Richland Creek Water Supply Program Program Update

Slides:



Advertisements
Similar presentations
Construction Management. Players Owner – owns project upon completion of construction –Private – owner owns land and pays for construction of facility.
Advertisements

Floyd County Board of Commissioners Special Town Hall Meeting Topic: Update on status of Georgetown WWTP.
1 Wastewater Capital Improvement Program (CIP) Large Users Meeting March 15, 2010.
1 Purpose  Summarize Monday’s workshop  Update on the Radio System – confirm staff’s recommendation  Jail Expansion – discussion/direction  Discussion.
Alderman Road Residences Phase II Design Build. Extensive master planning preceded this phase 2003 – Dagit Saylor Master Plan Hanbury Evans Update.
Company LOGO C o n s t r u c t i o n R e p o r t P r o f e s s i o n a l C o n s t r u c t i o n M a n a g e m e n t 2006 Prepared by:
ESTIMATING By Laith Jacob.
2013 JOB ORDER CONTRACTING CONTRACT MANAGEMENT DEPARTMENT 8/3/2015 CONTRACT KICKOFF Solicitation CLMB312 January 3, 2013.
Project Delivery Overview June 2015 Final PD Training FMD WUSM 6/15/15 1.
Design Build, Job Contracting, or Construction Manager at Risk In early 2000 the legislators added an alternate way to accelerate construction project.
Bridge Building Timelines Presented by The Richland County Engineers Office Thomas E. Beck, PE, PS 77 North Mulberry Street Mansfield, Ohio Jan.
Water System Planning Study
Commissioning of Fire Protection and Life Safety Systems Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
UESC Project Implementation Construction & Installation ä Issue TO for construction ä The pre-construction meeting ä Review/accept final construction package.
Water Supply Planning Initiative State Water Commission November 22, 2004.
Washington’s Water Use Efficiency Rule May Require Increased Coordination for Many Utilities Dan Sander, P.E. Senior Engineer.
1 Management Report on Bradley West Project BOAC Meeting October 5, 2009.
Calistoga Joint Unified School District Measure “A” Citizens’ Oversight Committee Meeting October 27, 2011.
City of Palm Coast, Florida City Council Meeting October 2, 2012.
Project Goals o Meet Strategic Action Plan Performance Measure Strategy 4.1.1: Utilize nature’s water supply resources effectively for water supply o.
You passed the Bond or secured some funds What do we do now? 2014.
UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.
Former DuPont Barksdale Works Project Update July 14, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center.
Richland Creek Water Supply Program Contract for WTP and Pump Stations CMAR Services and Program Update Paulding County, Georgia Board of Commission Work.
Update on RCR Permitting
Time is money. Use yours wisely. Bryan McCabe, PE | Pender County Utilities J. Ray Cox, PE | Highfill Infrastructure Engineering.
Update on the Richland Creek Reservoir and Water Supply Program Paulding County, Georgia Board of Commissioners Workshop Briefing October 13, 2015.
Richland Creek Water Supply Program Contract for Reservoir, Pump Stations, and WTP Final Design Services Paulding County, Georgia Water and Sewer Advisory.
Measure N Modernization IMPLEMENTATION PROCESS Planning, Bidding, Construction, and Occupancy.
1 EASTERN MUNICIPAL WATER DISTRICT Temecula Valley Recycled Water Pipeline Joe Mouawad Sr. Director of Engineering September 2, 2015.
Wastewater Treatment Plant No. 2 Construction Contract City Council Workshop February 9, 2016.
Richland Creek Water Supply Program Update and Design-Build Contract for 48” Raw Water Pipeline Paulding County, Georgia Board of Commissioners Workshop.
Richland Creek Water Supply Program Status Update Paulding County, Georgia Board of Commissioners Work Session January 26, 2016.
Alpine County Government Center Board of Supervisors Presentation October 2, 2012.
Richland Creek Water Supply Program Update Paulding County, Georgia Board of Commissioners Work Session March 08, 2016.
UTILITY PARTNERSHIP CITY OF STOCKTON & OMI / THAMES WATER SERVICE CONTRACT.
USAID Afghanistan Engineering Support Program (ESP) Pre-Bid Meeting July 14, 2015.
Big Cypress Basin Capital Project Update Jeffrey Kivett, P.E., Director Operations, Engineering and Construction Division Jeffrey Kivett, P.E., Director.
Update on the Richland Creek Reservoir and Water Supply Program Paulding County, Georgia Board of Commissioners Workshop Briefing May 26, 2015.
Southeast Rail Extension FasTracks Monitoring Committee July 14, 2015.
Richland Creek Water Supply Program Bid Recommendations Paulding County, Georgia Board of Commissioners Work Session February 23, 2016.
STOCKTON DELTA WATER SUPPLY PROJECT (DWSP) Final Environmental Impact Report (EIR) Certification Hearing November 8, 2005 Mark J. Madison, Director Municipal.
Pier Partial GMP Proposal for Marine Structural June 1, 2017
Process and customizations
Richland Creek Water Supply Program Briefing
Subtitle Statement of Capabilities.
Kings Bluff Raw Water System Parallel Raw Water Main Project
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
Case Road Sewer Joe Mouawad, P.E. October 27, 2016.
Capital Facilities Program Update San Rafael City Schools
Wastewater Treatment Plant Biological Nutrient Removal & Digester Project - Package 2 Construction Contract City Council Meeting – August 1, 2017 Package.
FY 2012 Status Report on the North Mainland (Ormond Crossings CRA)
Chesapeake Bay Program Budget & Finance Workgroup Meeting
Valley & Third Streets Redevelopment
Paulding County, Georgia
Designers’ Manual Overview and Chapter Contents
The Paulding County Richland Creek Reservoir (RCR) and Water Supply Program Speaker: Mark.
AX7665D82 Areawide Total Maximum Daily Load (TMDL) Design-Build
MARKETING, PURCHASING AND PRODUCTION (7 - 9%)
PROJECT DELIVERY METHODS
June 14, 2018.
SUSTAINABLE ENERGY INDUSTRY DEVELOPMENT PROJECT (SEIDP)
Request by Councilmember Madison to reagendize the Desiderio Park Design for reconsideration September 17, 2018 Item 17.
Brackish Water Desalination Project
Delta Water Supply Project
Cost Containment Working Group Board Update
Q2 Updates on 2019 Board Priorities
Q2 Updates on 2019 Board Priorities
TOTAL COST CONTROL ON CONSTRUCTION PROJECTS
Presentation transcript:

