Tuesday Access…. QPS intervention at 09:00 in point 8 (quench heater exchange) QPS installation oscillo for the ISRM measurement EPC intervention in point.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

LHC 14 & 15 April :22: Ramp to 6.5 TeV lost due to MUFO, resulting in quench 10:30: Access during cryo recovery 16:00: Pre-cycle 17:05: RB.A78 short.
05:31 Beam dump due to QPS trigger in sector 78.  Quench heaters discharged in MB10.L8. 07:28 Quench heaters charged ok again in cell B10L8.  Was a EN/EL.
RF observation from Saturday morning Observation of beam induced voltage/power following the two klystron trips: 03:18 3B1 just at end ramp, 1.26E14 p.
LHC status Wednesday 15 th July 2015 Coordination: Wolfgang Hofle, Mike Lamont.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
08h15: Injection.  Correction injection oscillations.  Transfer line steering.  Losses at 30% of dump threshold, limited by SPS scraping. 12h35: Start.
04:01 Injection kicker timing problems B2  Injection pre-pulse shifted, causing BETS to inhibit beam injection. 144 bunches on TDI.  Run without ROF.A81B2.
:00 meetingEBH 1  6:39 beam dump by BLM 655ms RS on BLMEI.05L4.B2E10_MBRB (which is downstream of BSRT B2).  The losses increased during.
Wednesday 5 th December until this morning 06:59 Stable beams fill #3375, L ~ 6.8e33 cm-2s-1. 10:40 Beam dump, trip of RD2.R5. Integrated L 72 pb-1 in.
LHC status Friday 11 th September 2015 Coordination: Mike Lamont, Jorg Wenninger.
Monday – Morning L. Drosdal: Injection line TI8: IQC threshold for BPM H from 2mm to 2.5mm to avoid unnecessary latches due to variations.
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Last 24 hours RQ4.L1 Lost going into collision Test ramp Storm
Summary Week 47 + Start Week 48
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Tuesday 11th September LHCb dipole presently fault off
LHC Status Wed Morning 13-April R. Assmann, B. Holzer et al
Monday 11/07: Recovery Plenty of accesses.
Thursday 09:30 VdM scan for CMS, standard ADT gain.
Summary week 23 Luminosity production
Last 24 hours RQ5.L1 RQ4.L1 RF trip Line4B LHC status.
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Tue :25 Beams dumped due to RF vacuum interlock
LHC Morning Meeting - G. Arduini
Saturday 12:00 Fill 1992 in stable beams.
Thursday morning – optics correction
LHC Morning Meeting - G. Arduini
Fri 29/7 – Sat 30/7 09:00 End of fill 1990, PC trip RCBXV3.R1 (likely SEU on QPS). Integrated Luminosity: 41 pb-1. Access for MKI2 main switch replacement.
Tuesday 08:30 Fill 2700 dumped by QPS on RCBXH2.L1
Wednesday 31 October: Morning
Tuesday Fill 1494 dumped by operations at (~ 0.25 ub-1 in ~6.5 h): LSS6 BPM interlock test 13:00 Fill 1495 dumped by RF dump (cavity quench) 14:00-17:30.
Note: squeeze in Atlas, CMS, LHCb and Alice on going
LHC Morning Meeting - G. Arduini
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Wire almost entirely through beam before BLM triggers dump
Tuesday 22 November 2011.
Thursday morning 7:20 – 12:30 faults of BLM sanity check, RQX.L8 QPS trip and iris scanner in UJ47. Access: Pt 8 for ELQA on RQX.L8 (The voltage.
Aims for the week Recover from technical stop and precycle at 10A/s
Monday 24 October hours of 25ns MD
LHC Morning Meeting - G. Arduini
Monday 14:00 beam dump Access:
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Saturday 3rd November - morning
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Friday 8/10/10 - Morning Planned to keep fill until the afternoon
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Monday Fill 1803 into stable beams at 9:30. Dump at 19:45.
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Summary Tuesday h23: Machine closed. Precycle started.
Sat 15/10 New record bunch population profiting of the scrubbing period on Friday. Nb~1.42x1011p/bunch  110 MJ at 3.5 TeV. Filling slowed down by ZS sparking.
Saturday 24 September 2011.
Coordination: Eva Barbara Holzer, Mike Lamont
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Thursday 20th July - morning
Monday 27th August & night
Wednesday 26 October 2011.
Wednesday 14:30 Fill 2011 dumped.
Wednesday morning / afternoon
Wed 12/10 09:30 – 10:30 Ramp down of ALICE solenoid to 50% nominal field on request of ALICE. Increase of the vacuum (e-cloud in this area that has not.
Wednesday 6.10 Morning: Quench test at 450 GeV
Saturday 26 November 2011.
Thursday 10:00 Fill 1986 in stable beams.
Wednesday 8th (I) 09:22 Fill #1855. Beams dumped by Alice dipole trip Stable beams for 10.5 hours; int. lumi 31 pb-1 After investigation EPC could not.
Wednesday Following the struggle with the vacuum in IR2 over the night, drop intensity to 1.2E11/bunch. Fill first B1 – pretty quiet – then B2 – quite.
Tuesday
Presentation transcript:

Tuesday Access…. QPS intervention at 09:00 in point 8 (quench heater exchange) QPS installation oscillo for the ISRM measurement EPC intervention in point 4 (60 A module in S34) aperture Kicker intervention in point 4 MKI AGK delay in point 8 vacuum recabling in point 2 vacuum : BPM cabling in point 8 CNGS in point 8 BI in UA43 for dev BBQ UX65 for RADMON installation UW25 : inspection from CV 8/26/2019 LHC 8:30 meeting

Frozen DFB in point 3 Insulation vacuum of DFBLC connection to the WRL was abnormally poor. When the pump was restarted and the valve towards the insulation vacuum was opened, the pressure raised from 1e-8 to few e-5. The ice was removed and the vacuum pumped back down to a good level. 8/26/2019 LHC 8:30 meeting

Tuesday-Wed Morning: ISRM tests on RQ4.L8 and RQ6.R8 00:00 Precycle. Injection a bit rocky – 50 ns quality not at its best (int. spread) – lot’s of injections blocked by SPS BQM. + steering of TI8. Lifetime dip when bringing into collisions – 4 hours – and losses in IR7 to 67% of threshold (on B1 monitor from B2 losses). 04:20 Stable beams fill 2204, 3.3E33 cm-2s-1. 8/26/2019 LHC 8:30 meeting

Lifetime & losses 8/26/2019 LHC 8:30 meeting

Today Stable beams. ALICE reduced field test. Abort gap at end of fill? 8/26/2019 LHC 8:30 meeting