CSS Consequential Programme Change Assurance March, 2019

Slides:



Advertisements
Similar presentations
Program Management Office (PMO) Design
Advertisements

Paramedic evidence-based education project (PEEP)
Project Management Framework May 2010 Ciaran Whyte Risk Administrator Planning & Strategic Projects Unit.
Peru c o n s u l t i n g Peru Programme Assurance Method.
Senior Stakeholder Forum 04/02/2014. Agenda UK-Link Programme Update –Including Data Cleansing Update Nexus Modification Update Faster Switching EU Reform.
 A project is “a unique endeavor to produce a set of deliverables within clearly specified time, cost and quality constraints”
UK Link Programme Dashboard Report Change Overview Board: 13/05/2014 Critical HLD activities complete enabling entry into Detailed Design Detailed Design.
UK Link Programme Update to PNUNC June 17 th 2013.
X Project Highlight Report – (Date) Achievements  Key high level outputs delivered by the project this month. Communications Key high level communications.
PNISG Update June Xoserve’s UKLP Assessment Principles 1.Maintain current delivery plans where possible and appropriate e.g. don’t just push all.
Cutover & Implementation Aggregated Programme RAG
Implementing Program Management Standards at Duke Energy.
Healthier Together Joint Committee Wednesday 15 th June 2016.
DSC Change Committee UK Link Future Releases Proposed Approach
Description of Revision
Phase 2 Tollgate Review Discussion Template
Phase 3 Tollgate Review Discussion Template
Project Roles and Responsibilities
Phase 2 Tollgate Review Discussion Template
Phase 1 Tollgate Review Discussion Template
Guidance notes for Project Manager
Change Assurance Dashboard
SmartMeterTM Steering Committee Update – March 2013
TransformUs Programme
MIS Development – DSC Change Management Committee update
Phase 2 Tollgate Review Discussion Template
Recommendations for using this ‘framework’ template
Cutover & Implementation Aggregated Programme RAG
DSC ChMC CSS update 7th November 2018
Change Assurance Update
Overall Project RAG Status
Xoserve IX Refresh Customer Update 12/02/2019.
Change Assurance Dashboard
Release 3 Update November 2018.
CSS Update for CoMC 19th September 2018
DSC Change Committee Summary – 11th July
DSC ChMC CSS update 11th December 2018
Xoserve IX Refresh Customer Update 03/01/2019.
Release 3 Plan Options Analysis
UNC Modification 0531 Provision of Industry Testing System
Change Assurance Findings for UK Link Release 3 Health-check 2
XRN4361 – UK Link Release 2 - Delivery
Change Proposals Capture to Delivery
Portfolio, Programme and Project
Release 3 Update 13th February 2019.
SmartMeterTM Steering Committee Update – November 2012
DSC Governance Sub Group Recommendations
Ofgem Switching Programme: Central Switching Service consequential change update 9th May 2018.
KVI Change Management Survey Feedback
DSC ChMC CSS Consequential Update 13th March 2019
DSC Change Committee Summary – 13th March ‘19
Change Management Committee – Retail & Networks Update
XRN4361 – UK Link Release 2 Project Status Update
TransformUs Programme
Ofgem Switching Programme: Central Switching Service consequential update 16th May 2018.
DSC ChMC CSS update 09th January 2019
DSC ChMC CSS update 12th September 2018
Holistic Release Criteria
Xoserve IX Refresh Customer Update 05/03/2019.
Change Assurance Report March 2019
4340 – UK Link Future Release 1.1
Project Progress Summary - Week 18
DSC Contract Management Committee Meeting
DSG Governance Group Recommendations.
Data Office POAP July/August 2019
KEC Dhapakhel Lalitpur
Street Manager Communications approach
World-Changing Glasgow Transformation Programme Board Summary
DSC ChMC Switching Programme Update 9th October 2019
SwitchStream: Product update
Presentation transcript:

CSS Consequential Programme Change Assurance March, 2019 Ahead of embedded assurance commencement, Xoserve’s Change Assurance team conducted a Healthcheck with two objectives: Assess readiness for Stage Gate B (start-up) – no risk was identified and the Gate was passed successfully With CSS C approaching Detailed Design, look beyond Gate B to overall Programme health Since agreeing the Healthcheck findings, the CSS C Programme has addressed recommendations made, 4 findings have been closed, and plan-aligned completion dates agreed for all others. No action is therefore requested from the change Management Committee and the following summary dashboard is provided for information.

CSS C Programme Early Assurance Summary Dashboard Assurance was performed ahead of Stage Gate B (Startup), against which only minor gaps were noted, and Gate passed. As the Programme is transitioning from High-Level to Detailed design, the assurance also looked beyond Gate B to the wider health of CSS C, as reflected in the below findings, which have been updated to reflect progress since the Healthcheck. Area Date Change Project RAYG by Area CA1 – CA4 Summary Programme Delivery March 2019 CSS Consequential Programme Change Assurance Overall Business Case Team Sponsorship Plan Governance Customer Scope and Solution Other CA1 CA2 CA3 CA4 A significant number of roles remain open in the Programme org structure. Although a resource model is in place and recruitment is in progress, there is a continuing risk of resources not being available when required, and of contractor engagement for urgently-required roles, in place of planned permanent resource. The Programme’s governance structure alongside existing Platform and functional Xoserve governance, needs to be consolidated and lean, to avoid duplication and unclear escalation and decision-making routes. The decision to bring design forward against a backdrop of requirement and solution uncertainty places risk on the HLD to DD transition, the mitigation and control of which needs to be clear in phase governance. There is a possibility of significant external scope change well into our Detailed Design phase and the Programme will need an effective Change Control process. Engagement of TCS for Detailed Design without significant prior Xoserve solution knowledge gives risk to Detailed Design and may impact response to scope change and delivery. The Programme needed to make clear how it will control the gap between Stage Gate governance and the actual lifecycle phase, which are not due to align until Gate C, end of design. This has been addressed and the finding closed. Update 09/04/19 At Healthcheck 2 2 10 9 15 12 Info Security Business Readiness Suppliers Finances Pocurement Contract Management