Presenter: Sohel Akhter, PMP, CCNA,ISMS

Slides:



Advertisements
Similar presentations
Connoizor Enabling Performance for Businesses through Software Website: Contact:
Advertisements

Connoizor Enabling Performance for Businesses through Software Website: Contact:
©2003 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third party, or used.
Earned Value Refresher By Robert Perrine, PMP Copyright reserved.
Budget Management. 57 Budget Management Budget Development Good scheduling skills and abilities Understanding of the project scope Well developed WBS.
 Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration.
1 Evaluating the Estimate at Completion (EAC) August 2013 NAVY CEVM.
Earned Value Management (EVM) Reference Card EVM Terminology ACWPActual Cost of Work Performed (Actual cost incurred for work accomplished during a given.
Monitoring and Control Earned Value Management (EVM)
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
Irwin/McGraw-Hill ©The McGraw-Hill Companies, 2000 Chapter 13 Progress and Performance Measurement and Evaluation.
Chapter 10: Monitoring and Controlling Change
Monitoring and Controlling
Project Monitoring and Control. Introduction Goal: ensuring that the project is on time and on budget and/or highlight any deviation from the plan Areas.
Project Management Process Project Description Team Mission/ Assignment Major Milestones Boundaries Team Identification Measures of Success Roles & Responsibilities.
Project Management 6e..
EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool
P ROJECT M ANAGEMENT, PMI A PPROACH (PMP) P ROJECT C OST M ANAGEMENT Sayed Ahmed BSc. Eng. in CSc. & Eng. (BUET, Bangladesh) MSc. in CSc. (University of.
Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.
This work is licensed under a Creative Commons Attribution 3.0 Unported LicenseCreative Commons Attribution 3.0 Unported License (CC-BY). Project Management.
GSET Technical Seminar Series Space Telescope Science Institute November 21, Earned Value Management: An Introduction and Short Tutorial Wayne Baggett.
Project Management Methodology Project monitoring and control.
Conducted By: Dr. Madhu Fernando, PMP, DBA, MEng. MGT PROJECT MANAGEMENT LESSON 5 AND 6: PROJECT PLANNING – TIME AND COST PLANNING AND MANAGEMENT.
Reporting Earned Value Metrics using Microsoft Office Project Server 2003
EARNED VALUE MANAGEMENT (EVM)
Earned Value Management System (EVMS). Given: –total budget of $100,000 –12 month effort –produce 20 units Status: –spent to date: $64,000 –time elapsed:
10/19/ :26 AM 1 Project Cost Control. 10/19/ :26 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
Earned Value SOS section Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much.
Project Management Part 6 Project Control. Part 6 - Project Control2 Topic Outline: Project Control Project control steps Measuring and monitoring system.
1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost.
Project Cost Con trol. 1.To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2.To forecast.
Mohawk Vehicle - MEGA HERZ ELEC & VEN - MOH-2 F C-0050 J:\CS40\Data Analysis\- Standard Analysis Package/Sample Standard Analysis Package.
Earned Value Management (EVM) Reference Card EVM Terminology ACWPActual Cost of Work Performed (Actual cost incurred for work accomplished during a given.
UU Master Class Earned Value 17 July Earned Value Contents What is Earned Value / Earned Value Analysis Why and where is it used A brief history.
EARNED VALUE MANAGEMENT (EVM) TUTORIALS
Introduction To Earned Value November 14, Definition Earned Value is a method for measuring project performance. It compares the amount of work.
Department of CS & Eng. MSSE Program, © Fissure 1 SOFTWARE PROJECT MANAGEMENT COURSE Executing, Monitoring and Controlling Session #7.
Earned Value Analysis Tracking Project Progress. Introduction | Components | Project Scenario | Values | Calculations | Forecasts | Summary l What Is.
Where Module 04 : Knowing Where the Project Is 1.
1 Earned value analysis Planned value (PV) or Budgeted cost of work scheduled (BCWS) – original estimate of the effort/cost to complete a task (compare.
PMP Study Guide Chapter 11: Controlling Work Results.
EARNED VALUE MANAGEMENT & ORACLE PRIMAVERA P6 TREY MILLER, MBA, PMP ORACLE PRIMAVERA P6 EPPM CERTIFIED IMPLEMENTATION SPECIALIST GLOBAL PROJECT MANAGEMENT,
Measuring Project Performance MS Project. Key Performance Indicators (KPIs) Quantifiable measurements – Reflect and measure achievements on critical success.
EVM – Do You Really Know What the Numbers Mean? Booz | Allen |Hamilton Seth Huckabee EVP, PMP, PMI-SP.
1 Understanding Earned Value in Under an Hour Breakout Session # A11 Name: Wayne Brantley, MS Ed, PMP, ITIL Senior Director of Professional Education.
EARNED VALUE  Earned Value Management Systems  Earned Value Analysis.
E ARNED V ALUE M ANAGEMENT ‘G OLD C ARD ’ Projected Slip ? Management Reserve Cost Variance Schedule Variance ACWP Cum BCWP Cum BCWS Cum $ EAC Time Now.
Schedule Control (Earned Value)
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
Earned Value Management
Measuring Progress HNC Project Management. Measuring Schedule Performance Break project tasks up into small work units. Work units that are too large.
Project Management Earned Value Management Demonstration
Earned Value Analysis by Miles M. Hamby, PhD Copyright©2014 Miles M
Project Monitoring
“PMP® Exam Prep” Earned Value Management
TOPIC-8B- PROJECT COST CONTROL
Budget Planning.
CHAPTER:7 Project Cost Management
Earned Value Management
Project Communication, Tracking, and Reporting
5. Cost resources & PLAN DURATION
Earned Value Management & Oracle Primavera P6
Progress and Performance Measurement and Evaluation
An Introduction to Earned Value Performance Measurement
Implementing EV in IT A Three Step Approach John Chapman Touchstone Ltd
Earned Value Measures Planned Value (PV) Earned Value (EV)
فرآيند كنترل پروژه.
5. Cost resources & PLAN DURATION
5. Project PLAN & cost estimation
Monitoring and Controlling
Presentation transcript:

