Vacuum Controls Stephen Schuh Tom Porter 25 October 2006

Slides:



Advertisements
Similar presentations
SESAME Radiation Safety and PSS Phase I : Microtron + Booster Morteza Mansouri on behalf of Safety group TAC SESAME TAC 2013 : Morteza Mansouri.
Advertisements

X. X September Mo Tu We Th Fr Sa Su
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.
Arturo Alarcon Undulator Controls Module Status 11/12/2008 SLAC National Accelerator Laboratory 1 Undulator Controls Module Status.
Hamid Shoaee Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory Controls Department LCLS Maintenance.
Stephen Schuh Vacuum Controls Final Design 6 April 2006 Injector Vacuum Controls Hardware Final Design Review 6 April 2006.
LCLS-II Linac LLRF Control System – L1, BC1 Zheqiao Geng Final Design Review May 7, 2012.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
Magnet Controls Group LCLS Magnet Controls August 16, Status of the LCLS Magnet PS Controls Needed for First Injection.
LBT Q Engineering Review DYB. 26-Oct-2007LBT Q Engineering Review Highlights (Q3/2007) Currently in Commissioning Phase Currently in Commissioning.
Vacuum Controls Status MACS week December 2010 PP a-JWA-VacControlStatus.ppt Joachim Wallner 1.
Stephen Schuh Vacuum Controls SCR and 16 November 2005 Vacuum Controls System Concept Review and Preliminary Design Review.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Issues in Accelerator Control Bob Dalesio, December 23, 2002.
September 2008 SundayMondayTuesdayWednesdayThursdayFridaySaturday
DATE POWER 2 INCOME JANUARY 100member X 25.00P2, FEBRUARY 200member X 25.00P5, MARCH 400member X 25.00P10, APRIL 800member.
18th June 2003 Diamond Vacuum System Steve Singleton 18th June 2003.
Status of Vacuum Control System MACS week June 2011 PP a-JWA-VacControlStatus.ppt Joachim Wallner 1.
Managed by UT-Battelle for the Department of Energy SCL Vacuum Control System Upgrade Derrick Williams
2011 Calendar Important Dates/Events/Homework. SunSatFriThursWedTuesMon January
News from LAL on Vacuum System Racks for cryotraps: call for tender done provider selected purchase of electro-tech components in progress prototype expected.
Hamid Shoaee Control LCLS ARR Oct 31, LCLS Accelerator Readiness Review Control System for Injector Commissioning.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
April 2005OLAV Workshop Diamond Vacuum Controls Hugo S Shiers.
26-Feb-16S.Movchan Straw manufacturing and QC1 Dubna NA62 straw tracker assembly area (milestone) halls plans conclusion Presented by S.Movchan.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
Krzysztof Radwan, PJAS, TE/VSC/ICM Interlocks, Controls and Monitoring Section HIE-ISOLDE Vacuum Controls INSTALLATION.
July 2007 SundayMondayTuesdayWednesdayThursdayFridaySaturday
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
LEDA Vacuum Interlocks Bob Dalesio. Outline Leda vacuum system – displays and interfaces PLC Interlocks as presented to the operator EPICS interlock to.
01/09/ KTAG 5/8 sectors equipped DCS system in pogress DAQ commissioning in progress Test pressure scan this week (t.b.c) 01/09/20142.
Cryoplant Controls Installation
RF Systems and Controls for the LERF CM Tests
SESAME Control System Status
Cryomodule test stand at ESS site
LEDA Vacuum Interlocks
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
CBETA Technical Review
Process Control System Requirements
Status of Vacuum Control System
352MHz Klystron Control for the 3MeV Linac test stand
Timing and Event System S. Allison, M. Browne, B. Dalesio, J
SPS CC: Final plan for interlocking of crab cavities in SPS
XFEL Vacuum System Commissioning
LLRF Controls Outline Requirements External Interfaces Schedule Design
WP Coordinaten XFEL RF Operation
ACS news Circulator TCU: control tests in progress All cavity racks
LLRF and Beam-based Longitudinal Feedback Readiness
X-ray Pump-Probe Instrument
13-block rotation schedule
Undulator Vacuum System
Testing Plan and Status
Installation of Photon Beam Transport to FEH
Injector / Linac Installation Current Status
Undulator Vacuum System
DOE Review 11 May 2005 Stephen A. Lewis
LCLS Undulator System Production Management
2007 Downtime Controls Installation
LCLS Personnel Protection System and Beam Containment System
DOE Review 7-9 February, 2006 Steve Lewis
Vacuum Control System for Monolith Vacuum
LCLS Control System Personnel Linac & BC2 Controls progress
LCLS e- Beams Systems Manager
Control System Overview Hamid Shoaee LCLS Control System Manager
2015 January February March April May June July August September
Presentation transcript:

Vacuum Controls Stephen Schuh Tom Porter 25 October 2006

Outline Requirements Block Diagram External Interfaces Design Maturity Hardware Status Software Status Schedule Testing Program

Requirements Use existing controls for linac vacuum hardware Remote control and status in EPICS for all new hardware Local control and status for all new hardware Interlock gate valves with gauges Notify MPS when a gate valve is not open Shut off klystron modulators when waveguide pressure exceeds a threshold Close all valves in a PPS region if that region is set to controlled or permitted access

Block Diagram

External Interfaces Valve status to MPS: Shut off beam when valve is not open (MPS ICD, Vacuum Controls ESD) Waveguide vacuum status to modulator: Shut off modulator when WG vacuum is bad (Vacuum Controls ESD) Access state from PPS: Close valves when in controlled or permitted access

Design Maturity Vacuum safety review – September 2005 Safety review of all vacuum components Audience: Vacuum experts and safety experts from several SLAC departments Internal design review – November 2005 Early review of vacuum controls plan Audience: SLAC controls department Vacuum Controls Requirements document – March 2006 Final design review – April 2006 Review of vacuum system controls hardware Audience: Control system experts and vacuum experts from SLAC

Hardware Status Date Needed: January 2007 Progress to date: Assembled test stand: PLC, gauge controller, pump controller, IOC Installed all long haul cables Procurement and bench testing of COTS vacuum controllers finished Most equipment installed in racks in Sector 20 (exceptions: PLC crates, valve control panels) Intra-rack wiring complete Remaining work: Make and install vacuum pigtail cables (in progress) Install PLC crates in Sector 20 (when programming complete) Fabricate valve control panels (in progress); install in Sector 20 Install wiring to provide vacuum interlocks to RF system

Software Status Date Needed: January 2007 Progress to date: Software requirements determined (Vacuum Controls ESD) EPICS device support mostly complete: EPICS ↔ PLC: done (using ether-ip from SNS) EPICS ↔ Vacuum Controllers: nearly done (using streamdevice from SLS) Test stand PLC programming in progress Test stand IOC development in progress Remaining work: PLC programming (in progress) EPICS databases and EDM screens (in progress) System testing (formal test plan to be written)

Schedule

Testing Program Vacuum equipment bench testing mostly done Pump controller load tests Gauge controller tests Valve control panels will be tested when delivered Intra-rack wiring mostly tested Most intra-rack wiring was tested before the racks were sent to Sector 20 Remaining wiring will be tested after PLC crates are installed System testing to be done in December All PLC interlocks will be tested after PLC programming is finished Detailed testing procedures not yet developed End to end testing in January-February