rd QUARTER IRO 2007/ FEBRUARY 2008.
BUCKET ERADICATION : KWAZULU-NATAL
PRESENTATION TO THE SELECT COMMITTEE ON APPROPRIATIONS
STANDING COMMITTEE ON APPROPRIATIONS
Water & Environmental Affairs
MANGAUNG METROPOLITAN MUNICIPALITY
Progress on the Bucket Eradication Programme
Progress report on the roll out of GIAMA
National Sanitation Programme
PRESENTATION TO PORTFOLIO COMMITTEE ON DEFENCE AND MILITARY VETERANS ON THE STATUS OF THE DMV INFRASTRUCTURE 08 November 2017 Presented by Mr. M. OZINSKY.
PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP) 17 AUGUST 2012 By MR T ZULU DIRECTOR GENERAL.
Water Services Targets
MPUMALANGA 4TH QUARTER EIG PERFOMANCE
BRIEFING THE PORTFOLIO COMMITTEE OF WATER AND SANITATION
PROGRAMME 2 CONT - NATIONAL WATER RESOURCES INFRASTRUCTURE BRANCH.
PRESENTATION ON THE CONDITIONAL GRANT TO THE SELECT COMMITTEE
Presentation transcript:

BRIEFING THE PORTFOLIO COMMITTEE ON WATER AND SANITATION ON UNFINISHED INFRASTRUCTURE PROJECTS DDG: IBOM

TABLE OF CONTENTS AUGMENTATION PROJECTS STRATEGIC ASSET MANAGEMENT (DSRP) SANITATION (BUCKET ERADICATION PROGRAMME) RBIG PROJECTS

Augmentation projects

Augmentation Unfinished Projects Project Name LOCATION 2019/20 FY Budget allocation (R‘000) Delays and recovery plan Expected completion date Mdloti River Development Project: Raising of Hazelmere dam KZN: eThekwini Metropolitan Municipality 110 000 Delays: Delayed procurement of permanent load cells Delay of resolution of disputes and claims Expiry of contract on 31 July 2018 and subsequent termination by contractor on 9 October 2018 Proposed Intervention Utilisation of DWS Construction Unit to execute all the works that do not require specialist contractor. Implement amicable solution to resolve disputes, claims and variation orders on the terminated contract. Compilation of definitive scope of work breakdowns and timeframes to complete the works. Alignment of all contracts (Engineer, ECO, OHS and Contractor) with definitive scope of work and time frame. Reappointment of Specialist Contractor by end of Mid March 2019. March 2020 Raising of Tzaneen Dam Limpopo: Greater Tzaneen Municipality 208 930 Delays Delays in the appointment of Contractor due transfer of project to DWS from Lepelle N. Water Water shortages and loss of public confidence Water Users financial compensation Use of DWS construction Unit Use of DWS Engineering Services as the PSP Stakeholders engagement October 2020

Augmentation Unfinished Projects cont... Project Name LOCATION 2019/20 FY Budget allocation (R‘000) Delays and recovery plan Expected completion date Olifants River Water Resources Development Project (ORWRDP-Phase 2D, E & F) Limpopo: Sekhukhune District Municipality 2D 160 203 2E & F Delays: Funding constraints Land matters and illegal mining Relocation and compensation of affected land owners on critical path Borrow pit license negotiations Encroachment to the pipeline servitude Proposed Intervention Reprioritise funding within ORWRDP Prioritise land acquisition and social facilitation. Secure Department of Mineral Resources intervention on illegal mining activities Engage with DMR to resolve the challenge on the rehabilitation funds for the project Finalise Memorandum of Understanding with tribal authorities Negotiate with Dikolong Mine to secure availability of the site 2021 Depending on availability of Funds

STRATEGIC ASSET MANAGEMENT: DSRP

DSRP UNFINISHED PROJECTS Project Name LOCATION 2019/20 FY Budget allocation (R‘1000) Delays and recovery plan Expected completion date Marico Bosveld Dam North West Groot Marico 5 000 The contract between DWS and the external Contractor expired before the Contractor can commence with site establishment due to the non-performance by the Contractor. Internal Contractor was approached to assist in taking over the project and complete it. The Internal Contractor’s priced BoQ was approved. The internal contractor will commerce with site establishment in April 2019 and is expected to complete the project in 6 month from commencement. 30 September 2019 Kalkfontein Dam Free State Koffiefontein 5 400 Community strikes delayed the sourcing of the local labour for the project. The local labour was appointed on the 12 February 2019 and will go for medical test on the 5 march to confirm fitness for working in construction. The Contractor will follow an accelerated project programme to complete the project. 31 May 2019 Rietspruit dam Ventersdorp 15 695 The project was requested to be removed from 2018/19 financial year due to delays by Top Management to approve the request to procure the service of the Environmental Control Officer (ECO). The request to procure the services of the Environmental Control Office is expected to serve at the next Top Management meeting scheduled for 5th March 2019. In the mean time the Internal Contractor was appointed and requested to start with the procurement of required materials. 31 July 2019

SANITATION: BUCKET ERADICATION PROGRAMME

BUCKET ERADICATION PROGRAMME Status Report NORTHERN CAPE PROVINCE DWS resolved to utilise it Internal Construction Unit for the completion of 4 of the 6 Projects of which; 4 projects require Sewer Collectors and Bulk Mains to allow for functional sanitation services. Of which 2 projects will require Pump stations; A further 2 projects will be completed by the Water Services Authority (as a WSIG Schedule 5B grant allocation). (Dawid Kruper LM, Louisvale PS: a PSP is already appointed, contractor is planned to be appointed in Feb 2019. Siyancuma LM, Breipaal PS: PSP / Contractor already appointed. Planned to start with construction in Feb 2019. 9