Project Management Professionals Hot Topics & Challenges - Cost Management Presenter: Sohel Akhter, PMP, CCNA,ISMS PMP and Six Sigma instructor, Netcom Learning Adjunct Professor , MBA program, CUNY

Project Management Professionals Hot Topics & Challenges - Cost Management 1. PV 2. EV 3. AC Variance Formulas: 4. SV = EV – PV 5. CV = EV - AC Index Formulas: 6. SPI =EV/PV 7. CPI = EV/AC Forecasting Formulas: 8. BAC 9. EAC = BAC/CPI 10. ETC = EAC - AC 11. VAC = BAC - EAC 12. TCPI = (BAC – EV) / (BAC – AC) or (BAC – EV)/ (EAC – AC)

Project Management Professionals Hot Topics & Challenges - Cost Management Planned Value Earned Value Actual Cost Budgeted Cost of Work Scheduled Performed Actual New Name The rest of the presentation will use the new names, but the instructor should urge students to memorize both, since both old and new are currently used on the PMP exam. Old Name

Project Cost Management – Formula Acronym Term Formula Interpretation PV or BCWS Planned Value Budgeted Cost of Work Scheduled BAC x (Time Passed /Total Scheduled Time) BAC x Planned % Complete What is the estimated value of the work planned to be done? EV BCWP Earned Value Budgeted Cost of Work Performed BAC x (Work Completed /Total Work Required) BAC x Actual % Complete What is the estimated value of the work actually accomplished? AC ACWP Actual Cost Actual Cost of Work Performed What is the actual cost incurred for the work accomplished? SV Schedule Variance SV = EV- PV A comparison of amount of work performed during a given period of time to what was scheduled to be performed. Negative = behind schedule Neutral = on schedule Positive = ahead of schedule CV Cost Variance CV = EV – AC A comparison of the budgeted cost of work performed with actual cost. Negative= over budget Neutral = on budget Positive= under budget CPI Cost Performance Index CPI= EV/AC It measures the value of the work completed against actual cost. CPI<1=over budget CPI >1= under budget CPI= 1= on budget 𝐂𝐏𝐈 𝐜 Cumulative CPI 𝐂𝐏𝐈 𝐜 = 𝐄𝐕 𝐜 / 𝐀𝐂 𝐜 It represents the cumulative CPI of the project at the point the measurement is taken. SPI Schedule Performance Index SPI= EV/PV It measures the progress to date against the planned progress. SPI<1 = behind schedule SPI > 1= ahead of schedule SPI = 1 = on schedule 𝐒𝐏𝐈 𝐜 Cumulative SPI 𝐒𝐏𝐈 𝐜 = 𝐄𝐕 𝐜 / 𝐏𝐕 𝐜 It represents the cumulative SPI of the project at the point the measurement is taken. BAC Budget at Completion How much did we BUDGET for the TOTAL project effort? EAC Estimate at Completion If CPI is expected to be the same EAC= BAC/CPI   If current variances are thought to be atypical of the future EAC = AC+ (BAC-EV) If both CPI and SPI influence the remaining work EAC = AC+[ (BAC-EV)/ (CPI x SPI)] What do we currently expect the TOTAL project to cost? ETC Estimate to Complete ETC= EAC - AC From this point on, how much MORE do we expect it to cost to finish