Saturday 06/11 Triplet R8 tripped during ramp for collision setup.

Slides:



Advertisements
Similar presentations
● Morning: – Squeeze and collide. – Smooth, orbit rather well under control (max. excursion ~ 0.2 mm at TCT, roughly sigma). Orbit evolution at the.
Advertisements

● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Week 13: R. Assmann, J. Wenninger
LHC Status Fri Morning 3-June
Ion Commissioning: Thursday & Friday
Wednesday
Wednesday 8.9 External crossing angles:
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Wednesday September 14th
Friday 30th September 06:00 Operator dump fill #2171, int. lumi about 75 pb-1 Previous operator dump from physics was on 14 September ! 07:00 Start of.
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Summary week 36 Coordination by B. Holzer & J. Wenninger
Overview LHC Operation Week 47
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
LHC Morning Meeting - G. Arduini
Saturday 12:00 Fill 1992 in stable beams.
Machine availability reaching well over 80%
Tuesday TOTEM and transverse loss map (1) OK
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
LHC Morning Meeting - G. Arduini
Alice solenoid – orbit distortion
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
LHC commissioning Week 38
Lost at 12:05 to power converter (RTQX2.R1) problem
Mike Lamont, Jorg Wenninger
Week 36 plan Todo’s: And also: 12+b injection.
LHC Operations overview Week 28 – Getting back
Week 35 – Technical Stop and Restart
Summary of Week 26 Main aims: G. Arduini, B. Holzer, M. Lamont
Monday Morning – recovery from cryo.
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Friday morning 10:30 Optics measurements and corrections.
Saturday – Morning 7:36 beams dumped
LHC Morning Meeting - G. Arduini
Tuesday 9th November 10:02 Fill beams dumped
Friday Morning 7:30 injection for fill 2908
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
Yesterday morning Held 1647 for a while – SPS kicker problem
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Saturday 7th May Sat – Sun night
Sunday/Monday & :30 Stable beams. Fill #1851.
Monday 24 October hours of 25ns MD
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
Tuesday morning 08:30-09:00 Squeeze with probe.
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Saturday Nov Stop proton operation. Switch back to ions
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Thursday 26th July 13:21 Fill 2880 beam dumped
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Monday 11th June 08:10 Beam dumped in the ramp by OP. OFB did not start its function and kept the injection orbit. 08:50 Switch LHCb polarity to negative.
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Saturday :42 stable beams fill 3541
Monday :15 fill 3523 dumped by BPMs IP6
Plan for 1 m b* J. Uythoven & J. Wenninger
Polarity inversion 07:00 ALICE solenoid and dipole polarity switched to positive External Crossing angle polarity unchanged at injection/ramp & squeeze.
Monday Fill 1803 into stable beams at 9:30. Dump at 19:45.
Saturday 12 March Morning: problem on RSD1.A12B2 – flow rate problem on the cooling water for the converter. 14:00: Loss map -500 Hz (positive energy offset)
LHC Morning Meeting - G. Arduini
Tuesday In the morning test cycle with probe for Q’ measurement.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Tuesday – Morning and Evening
LHC Morning Meeting - G. Arduini
Another Immortal Fill….
Wednesday morning / afternoon
Saturday Luminosity production 1380 bunches
Tuesday
HI2011 Commissioning Status
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Saturday 06/11 Triplet R8 tripped during ramp for collision setup. Lost status of access door (YCPS04=Uj56) and patrol in Pt5. Patrol found the door (slightly ~ 1 cm) open, but contacts were such that LASS saw it closed – until the patrol was lost. Access to Pt8 to fix triplet PC RQTX.R8. Triplet finally back in operation around 18:00. Pre-cycle. Beam delayed by MKI problem and water problem in TT2. Beam in at 21:30. BPM interlock test. Ramp & squeeze. 05/11/2010 LHC 8:30 meeting

Saturday lat evening 00:30: Colliding in all IPs with TCTs at 25 sigma. With proton settings for Xing and lumi scan knobs (ALICE separation to 0). 05/11/2010 LHC 8:30 meeting

Saturday PM – collision setup Xing in ATLAS and CMS to 0. Xing in ALICE to 0 effective Xing angle. External angle -140 urad. Optimized orbit and beam overlap. 05/11/2010 LHC 8:30 meeting

Saturday night 01:45 TCT collimator setup. 04:02 Beam dumped during TCT movement in Pt2. Triggered while moving in TCTVB.4L2 between 15-20 sigma. 5 TCTs setup in B1, 3 TCTs set up in B2 All TCTH B1, 3 TCTH B2 (miss Pt2), TCTVA.4L5.B1 QPS OK issues on RB.56. Two issues on the same circuit: heater PS. Access finishing soon… Intensity issue on the ion source (factor 2 weaker than in the last few days). Investigating… 05/11/2010 LHC 8:30 meeting

Dump 05/11/2010 LHC 8:30 meeting

Bunch lengthening 05/11/2010 LHC 8:30 meeting

Emittance increase seen by BSRT – V plane 05/11/2010 LHC 8:30 meeting

Collimator loss map end of squeeze (b* 3.5 m) Loss map analysis (R. Assmann): Leakage IR7 to: DS: 1-2% Arc: 0.1-0.3% IR3: up to 30% (H plane) Exp. IRs: clean 05/11/2010 LHC 8:30 meeting

Plan Sunday AM Collimator setup to finish Sunday PM & Night Loss maps (betatron & off-momentum) Asynch dump test Stable beams 2x2 Monday++ 4b cycle and injection Stable beams 17x17, 128x128 etc 05/11/2010 LHC 8:30 meeting