Thursday - setup 10:00 Starting pre-cycle. 11:30 Injection.

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

Lot’s of time lost due to cryo problem in IR8. Major impact, therefore review of MD program… Start discussion here, please let us know your input. Will.
LHC 30 th and 31 st July :10 Finish scrubbing fill 25 ns trains by operator dump. –No XPOC data … 08:40 Inject for another scrubbing fill 09:09.
LHC Scrubbing Runs Overview H. Bartosik, G. Iadarola, K. Li, L. Mether, A. Romano, G. Rumolo, M. Schenk, G. Arduini ABP information meeting 03/09/2015.
G. Rumolo, G. Iadarola, H. Bartosik, G. Arduini for CMAC#6, 16 August 2012 Many thanks to: V. Baglin, G. Bregliozzi, S. Claudet, O. Dominguez, J. Esteban-
LHC 1 st August :34 Dump on TDI.B2 jaw position while filling –Checks and change TDI.B2 reference position by 0.1 mm outwards 09:40 Lost cryo in.
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Scrubbing Run: TDI, MKI and MKE interlocks Chiara Bracco, Jan Uythoven ABT/BTP Acknowledgments: T. Baer, M. Barnes, E. Carlier.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Saturday 9 th April 10:24 Finally « 600 » bunches 14:30 Dump the 600 x :00 Loss maps Green light for 800 bunches 18:40 Fill for 800 bunches 20:48.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
LHC Scrubbing Run 1 Day 3 (27/06/2015) Scrubbing team 28/06/2015.
LHC report Friday 22 nd June 2016 Coordination: Wolfgang Hofle and Mike Lamont.
Floating MD week 28 summary
Wednesday 8.9 External crossing angles:
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Machine Coordinators: G. Arduini, J. Wenninger
Saturday :12 Stable beams fill 3351 Initial luminosity
Electron cloud & vacuum pressure observations: 2011 proton run
Thursday 25/11/10 & Night Work on: 16:15 Inject fill #1520
Monday :00 Stable beams 9_6_6_6 13:40 Access.
Summary Friday h38: Ramp down and pre-cycle.
LHC Status Wed Morning 13-April R. Assmann, B. Holzer et al
Monday 11/07: Recovery Plenty of accesses.
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Thursday morning – optics correction
LHC Morning Meeting - G. Arduini
Summary of Week 11: 14 – 21 March
Monday – recovery from MKI flashover
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Wednesday 31 October: Morning
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
LHC commissioning Week 38
Summary of Week 16 G. Arduini, J. Wenninger
Note: squeeze in Atlas, CMS, LHCb and Alice on going
Scrubbing progress - 09/12/2012
Scrubbing progress - 10/12/2012
LHC Morning Meeting - G. Arduini
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Friday 14th December - morning
Thursday :00: Physics fill from the night shift
Wire almost entirely through beam before BLM triggers dump
Saturday – Morning 7:36 beams dumped
LHC Morning Meeting - G. Arduini
Sunday
Wednesday 03/11 – The Plan Finish electron-cloud program:
Tuesday morning 09:30 Beam dump, SIS dump due to lost connections with FCG FECs. Coincides with starting a development SIS server to test new interlocks.
Summary Thursday h21: Stable beams fill #1303.
Monday 24 October hours of 25ns MD
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Scrubbing progress - 08/12/2012
IP8 aperture measurements (07:30-10:30)
Monday Fill 1803 into stable beams at 9:30. Dump at 19:45.
LHC - Week 38 Technical stop: Katy Foraz
Wednesday 16th May 03:05 beam dump, RF fault crowbar problem on module M1B2 06:09 Another crowbar at injection. Access for RF; problem Beam Imminent Warning.
Wednesday 23/2 Thanks CRYO!!!.
Fri :52 Stable beams fill #2536
Wednesday 6th April Injection of 50 ns up to 108 bunches (3 x 36).
Wednesday h18: 228b fill lost just before start of ramp.
Another Immortal Fill….
Tuesday 24/5 Fill # :00 Stable beam fill # bunches
Monday 14th May 00:03UFO at BLMQI.06R8.B2E10_MQML. Beam dump Re-steering required for TI2 03:28 STABLE BEAMS # e11 ppb, 4.11e33 cm-2s-1 13:36.
Tuesday 6th April 8:00 Injection studies 16:00 RF studies
Thursday 10:00 Fill 1986 in stable beams.
Tuesday
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Thursday - setup 10:00 Starting pre-cycle. 11:30 Injection. RCBH18.L7B1 has FCGC problem – removed from active set. 11:30 Injection. A few issues with the OFB that seems to use a strange set of correctors – problem of masks – refresh had to be enforced ADT setup starting. 15:00 ADT setup finished with single bunches. Starting setup for 25 ns with 12b injections. Injection lines and ADT. 17:00 72b injections. Beam unstable with Q’ ~ 2. Increased Q’ by 10 units. 17:30 First injections of 144b – dumped after few turns. 7/29/2019 LHC 8:30 meeting

