LHC Morning Meeting - G. Arduini

Slides:



Advertisements
Similar presentations
The ATS MD part III (Achromatic Telescopic Squeezing scheme) Participants: Any (active) volunteers Goal: 1)MD1 (S. Fartoukh & R. Assmann  10h): “Pre-squeeze’’
Advertisements

● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
Plan for start-up with beam Friday  19:00 Machine closed. Ramp for powering tests & pre-cycle  22:00 Pilots through nominal cycle up to collisions. Measure.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
:30 meetingEBH 1  4:14 lost cryo conditions in Sector 34/45 due to communication problem  6:30 Faulty IT network switch identified  access.
:00 meetingEBH 1  8:40 – 9:30 access for MKB (dilution kicker) LBDS B2 – PLC exchange  Pre-cycle  11:17 – 12:50 RF problem with ion injection.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
LHC Status Sat Morning 30-June Bernhard Holzer, Jan Uythoven Status Friday Late: preparing restart some issues... LHCb dipole tripped / router problem.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Ion Commissioning: Thursday & Friday
Wednesday
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
MD Planning Fri – Sat (26. – 27.8.)
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Saturday 24 March 2012.
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Monday 14th March Second fill with pilot + 3 nominal bunches
Coordination: G. Arduini, E.B. Holzer, J. Jowett
LHC Progress Week 6 Coordination: G. Arduini, E.B. Holzer
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
LHC Morning Meeting - G. Arduini
Machine availability reaching well over 80%
Tuesday TOTEM and transverse loss map (1) OK
Summary of Week 11: 14 – 21 March
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
LHC Morning Meeting - G. Arduini
Summary of Week 13 G. Arduini, B. Holzer
LHC commissioning Week 38
Lost at 12:05 to power converter (RTQX2.R1) problem
Wed :40 Lost S78 - QPS controller.
Saturday 2/4/ :00-09:00 Problems with SPS:
Week 36 plan Todo’s: And also: 12+b injection.
Week 35 – Technical Stop and Restart
Week 36 Machine coordinators R.Assmann, R.Bailey
Planning at 5 o’clock meeting Friday
Friday morning 10:30 Optics measurements and corrections.
LHC Morning Meeting - G. Arduini
Wednesday 09 March …:09:00: beta* measurement (1.5 m) by K-modulation and with AC-dipole excitation. 1/17/2019 LHC 8:30 meeting.
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Saturday 7th May Sat – Sun night
Friday 23rd March 08:00 Access
Progress with Commissioning the first LHC p-Pb run
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Monday :20 beta beat corrections during squeeze for flat machine finished Afterwards fixing issues at injection: BPM rephrasing for B2 solved.
Wednesday 13th 9:30 Stable Beams… with 1 pilot and 2 nominals
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Sat morning Until 12:40: Loss maps at injection
Collimation qualification during the first weeks of the 2011 run
Summary for LPC (March 7th, Ralph Assmann)
Saturday :42 stable beams fill 3541
Monday :15 fill 3523 dumped by BPMs IP6
Plan for 1 m b* J. Uythoven & J. Wenninger
Saturday 12 March Morning: problem on RSD1.A12B2 – flow rate problem on the cooling water for the converter. 14:00: Loss map -500 Hz (positive energy offset)
LHC Morning Meeting - G. Arduini
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Saturday 06/11 Triplet R8 tripped during ramp for collision setup.
Wednesday h18: 228b fill lost just before start of ramp.
Tuesday – Morning and Evening
Another Immortal Fill….
Monday 14th May 00:03UFO at BLMQI.06R8.B2E10_MQML. Beam dump Re-steering required for TI2 03:28 STABLE BEAMS # e11 ppb, 4.11e33 cm-2s-1 13:36.
Tuesday
Daniel, Gianluca and Belen (for the Collimator team)
HI2011 Commissioning Status
Saturday Morning used to complete the loss maps and asynch dumps (with RPs). All loss maps OK (B. Salvachua), but the off-p cleaning for B1 (Lead) was.
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

