Friday h55 Stable beams. Fill #1841. Lumi ~1.2e33.

Slides:



Advertisements
Similar presentations
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
Advertisements

Saturday 7ish – refill for RP set-up 9:15 Going for Roman pot alignment. Stefano is coming. 12:10 TOTEM: Alignment of horizontal RPs B2 finished, short.
Monday :00 Injection for physics fill # :00 Stable beams fill #1816, luminosity ~1.2x1033 cm-2s-1 11:08 Beams dumped. QPS trigger on detector.
08h15: Injection.  Correction injection oscillations.  Transfer line steering.  Losses at 30% of dump threshold, limited by SPS scraping. 12h35: Start.
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
LHC Status Fri Morning 3-June
Friday 15th June 01:11 Injection.
Wednesday September 14th
Monday :00 Stable beams 9_6_6_6 13:40 Access.
Friday 30th September 06:00 Operator dump fill #2171, int. lumi about 75 pb-1 Previous operator dump from physics was on 14 September ! 07:00 Start of.
Tuesday Fill lost #1855 at 7:28 due to the trip of RQX.R1. This was traced to a software bug in the FGC… The Class 51 (LHC_PC) FGC software has been upgraded.
Wed :55 Fill 2653 stable beams 1.40e11 ppb, cm-2s-1peak lumi, 11.6 pb-1 total lumi delivered. 09:31 Dumped by collimator interlock:
Tuesday Nov 16th Fill 1492 into physics around 07.30
Monday fill with 1092 bunches (6 h stable beams)
Wednesday 17th August Rocky, short fills, initial luminosities are good LHCb polarity change to negative seems ok 18/08/2011 LHC 8:30 meeting.
LHC Morning Meeting - G. Arduini
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Saturday 12:00 Fill 1992 in stable beams.
LHC Morning Meeting - G. Arduini
Summary of Week 11: 14 – 21 March
LHC Status Su Morning 17-April R. Assmann, B. Holzer et al
Fri 29/7 – Sat 30/7 09:00 End of fill 1990, PC trip RCBXV3.R1 (likely SEU on QPS). Integrated Luminosity: 41 pb-1. Access for MKI2 main switch replacement.
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Summary of Week 16 G. Arduini, J. Wenninger
Lost at 12:05 to power converter (RTQX2.R1) problem
Friday 31st August & night
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
LHC Operations overview Week 28 – Getting back
Sunday morning Recovering from 400 kV disturbance.
Monday Morning – recovery from cryo.
Chromaticity can make a difference…
Friday 11/5 08:00 RF communication problem solved. Ready to inject but beam not available from the injectors. Injection line collimators opened from 4.5.
Friday :00 machine setup for luminosity run. Better b-to-b stability from injectors. 01:58 stable run with 228 bunches 11:00 luminosity leveling.
Friday morning 10:30 Optics measurements and corrections.
Saturday – Morning 7:36 beams dumped
Finally.... We had to wait a long time.... We had many problems....
Friday Morning 7:30 injection for fill 2908
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
Wednesday 9:08 Fill 3214 dumped by OP after 5:26 hours in stable beams
LHC Morning Meeting - G. Arduini
Summary Thursday h21: Stable beams fill #1303.
Wednesday 10/5 Cryo recovery until 18:30
Sunday/Monday & :30 Stable beams. Fill #1851.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Aims for the week Recover from technical stop and precycle at 10A/s
Monday 14:00 beam dump Access:
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
Tue/Wed 12/ :00 Probe beam back again
Thursday – Morning Energy matching at injection with H CODs
Fill 1743 Peak luminosity ~6.7 e32 Integratated lumi ~20 pb-1
Monday 6th 07:39 Dump fill #1854, RQ6.L2 tripped, followed by access
Monday Fill 1803 into stable beams at 9:30. Dump at 19:45.
Friday morning 08:00 Stable beams with 840b.
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Wednesday 6th April Injection of 50 ns up to 108 bunches (3 x 36).
Saturday 24 September 2011.
Saturday 06/11 Triplet R8 tripped during ramp for collision setup.
Coordination: Eva Barbara Holzer, Mike Lamont
Wednesday h18: 228b fill lost just before start of ramp.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Tuesday 24/5 Fill # :00 Stable beam fill # bunches
Wednesday 14:30 Fill 2011 dumped.
Saturday 28th 08:17 Fill #1812: Stable beams, peak luminosity ~1.1x1033 cm-2s-1 19:00 Go to adjust for RF-checks; Record fill lumi of 31.7 pb-1 for CMS.
Friday During the night from Thursday to Friday: by mistake, SPS longitudinal blow-up was not active  Smaller transverse emittance from the.
Saturday 26 November 2011.
Thursday 10:00 Fill 1986 in stable beams.
Sunday 12th 00:29 Stable beam fill #1864. Initial lumi 1.1e33
Wednesday 8th (I) 09:22 Fill #1855. Beams dumped by Alice dipole trip Stable beams for 10.5 hours; int. lumi 31 pb-1 After investigation EPC could not.
Tuesday
Presentation transcript:

Friday 03.06. 05h55 Stable beams. Fill #1841. Lumi ~1.2e33. 13h30 Beams dumped: Loss of I_meas reading (only channel A of PC) for 4 ms. This tripped the PIC. Note that the after the loss of I_MEAS, the signal came back. Delivered lumi: 27.5pb-1. Length of stable beams: 7h35. 18h24 Beam dump @3.5TeV: UFO in IR8R during squeeze. 20h54 Stable beams. Fill #1844. Lumi ~1.1e33. 21h17 Beam dump: Undulator IR4 tripped. Reset was needed (forgotten before). Length of stable beams: 0h23. 23h30 Cryo back for ML4. 02h16 Stable beams. Fill #1845. Lumi ~1.1e33. 07h56 Beam dump: QPS FIP comm. lost. S12 tripped. 04/06/2011 LHC 9:00 meeting

Ongoing injection problems Consistent problems after long fills: First filling attempts after long fills hit by strong emittance blow-up: ~100%. Blow-up happens a few seconds after injection. Seen as beam instability. Not all batches affected. Some good, some bad. Seeing drifts in chromaticity at flat bottom after long fills. Not understood. Possible actions: Update Fidel model to take into account better long powering history. Full pre-cycle after long fill. Check for the hump. Is it back? Tails beneficial for Landau damping  less scraping in SPS? Last fill with larger emittances (less scraping) went without problem, but also benfited from earlier short fills. 04/06/2011 LHC 9:00 meeting

Chromaticity Drift 04/06/2011 LHC 9:00 meeting

Vertical Blow-up B2 04/06/2011 LHC 9:00 meeting

Length Stable Beams: 9 this week so far Fill Length 1816 09h00 1822 00h27 1823 01h13 1835 01h06 1836 14h55 1839 00h04 1841 07h35 1844 00h23 1845 05h40 40h23 Average length stable beams: 4.5 h 04/06/2011 LHC 9:00 meeting

Beam Dumps at > 450 GeV Date Time State Reason 30/05 11h08 Stable beams QPS trigger circuit detector of RCBXH2.L1. SEU? 15h43 Adjust New RF interlock not masked 20h20 FMCM. Electrical glitch 31/05 06h22 UFO IR2L 10h38 Communication with DFBAJ. SEU? 22h20 Squeeze 01/06 02h10 QPS trigger (Quench of Q9R5 ?) 06h53 RF trip (radiation-induced arc detector signal?) 09h17 Ramp Collimator temperature 20h37 Collimation crate IR5R failure (PRS) 02/06 16h58 Beam dump EIC 21h50 UFO IR8 03/06 00h28 Trip of RQTF.A23B2 13h30 Loss of I_meas reading 18h24 UFO in IR8R 21h17 Trip undulator IR4. 04/06/2011 LHC 9:00 meeting

UFO’s 2.6. 5 MKI R8 1 MKI L2 04/06/2011 LHC 9:00 meeting

3 MKI L2 4 MKI R8 04/06/2011 LHC 9:00 meeting

Injection Kicker Temperatures 04/06/2011 LHC 9:00 meeting

Luminosity Production 04/06/2011 LHC 9:00 meeting

Ahead Physics fills continued (1092 x 1092 bunches, 108b injections). Average bunch intensity: ~ 1.2e11 p End of fills (if any): Try to reduce DS losses with TCL collimators (open now) RF cavity switch off test 04/06/2011 LHC 9:00 meeting