the project? VAC Variance at Completion VAC= BAC - EAC How much over or under budget do we expect to be at the end of the project? TCPI To Complete Performance Index If targeting the current plan TCPI= (BAC- EV)/ BAC – AC If targeting the current EAC TCPI= (BAC- EV)/ EAC – AC Performance that must be achieved in order to meet financial or schedule goals. TCPI >1 = harder to complete TCPI<1 = easier to complete Project Cost Management – Formula

Actual Amount Spent by week Three Planned Completion by week three Project Management Professionals Hot Topics & Challenges - Cost Management Project Planned End Date Planned Budget Actual Amount Spent by week Three Planned Completion by week three Actual Completion Corporate Training Project End of 4th week $10,500 for total project $2625 for each module $9000 3 out of 4 modules 2 out of 4 modules PV Planned Value BAC x ( Time Passed /Total Scheduled Time) = $10,500 x (3/4) = $10,500 x .75 = $7875 EV Earned Value BAC x (Work Completed /Total Work Required) = $10,500 x (2/4) = $10,500 x .5 = $5250

Project Management Professionals Hot Topics & Challenges - Cost Management You have a project to build a new fence. The fence is four sided as shown. Each side is to take one day to build and is budgeted for #1000 per side. The sides are planned to be completed one after another. Today is the end of day three. Using the project status chart below calculate the formulas. Activity Status End of day 3 Side 1 Complete, Spent $1000 Side 2 Complete, Spent $1200 Side 3 50% done, Spent $600 Side 4 Net yet started PV EV AC BAC CV 3000 2500 2800 4000 -300 CPI SV SPI EAC ETC VAC TCPI .893 -500 .833 4479 1679 -479 1.25

Project Management Professionals Hot Topics & Challenges- Cost Management You have a project to build a new fence. The fence is four sided as shown. Each side is to take one day to build and is budgeted for $1000 per side. The sides are planned to be completed one after another. Today is the end of day three. In this case, assume that the sides have a finish-to-finish relationship instead of a finish-to-start relationship. Using the project status chart below calculate the formulas. What is Answer PV EV AC BAC CV CPI SV SPI EAC ETC VAC TCPI 3000 Activity Status End of day 3 Side 1 Complete, Spent $1000 Side 2 Complete, Spent $900 Side 3 50% done, Spent $1000 Side 4 75% done, Spent $300 3250 3200 4000 50 1.016 250 1.083 3937 Key S= Actual Start, F = Actual Finish, PS = Planned Start, PF = Planned Finish 737 63 .937

Project Management Professionals Hot Topics & Challenges - Cost Management Your project is running well. In the latest earned value report, you see the CPI=1.2, the SPI= 0.8, the PV= $600,000 and the SV = -$120,000. You can’t find the CV in the report, so you calculate it based on the info given. What is the CV? Key S= Actual Start, F = Actual Finish, PS = Planned Start, PF = Planned Finish