LHC Morning Meeting - G. Arduini Thu 17/1 Cryo back at 06:00 7:20 Injection Some difficulties to get stable bunch intensity from the injectors and to measure chromaticity. After having injected pilots we start to inject bunches of 3x1010 p and we start to get bad readings from some BPMs. No improvement after re-phasing. This is not good! 07/08/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Thu 17/1 …even worse if we go with low sensitivity settings… For this fill we gate the orbit acquisition on a single pilot bunch (synchronous acquisition). Not acceptable for multi-bunch schemes with proton bunches of more than 1.5x1010 p. Not evident to increase the proton intensity later… 07/08/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Thu 17/1 12:18: Beginning ramp 12:30: end of ramp. Orbit not very good. Likely because of the losses on the pilot bunch 07/08/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Thu 17/1 14:00 Decided to scrape the beam down to ~1-1.5x1010 p/b and go ahead with programme 15:00 first set of loss maps completed 16:00 Collimator alignment in point 7 completed 17:30 second set of loss maps completed 07/08/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Thu 17/1 Loss maps before and after alignment are consistent and the observed collimator aperture centres are consistent with previous ones (within tolerances) except for 1 collimators. Being checked. G. Valentino Collimator March January Delta (mm) TCSG.4R6.B1 0.125 0.405 -0.28 TCP.D6L7.B1 0.240 0.200 0.04 TCP.C6L7.B1 -0.178 -0.225 0.047 TCP.B6L7.B1 -0.320 -0.340 0.02 TCSG.A6L7.B1 -0.078 -0.148 0.07 TCSG.B5L7.B1 -0.375 -0.455 0.08 TCSG.A5L7.B1 -0.240 -0.190 -0.05 TCSG.D4L7.B1 -0.070 -0.073 0.003 TCSG.B4L7.B1 0.845 0.803 0.042 TCSG.A4L7.B1 0.835 0.783 0.0525 TCSG.A4R7.B1 0.693 0.768 -0.075 TCSG.B5R7.B1 0.370 0.305 0.065 TCSG.D5R7.B1 -0.228 -0.280 0.052 TCSG.E5R7.B1 0.020 -0.040 0.06 TCSG.6R7.B1 -0.233 -0.263 0.03 TCLA.A6R7.B1 0.328 0.228 0.1 TCLA.B6R7.B1 -0.353 -0.415 0.062 TCLA.C6R7.B1 1.443 1.283 0.16 TCLA.D6R7.B1 -0.270 0.045 TCLA.A7R7.B1 -0.418 -0.465 Collimator March January Delta (mm) TCP.D6R7.B2 0.770 0.703 0.067 TCP.C6R7.B2 0.520 0.618 -0.098 TCP.B6R7.B2 -0.235 -0.208 -0.027 TCSG.A6R7.B2 0.075 0.040 0.035 TCSG.B5R7.B2 0.315 0.138 0.177 TCSG.A5R7.B2 0.540 0.438 0.102 TCSG.D4R7.B2 -0.150 -0.170 0.020 TCSG.B4R7.B2 -1.058 -1.228 0.170 TCSG.A4R7.B2 -0.735 -0.895 0.160 TCSG.A4L7.B2 -0.760 -0.825 0.065 TCSG.B5L7.B2 0.388 0.132 TCSG.D5L7.B2 -0.240 -0.265 0.025 TCSG.E5L7.B2 -0.115 0.150 TCSG.6L7.B2 -0.128 -1.028 0.900 TCLA.A6L7.B2 0.338 0.341 -0.003 TCLA.B6L7.B2 0.113 -0.105 0.218 TCLA.C6L7.B2 0.805 0.810 -0.005 TCLA.D6L7.B2 0.188 0.260 -0.072 TCLA.A7L7.B2 0.688 0.765 -0.077 TCSG.4L6.B2 -0.188 -0.11 -0.078 07/08/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini 17:47 Squeeze in one go completed chromaticity at the beginning and end of the squeeze now at ~3-5 units. Corrected to 3 units. Tune feedback corrections during the squeeze fed forward in the tune trim functions 18:00-24:00 IR2 aperture measurements 07/08/2019 LHC Morning Meeting - G. Arduini

Aperture measurement IP2 RB, MG, PH, LL, DM, SR, MS, RV) We measured the aperture in IR2 for both beams and planes at the end of the squeeze with separated beams. We used the method of TCT scan + orbit bumps: after centring the TCTs (beam-based alignment around the reference orbit), we added orbit bumps to the orbit and increased the TCT gap until the triplet aperture was exposed. For the different planes/beams, we found the following on-momentum apertures: B1 - V (crossing) : 14.0-14.5 sigmas B2 - V (crossing) : 13.5-14.0 sigmas B1 - H (separation) : > 14.0 sigmas B2 - H (separation) : > 14.5 sigmas For the case B2-V we re-measured the aperture for both off-momentum signs (with off-momentum beta-beat correction knob active). We found that for the negative dp/p case we lose 0.5 sigmas whereas we lose nothing for the positive dp/p case. In conclusion, these apertures are fine for the operation at 80 cm. These preliminary results will have to be confirmed by loss maps after detailed TCT setup. 07/08/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini 01:45-05:30 Steering RF capture Issues with the FBCT reading B1 07/08/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Bunch length (long blow-up left off for B1 on purpose) Centred orbits at flat-top 07/08/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Cogging done without problems Still Beam 2 losses at TCTs in point 2 during the squeeze (to be set-up). 07:20 Looking for collisions 08:30 So far only LHCb missing 07/08/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Plans Collisions to be found If OK: One ramp for TCT and Roman pot (vertical) alignment (~10 h) At least 4 more ramps for validation (~12 h) Validations at injection (~2 h) Still pending: check of the inejction of trains (2 h). Likely after the first alignment shift 07/08/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Validation Injection (Inj. Prot. IN) Injection (Inj. Prot. OUT) Flat-top Squeezed, separated Squeezed Collision Betatronic-H tbd Betatronic-V Neg. off-mom -- tbd (+500 Hz) Pos. off-mom tbd (-500 Hz) Asynch dump tbd=to be done 07/08/2019 LHC Morning Meeting - G. Arduini