Richland Creek Water Supply Program Program Update Paulding County, Georgia Richland Creek Water Supply Program Program Update Paulding County BOC Meeting June 14, 2016 Speaker: Kelly

Update on 61 Entrance Road and Timber Harvest WTP area harvest is complete Construction Erosion control installed Entrance road under construction Initial grading at WTP site underway Intersection Improvements along Highway 61 initiating GDOT Permit received Stream crossing Permit received Speaker: Kelly

Update on Richland Creek Reservoir Contractor Procurement Six prequalified contractors Bidding among prequalified contractors ongoing (June 24 bids due) Corps of Engineers Preconstruction Conference Held meeting with USACE and USFWS on 06/08/16 Construction Timber harvest for Dam area will commence on 06/15/16 Selected Dam contractor will begin construction in late August / early September Speaker: Kelly

Update on WTPs and Pump Stations Procurement PC has competitively bid all components GMP GMP has been developed and submitted (within program budget) Being presented to BOC today Construction Construction will begin in late August / early September Program Manager Speaker: Kelly

Update on Raw Water Pipeline Design Met with Bartow County to provide update Beginning process of easement acquisition Design is at 60% Construction Construction will begin in Late 2016 and will be complete in late 2017 / early 2018. Speaker: Kelly

Update on Finished Water Pipeline and BPS Design Issued NTP to Atkins Held design kickoff meeting Design will be complete by January Construction Contractor Procurement in early 2017 Construction will begin in March of 2017 and be complete in March 2019 Speaker: Kelly

Program Cost Summary Update Project Element Original Cost Estimate Currently Under Contract 06/09/16 Recommendation Remaining Estimate Revised Cost Estimate Reservoir $ 70,300,000 $ 16,808,000 $ 1,200,000 $ 52,313,000 $ 70,321,000 WTPs and Pump Stations $ 98,800,000 $ 12,221,000 $ 88,295,000 $ 100,000 $ 100,616,000 Raw Water Pipeline $ 9,400,000 $ 9,000,000 $ 400,000 Finished Water Pipeline and BPS $ 36,500,000 $ 2,304,000 $ 1,400,000 $ 29,109,000 $ 32,813,000 Contingency $ 1,850,000 Total $ 215,000,000 $40,333,000 $ 90,895,000 $ 83,711,000

