Undulator Assembly and Installation Planning Rodd Pope, SLAC
By Scott Doran, ANL UNDULATOR CELL ASSEMBLY NEXT CELL UNDULATOR SHOWN FOR CLARITY
By Scott Doran, ANL UNDULATOR CELL ASSEMBLY NEXT CELL UNDULATOR SHOWN FOR CLARITY
Collaboration Roles and Responsibilities (abridged) ANL – Stephen Milton Geoff Pile Design the System and Sub-assemblies minus WPM/HLS Supply Designed Sub-assemblies Provide Expertise SLAC Metrology – Robert Ruland Design and Supply WPM/HLS System Undulator Tuning & Quadrupole Measurement Develop and Test Fiducialization Procedures SLAC Assembly & Installation – Ben Poling Girder Assembly System Installation Material Handling and Storage
Assembly, Installation, and Maintenance Group Undulator Assembly, Installation and Maintenance Group (U-AIM) Supervisor – Ben Poling Principal Technician – Ed Akerstrom Principal Technician – Nick Horton Material Handling, Assembly Preparation, Installation Planning Three Engineering Assistants Michelle Chan, William Rowan, Austin Schuh Summer Support of Design, Engineering, Production Activities
Assembly – Installation Outline Receive Assemblies, Sub-assemblies, and Kits Inspect, Modify, Store Girder Rough Assembly Girder Precision Assembly Anchor Installation (Davis-Bacon) Pedestal Installation (Davis-Bacon) Girder Installation (Davis-Bacon) and Mover Startup Vacuum System Completion WPM/HLS Installation and Startup Undulator Magnet Installation
Assembly, Install, & Storage Space Undulator Tunnel B081 – MMF Tuning/Fiducialization - B033 GLAST: Limited space, other groups vying for space - B006 SSRL/ILC: More limited space than B033, requires ~$30k to cleanout - B750: Much space, dirtiest, access may be limited by construction B750 – Storage/Assembly
Undulator System Girder Assembly Precise/Vacuum Assembly performed in a control environment Field Installation
SLAC Magnetic Measurement Facility Wolf, Zachary, LCLS Management Presentation, April 11, 2006, Slide 3 Floor plan divided into three functional areas Magnetic Measurements (± 0.1º C) Fiducialization and Assembly (± 1º C) Storage (± 2.5º C) Assembly Area Storage and Queuing LCLS-TN-04-1
Schedule, Summary
Component Delivery Schedule – 7/10/07 Actual Plan
Component Deliveries by 1/10/2007 (+6 Months from Now)
Next Six Months WPM and HLS Hardware Delivered Undulators RFI Component Deliveries Minus RF BPMs and Vacuum Chambers Cable Plant Design Review Complete Procurements Placed for Materials and Labor Early Occupancy of Undulator Hall Pedestal Installation Contract Let Girder Installation Contract Out for Bid
End of Presentation
Component Delivery Schedule – 2/10/07
By Scott Doran, ANL SHORT BREAK
SHORT BREAK CROSS SECTIONS By Scott Doran, ANL SHORT BREAK CROSS SECTIONS
By Scott Doran, ANL LONG BREAK
LONG BREAK CROSS SECTIONS By Scott Doran, ANL LONG BREAK CROSS SECTIONS
Component Delivery Schedule
Girder Assembly Flow ANL Supplied ANL Supplied - Insert isometric view of undulator system - Insert table of components that make-up the undulator system assembly work