CF Scope, Management & Organization

Slides:



Advertisements
Similar presentations
David Saenz FAC CF April 20, 06 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities D. Saenz.
Advertisements

Jess Albino Session 5 Conventional November 11, Facility Advisory Committee LINAC Coherent Light Source Project.
David Saenz Facility Advisory October 30, 2007 CONVENTIONAL FACILITES MANAGEMENT.
1 David Saenz 1 Hutch Construction in FEH June 08, 2009 Hutch Construction in Far Experimental Hall David Saenz – Project Manager.
Jess Albino FAC CF April 16, 2007 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities Jess.
David Saenz FAC CF Oct 12-13, 2004 Conventional Facilities Overview SLAC Site Plan Systems Description Construction Schedule.
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
David Saenz CF Oct 30, CF MEP Commissioning.
David Saenz FAC November 11, 2008 SLAC National Accelerator Laboratory 1 Far Experimental Hutches David Saenz Project Manager.
State of Kansas Statewide Financial Management System Pre-Implementation Project Steering Committee Meeting January 11, 2008.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
Javier A. Sevilla Interface & Configuration FAC Review October 12, Interface and Configuration Management Outline.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
David Saenz FAC Review CF Design, Cost and Schedule Oct 27, 2005 CF Overview & Status Design Status CMGC Status Latest.
David Saenz Readiness for Oct 12, 2006 # Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
David Saenz EIR Review Oct 9-11, Conventional Facilities (CF) WBS 1.9 ETC and Methodology David Saenz CF Systems Manager.
The Contract Management Process Post Award Activities.
Conventional Facilities integration: Approach and Issues Daniel Piso Fernández WP Leader (WP13 Conventional Facilities Integration Support) November 5,
PIP-II Environment, Safety, Health & Quality Assurance Strategy John Anderson Jr. DOE Independent Project Review of PIP-II 16 June 2015.
LS2 Safety Preparation Thomas Otto, LS2 Safety Support Officer for LHC
Director’s Progress Review Closeout Meeting
Installation Procurement Package
Installation Global System
Project Management W. J. Foyt
Meeting of the LCLS Facilities Advisory Committee
Experimental Facilities Planning
Description of Revision
Capital Budget Development
Management Breakout: MREFC Budget Summary Victor L
CF Organization & Schedule
Director’s Progress Review Closeout Meeting
LTU/Undulator Installation Status
Meeting of the LCLS Facilities Advisory Committee
Undulator Scope, Management, and Organization
Linac Ops Budget Structure & Approach WBS 1 – LCLS Mgmt & Admin
Far Experimental Hall Hutches Civil Construction
Far Experimental Hall Hutches Civil Construction
Conventional & Experimental Facilities Dept.
CONVENTIONAL FACILITIES STATUS
Electron Beam Systems ETC and Methodology
Department Of Energy Review LINAC Coherent Light Source Project
X-Ray Endstations Update
Conventional Facilities (WBS 1
Details supporting the increase
CONVENTIONAL FACILITIES LCLS Office Space Procurement
DOE Review of the LCLS Project
Far Experimental Hall - Hutches
Project Management Issues John N. Galayda, SLAC April 24, 2002
DOE Review of the LCLS Project
Conventional Facilities WBS 1.9
Integrated Safety and Environmental Management
EVMS Status and Overview
Conventional Facilities Status
LCLS Injector System Overview D. H
Linac Coherent Light Source (LCLS)
Installation Status & Operational Readiness Process
DOE Review of the LCLS Project October 2006
Preliminary Project Execution Plan
Department Of Energy Review Linac Coherent Light Source Project
Conventional Facilities
Phase 1 Statement of Work Preconstruction “Plan The Work”
DOE Mini-Review of the LCLS Project
Electron Beam Systems ETC and Methodology
LCLS Lehman Review February 7-9, 2005
{Project Name} Organizational Chart, Roles and Responsibilities
LINAC System Engineering / Design Status C.E. Rago
DOE Status Meeting of the LCLS Project
CMGC Overview SLAC Site Plan Systems Description Construction Schedule
Presentation transcript:

CF Scope, Management & Organization General Philosophy CF Scope Documents Meetings CF Management and Organization Summary

General Philosophy CF Group will manage the entire WBS 1.9 design, construction and commissioning in the development and delivery of the LCLS Conventional Facilities CF Group will manage various architectural engineering, consulting firms, Construction Managers and General Contractors with a team approach during Titles I/II and III CF Group will work in collaboration with System Managers and WBS Managers to ensure design requirements are incorporated during construction phase