Update on Public Outreach Artwork and Mascot Competition were a success - approximately 40 submissions Winning artwork is on display at the customer service office and RCRWater.com Winning Mascot – Becky the Beaver Speaker: Kelly

Speaker: Kelly

New Business Item 3 –WTP GMP GMP for the construction of the RCR Water Treatment Plant, Reservoir Intake and Pump Station, and Etowah River Intake and Pump Station Speaker: Kelly

New Business Item 3 –WTP GMP PC Construction Inc was brought placed under contract in late 2014 for providing Construction Manager at Risk (CMAR) services for the Water Treatment Plant, Reservoir Pump Station, and the Etowah River Pump Station Throughout Design they have provided feedback on Construction Cost Construction Schedule Constructability Review Value Engineering / Alternative Concepts Speaker: Kelly

New Business Item 3 –WTP GMP CMAR approach has been successful in driving down cost throughout the design process. Design Status PC Cost Estimate 30% Design Estimate $ 98,592,027 60% Design Estimate $ 89,346,725 100% Design GMP $ 86,795,045 Speaker: Kelly

New Business Item 3 –WTP GMP 100% of the project has been competitively bid per GEFA Speaker: Kelly

New Business Item 3 –WTP GMP Next step under current contract is to award the “Guaranteed Maximum Price” GMP is based on 100% design so contingency level is low GMP does include approximately $741,000 of Contingency and allowance items under the control of Paulding County. Total GMP is $ 86,795,045 Slightly higher (2%) than original element budget due to higher than anticipated electrical contractor cost (occurring throughout the industry). However cost is within the overall program budget contingency. Speaker: Kelly

Speaker: Kelly

New Business Item 4 – Program Management Funding Authorization 2 Brown and Caldwell was awarded the Program Management Contract in October of 2014. 4 Year Contract – Initial Funding Authorization was planned to be for the first 12 month period with subsequent funding authorizations to come before the BOC for approval. Efficient management allowed the initial funding to last for 20 months (8 months longer than originally planned). All work is authorized on a Task Order Basis with specific scope and budget authorized by the County for each activity. Speaker: Kelly

New Business Item 4 – Program Management Funding Authorization 2 Services Provided During Initial Authorization Procurement Assistance - PC Construction as CMAR Contractor Arcadis for Final Design and Construction Management of Dam and WTP Garney / Croy Design Build Team for Raw Water Pipeline Atkins for Finished Water Pipeline Design GA Power for Power Service for the Etowah River Pump Station Greystone Power for Power Service for the WTP and Reservoir Pump Station Brad Cole for the Highway 61 Entrance and Initial grading contract Reece Logging for the Timber Harvesting Contract Bidding of subcontractors for WTP and Pump Station Project Bidding assistance with Reservoir Contract Contract Management- Management of the various contracts and regular coordination and meetings with teams Speaker: Kelly

New Business Item 4 – Program Management Funding Authorization 2 Services Provided During Initial Authorization(cont’d) Public Outreach and Communication Development and maintenance of the RCRWater.com website Community Outreach and numerous briefings to civic organizations, cities, and neighboring jurisdictions Outreach to schools (science curriculum, art contest) Regular briefing to WSAB and County Commission on program progress Design Review and Project Coordination Provided design review and coordination of WTP, pump stations, and pipeline contracts Coordinated design to accommodate owners preferences Coordination with distribution system hydraulic modeling as part of master planning process SCADA system coordination Speaker: Kelly

New Business Item 4 – Program Management Funding Authorization 2 Services Provided During Initial Authorization(cont’d) Financial Assistance Assisted is establishing State Direct Investment through GEFA Coordinated with GEFA on all loan requirements Preparation and submission of loan draws Development of financial model and plan for program Assistance in setting rates Permitting Assistance Assistance with 404 Permitting and compliance with Permit Bat Assessment Required biological monitoring Historical data analysis and reporting on temperature Coordinated installation of USGS Monitoring Station Speaker: Kelly

New Business Item 4 – Program Management Funding Authorization 2 Anticipated Activities Contract administration for all program contracts Owners agent for the WTP and Reservoir Construction (full time on the site throughout construction) Permit compliance assistance and reporting Program document control Inspection services for the raw water pipeline, finished water pipeline, and Macland Tank projects Bonding assistance including engineering and financial analysis to support bond issue Easement acquisition assistance Organizational assistance – organizational planning, staff training, organizational tools (asset management, cmms system development) Public outreach during construction Speaker: Kelly

Speaker: Kelly