XRN Nov 19 Release - Status Update

Slides:



Advertisements
Similar presentations
XRN4361 – UK Link Release 2 - Delivery
Advertisements

XRN4572 – UK Link Release 3 - Design
Overall Project RAG Status
DSC ChMC CSS update 13th June 2018
Overall Project RAG Status
Overall Project RAG Status:
Release 3 Update December 2018.
XRN4340 – UK Link Future Release 1.1
Overall Project RAG Status
R&N Timeline Release 2 Release 3 Feb-19 June-19
Release 3 Update November 2018.
XRN4361 – UK Link Release 2 - Delivery
EUC Project Timelines Key Upcoming Dates:
XRN4361 – UK Link Release 2 - Delivery
Overall Project RAG Status
XRN4361 – UK Link Release 2 - Delivery
Release 3 Update 9th January 2019.
Overall Project RAG Status:
R&N Timeline June-19 Sept-19 (EUC) Nov-19 Minor Release D4
xrn4340 – UK Link Future Release 1.1
Release 3 Update 13th February 2019.
XRN4534 Deployment Options December 2018
Potential Minor Release Drop 4 Timeline & Scope
DSC ChMC CSS Consequential Update 13th March 2019
Overall Project RAG Status:
XRN Nov 19 Release - Status Update
XRN Nov 19 Release - Status Update
June 19 Timelines Key Upcoming Dates:
4361 – UK Link Future Release 2
Release 3 Scope & Proposed Plan
Change Management Committee – Retail & Networks Update
XRN4361 – UK Link Release 2 Project Status Update
Overall Project RAG Status
Minor Release Drop 3 Timeline
4361 – UK Link Future Release 2
4340 – UK Link Future Release 2
Overall Project RAG Status:
Overall Project RAG Status:
XRN4361 – UK Link Future Release 2
Overall Project RAG Status
XRN June 19 Release - Status Update
XRN Feb 19 Minor Release - Status Update
June 19 Timelines Key Upcoming Dates:
XRN4361 – UK Link Release 2 - Delivery
XRN Nov 19 Release - Status Update
XRN4361 – UK Link Release 2 - Delivery
Retail & Networks ChMC Update
XRN4361 – UK Link Release 2 - Delivery
Overall Project RAG Status:
XRN November 2019 Release - Status Update
4340 – UK Link Future Release 1.1
XRN Nov 19 Release - Status Update
UIG Task Force Progress Report
XRN June 19 Release - Status Update
Potential Minor Release Drop 4 Timeline & Scope
Minor Release Drop 3 Timeline
XRN4361 – UK Link Release 2 - Delivery
UK Link Timeline June-19 Sept-19 (EUC) Nov-19
UIG Task Force Progress Report
UK Link Change Impacts and Release Update
XRN 4954 – MiR Drop 5 - Status Update
XRN 4927 – MiR Drop 4 - Status Update
Overall Project RAG Status:
XRN June 19 Release - Status Update
XRN June 19 Release - Status Update
XRN Nov 19 Release - Status Update
XRN4361 – UK Link Release 2 - Delivery
7.1 XRN4665 End User Categories (EUC) – Project Update
UIG Task Force Progress Report
UIG Task Force Progress Report
Presentation transcript:

XRN4828 - Nov 19 Release - Status Update 10th July Overall Project RAG Status: Schedule Risks and Issues Cost Resources RAG Status Status Justification Start Up and Initiation phases complete Detailed Design commenced on 17th June, design workshops complete with phase on track to complete by 12th July Build to commence w/c 1st July Test plan and scenarios under review Funding: BER for full delivery approved in April 2019, BER for XRN4866 UIG Recommendation approved at ChMC on 12th June. Risk: There is a risk that the Nov 19 Release may be impacted by Pre-Production environment congestion due to multiple deliveries running in parallel Risk: There is a risk that due to multiple UKLink deliveries running in parallel there may be limited access to resources. The BER with full delivery costs were approved at ChMC in April 2019, BER for XRN4866 UIG Recommendation approved by ChMC on 12th June Weekly monitoring of Xoserve SME resources supporting multiple demands (e.g. BAU defects, Future Releases etc) is ongoing

XRN4828 - Nov 19 Release Timelines Key Milestone Dates: Design Completion – 12/07/19 Build & Unit Test Completion – 02/08/19 System & UAT Completion – 27/09/19 Regression Test Completion - 11/10/19 Implementation – 08/11/19 TBC PIS Completion – 06/12/19 2019 Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec XRN4828 Nov-19 HLD & Change Pack Production Design Build & FUT ST & SIT UAT RT PT Test Cont. IDR PIS GO LIVE 08/11/19 - TBC 04/02: EQR Approval 10/04: BER Approval 08/05: Change Pack Approval