General Philosophy – cont’d CF Group will ensure best practices are applied using industry standards, past experience, professional knowledge and judgment, and various technologies as recommended or required by Subject Matter Experts, committees, consultants or Advisory Groups CF Group will collaborate with on-site maintenance group (CEF) and LCLS applicable team members during commissioning, punch-list, beneficial occupancy, and certificate of occupancy stages CF Group will aim to provide seamless final integration of commissioning to start up of operations

CF Scope The Conventional Facilities scope for the Linac Coherent Light Source (LCLS) will include renovations to the existing SLAC facilities and the development of new facilities. The scope will include 13 elements: Sector 20 Injector Facilities Magnetic Measuring Facility Main Control Center Modifications Linac Upgrades Beam Transport Hall Research Yard Modifications Undulator Hall Front End Enclosure Beam Dump Near Experimental Hall X-Ray Transport & Diagnostic Tunnel Far Experimental Hall Central Lab Office Complex.

CF Scope – cont’d Activities within these 13 elements include - Site preparation and development (including establishment of survey monuments for site alignment) Beam line housings Beam dump Renovations to existing facilities Buildings Service buildings Utility systems (including cooling systems) Fire protection systems Roads Sidewalks Moderate landscaping

Documents Physics Requirement Document Used to convey the essential physics requirements to CF CF engineers utilize this document as the basis of their designs Example: “UH shall extend 175 meters in the direction of the beam.” “Max. air temp deviation ±0.2°C” Engineering Specifications Document Room Data Sheets used to identify specific engineering details CF engineers utilize this document as a supplement to the PRD and to provide specific details of the item they have designed so that AE firms can meet the design criteria Example: equip power loads, utility flow reqt’s, i.e. temp, pressure, etc Interface Control Document Used to specify in detail all interfaces between internal LCLS systems and non-LCLS groups Status All required documents are not at equal status in terms of completion. A complete development of these documents must be accomplished. This assignment will be a priority to the new CF engineer expected to be hired in the next 4-6 weeks

Meetings CF group meetings or those related to management meetings occurring every week CF/SLAC ESH Biweekly Meeting – Wednesday 10:30 to coordinate requests and issues regarding ESH support CF Sys Mgr LCLS ESH Coordinator SLAC ESH “LCLS Liaison” ESH Group Leaders LCLS CF/JE Title II Weekly Update – Tuesday 11:00 to discuss top 3 priorities by discipline, i.e. struct, mech, elect, etc CF Key Personnel LCLS Key Personnel JE Team Leaders via teleconference LCLS Monthly Risk Management Meeting - 2nd Wednesday of every month WBS managers and System managers are present with the project office and LLNL/APS via teleconference for meeting LCLS Cost and Schedule Performance Meeting - 4th Wednesday of every month All WBS managers and their CAMS are present via teleconference/net meeting for meeting with the project office CF Group - Monday 8:00 meeting to review past weeks accomplishments, upcoming tasks, identify potential issues or show stoppers System Mgr CAM’s UTR’s Project Controls Procurement CF Sys Mgr and Project Controls – Monday 9:30 meet every week to discuss WBS cost and schedule status, BCR’s, monthly accruals, invoices, 6 month look ahead schedule, CPI, etc CF Sys Mgr and SLAC’s Conventional Experimental Facilities group (CEF) Dept Head – Monday 10:00 to review status of support effort for internal service requests, ex. LCLS/CEF Service Request Report CF Sys Mgr and RSYWG – biweekly (Mondays) Review status of activity in RSY Report on upcoming impact to RSY LCLS Management Meeting - Tuesday 10:00 meeting WBS managers and System managers are present with the project office and LLNL/APS via teleconference for meeting

LCLS/CEF Service Request Report Assigned to… Need By Received Into System

CF Organization FY 05

CF Organization FY 06-08

JE ORG

Summary General Philosophy Scope Management Organization CF Group will provide seamless integration from commissioning to start up of operations Scope The CF scope is clearly defined Management Tools are in place such as PRD’s, ESD’s, ICD’s, regular management meetings, and reporting documentation to ensure project delivery on time and within budget Organization Most critical key positions have been filled, employee requisitions in place for remaining personnel LCLS/SLAC organization integration has been strengthened but will still need additional fostering in collaborative areas

End of Presentation