Thursday - setup 17:30 First injections of 144b – dumped after few turns. Increase Q’ to ~15. 18:00 ADT setup for 25 ns: Transfer functions checked. Only minor changes. ADT to remain in wide-band mode. 18:30 Injection of 216b becoming unstable at injection. 19:30 Injection of 288b becoming unstable just after injection. 20:00 Injections up to 288b are ‘clean’, but the beams do not stay in… 7/29/2019 LHC 8:30 meeting

Thursday - scrubbing 20:30 Scrubbing with 72b per beam. 21:20 SIS injection interlock on Wire Positioning System (WPS) L5. Problem on the FEC (power supply). 22:00 Hitting vacuum limit on MKI interconnects (1E-8) for B2. 23:30 Interlock on interconnects vacuum increased to 1.5E-8. TDI LVDT out of tolerance (~20 um only!). Back ok after a cycle. 02:20 Injection of 288b. 02:30 Dump – TDI vacuum reaching 1E-7 – heating. 7/29/2019 LHC 8:30 meeting

LHC scrubbing run (day 1) Beam lifetime improvement observed after injection of ~7 trains (both Beam 1 and 2), it then got better and better during the fill Decision to inject trains closer to each other (925ns spacing), then move gradually to injections of trains of 144, 216 and finally 288 bunches 1596 1524 Pattern of bunch lengths follows that of bunch-by-bunch intensity

LHC scrubbing run (day 1) Limiting factors encountered during the fill 3389: Pressure in the MKI interconnects, M. Barnes raised the thresholds a few times After moving TDI jaws out, some secondary LVDTs are beyond limits for both TDIs (this happened twice, but due to bad configuration of the tool – not a problem because due to heating) Pressure rise in ATLAS (interlock value 4e-7mbar, 1e-7mbar reached!). CMS does not exhibit any pressure rise, but they have the experimental solenoid on. Vacuum at TDI.4L2 rising (VGPB.231.4L2.X.PR), caused manual dump of fill 3389  decision for next fill to keep TDI in IR2 open when filling Beam 2 and TDI in IR8 open when filling Beam 1 + move both out whenever possible

First injection of 288b Losses improving a lot… 7/29/2019 LHC 8:30 meeting

LHC scrubbing run (day 1) Heat load in Sector 56 during fill 3389: Peak value ~28 W/hc to be compared with ~40 W/hc, maximum value reached during 25ns scrubbing in 2011

LHC scrubbing run (day 1) Summary of lifetimes of Fill 3389 Clear improvement for last trains injected Low and slow losses on trains of 288 bunches injected!! Beam1 Beam2

LHC scrubbing run (day 1) Fill 3390  Train of 288 bunches for both Beam 1 and Beam 2, started at about 3:45 after ~1h vacuum recovery Chroma set to 6-7 from the beginning, remeasured with pilots in Injected first two trains for Beam 2, then stop for ~45’ due to MKI interconnect vacuum interlock + RF problem in Ring 4 of the PSB. Good lifetime!

LHC scrubbing run (day 1) Filled with 4 trains per beam, then stopped for a long while due to the high vacuum in ATLAS (above 2e-7mbar!). Possible to inject more after slightly increasing the threshold Also strong heating in Sectors 45 and 78 Machine finally full (beam 1)! 2316 2740

LHC scrubbing run (day 1) Heat load in sector 56 Higher values than ever last year Kept high throughout the fill, ensuring scrubbing efficiency Dumped because of BPMs in IR6, i.e. bunches at the end of trains below detection threshold

Intensity evolution 7/29/2019 LHC 8:30 meeting