NORTHERN CAPE PROVINCE MUNICIPALITY PROJECT BUCKETS CONNECTED (Y/N) WORK REQUIRED IMPLEMENTOR Siyacuma LM Griekwastad 475 N Completion of the internal reticulation and Installation of a Pump station DWS Construction Campbell 596 Outfall Sewer and pump station required to match new municipal proposed oxidation ponds. Tsantsabane LM Maranteng 392 Sewer Collector (Reticulation) network expansion required Postdene 219 expansion required and construction of 368 toilet structures

FREE STATE PROVINCE A turnkey contractor was appointed to complete the Bucket Eradication Programme in the Free State Province the Department issued a notice of intention to terminate the relationship after the contract lapsed in March 2018; 1 out of 12 projects remains incomplete Senekal requires the completion of internal reticulation; The Department resolved to utilise Internal Construction for the completion of Bulk infrastructure of which; 7 projects requires bulk services to enable the flushing of new toilets;

FREE STATE PROVINCE MUNICIPALITY PROJECT BUCKETS CONNECTED (Y/N) WORK REQUIRED IMPLEMENTOR Setsoto LM Ficksburg 1469 Y (& N) 1215 buckets eradicated and functional. Remaining 218 not functional due to not being connected to the Bulk Sewer Main. Rising main and 3 x ump-stations DWS Construction Senekal 2435  N Lack of water supply requires Greywater circuit (Grey-water package plant); Sewer Collector system must be connected to a Bulk Sewer Main and Pump-station. Completion of internal reticulation Clocolan 3379 Sewer collection system to connected to Bulk Main and therefore not connected to the WWTW. Bulk Sewer Main and Pump-station Nketoana LM Reitz 739 Bulk sewer main and pump- station required.

FREE STATE PROVINCE MUNICIPALITY PROJECT BUCKETS CONNECTED (Y/N) WORK REQUIRED IMPLEMENTOR Nketoana LM Arlington 1192  N Inadequate water supply; need to erect a water tank and Grey-water package plant to be connected, Pump-Station, Bulk Sewer Main. DWS Construction Petrus Steyn 960 Bulk Sewer main to be constructed as well as a Pump station to connect collector system with WWTW. Tokologo LM Dealesville 1290 N  2 Pump stations

Regional bulk infrastructure PROJECTS

RBIG projects Category and description No of projects Mega Total cost of at least R1 billion over the project life cycle 15 Large Total cost of at least R250 million to R1 billion over the project life cycle 53 Small 38 Total 106

RBIG Unfinished Projects Project Name LOCATION 2019/20 FY Budget allocation (R‘000) Delays and recovery plan Expected completion date Sebokeng Wastewater Treatment Works Gauteng 128 912 Delays: Constant community unrest Constant labour unrest Proposed Intervention National Treasury has involved in South African Defence Force to implement some of the project modules in partnership with Department of Water and Sanitation. This has also assisted in dealing with community unrest 2020 Polokwane Bulk Water Supply Limpopo 530 997 Delays Municipality increased the scope which is funded through their internal funding. The project is implemented within the CBD of Polokwane, this causes some delays as there is congestion within the CBD The Implementing Agent has extended the contract for the contractor who was on site and time frame has been extended to implement the amended scope

RBIG Unfinished Projects Project Name LOCATION 2019/20 FY Budget allocation (R‘000) Delays and recovery plan Expected completion date Mametja Sekororo Limpopo 70 000 Delays The delay was as a result of funding shortfall Proposed Solution The project has been reallocated 70 million to ensure completion 2021 Moutse BWS 75 000 The project progress is very slow due to number of issues that affect the project. the issues are as follows: - The unresolved dispute between SDM(IA) and PSP - The expired contract period of DWS construction- Extension of time claim submitted but not yet approved The procurement delays experienced by DWS construction that impacted on the programme, i.e. procurement of goods and services, including the service provider for M&E. Proposed Intervention The department of water and sanitation has met with IA to try and resolve the issues with the implementing agent The department will fast track the issues of procurement in order to ensure that the project is completed

RBIG Unfinished Projects Project Name LOCATION 2019/20 FY Budget allocation (R‘000) Delays and recovery plan Expected completion date Ratlou BWS Phase 1 (Setlagole) North West 40 000 Delays The bulk water Supply project in Setlagole village and construction of reservoir at 99% completion, but currently no activity is happening on site due to termination of the pipeline contractor as result of non payment/ delays in payment Proposed Solution Adjudication of the new contractor is awaiting .Projected completion date to be revised soon as contractor appointed . 2019 Madibeng BWS Phase 2 All phases are 100 % completed ,however there is a challenge with energy supply to the plant to be in operation. Eskom requires R1.8 million for connection and installation of the big transformer. 2020

RBIG Unfinished Projects Project Name LOCATION 2019/20 FY Budget allocation (R‘000) Delays and recovery plan Expected completion date Meyerton WWTW Gauteng 56 749 Delays The project is around 89% complete. Incessant community protests poses a huge risk to the timely completion of project. Proposed Solution The department is having constant engagement with all relevant stakeholders to address community challenges 2020 Stellenbosch WWTW Western Cape Inability of the municipality to co-fund. The department has exhausted its co-funding allocation however the project has been stalled because the municipality has not honoured its co-funding allocation The municipality has indicated that, it will make funding available in the 2019/20 financial year

THE END